We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
On July 6, 2009 a limited Phase II Environmental Site Assessment was conducted on a vacant lot. DRO, arsenic, chromium above DEC cleanup concentrations were detected in sub-surface soil. RRO and other metals were detected, but below cleanup levels. The source of contamination is believed to be contaminated fill material.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
8/5/2009 | Site Added to Database | A new site has been added to the database | Mitzi Read |
8/5/2009 | Exposure Tracking Model Ranking | Initial ranking with ETM completed for source area id: 78805 name: Contaminated Fill Material | Mitzi Read |
8/25/2009 | Update or Other Action | Grant Lidren assigned as ADEC project manager for this site. | Linda Nuechterlein |
8/25/2009 | Document, Report, or Work plan Review - other | ADEC received Limited Phase II Environmental Site Assessment, 110 Bartel Avenue, Kodiak, Alaska, submitted by Shannon & Wilson, dated July 22, 2009. The area is suspected to contain areas of fill from an unknown source. Four test pits were advanced, TP1-TP4, in areas that were suspected of fill material, to a depth of 4.5 ft. bgs(@ TP4)to 9.5 ft. bgs( @ TP1)depending on where the groundwater interface was encountered. Soil samples were collected at 2 ft. intervals. An analytical soil sample was collected from each test pit from the location of the highest pid reading. A soil sample collected from TP3 at a depth of 2 to 3 ft. bgs contained DRO up to 268 mg/kg. A soil sample collected from TP1 at a depth of 4 to 5.5 ft. bgs contained arsenic up to 12.1 mg/kg and chromium up to 30.4 mg/kg. Note: the benzene reporting limit for samples TP3 and TP4 were greater than the ADEC cleanup level of 0.025 mg/kg. | Grant Lidren |
11/2/2011 | Update or Other Action | Phone conversation with the landowner Legacy LLC on this date. Legacy LLC has no immediate plans to develop the property. When/if Legacy LLC develops the property they will need to contact ADEC. | Grant Lidren |
12/9/2011 | Potentially Responsible Party/State Interest Letter | PRP letter sent to Legacy LLC on this date | Grant Lidren |
6/27/2014 | Exposure Tracking Model Ranking | A new updated ranking with ETM has been completed for source area 78805 Contaminated Fill Material. | Joshua Barsis |
8/14/2014 | Cleanup Complete Determination Issued | Cleanup complete issued on this day. | Joshua Barsis |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
DRO | Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation | Soil |
Control Type
Type | Details |
---|---|
No ICs Required |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. |