Action Date |
Action |
Description |
DEC Staff |
11/5/2009 |
Spill Transferred from Prevention Preparedness and Response Program |
Spill transferred by PERP staff Brian Jackson. Spill no. 09309918902; spill date = 7/8/09; substance #2 diesel; quantity = ~500 gallons. |
Mitzi Read |
11/20/2009 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
12/2/2009 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 78828 name: Day Tank Overfill |
Mitzi Read |
1/28/2015 |
Final Cleanup Report Reviewed |
Soil removal actions were conducted in 2009. Contamination extended to the water table. Free product recovery efforts continued until recovery was no longer feasible. Contamination likely extends under the pump house. No groundwater data was evident in the file but residents in the area are on city water. Exposure or subsurface soil may still be a concern if excavation were to occur in the future. Site closure with Institutional controls might be possible if groundwater was evaluated. |
Kim DeRuyter |
1/28/2015 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78828 Day Tank Overfill. |
Kim DeRuyter |
3/29/2017 |
Update or Other Action |
Contacted City Manager for update on site progress |
Jim Fish |
7/11/2017 |
Update or Other Action |
City has contracted with consultant to review data gaps and propose a course of action for site closure. |
Jim Fish |
2/21/2018 |
Update or Other Action |
Received contractor scope of services from City Manager; work plan for well installation and groundwater monitoring pending. |
Jim Fish |
2/26/2018 |
Meeting or Teleconference Held |
Teleconference held to discuss work plan development with City NP staff and consultant |
Jim Fish |
3/23/2018 |
Document, Report, or Work plan Review - other |
Work plan monitoring well installation & sampling approved |
Jim Fish |
4/25/2018 |
Document, Report, or Work plan Review - other |
Revised location of eastern monitoring well (moved because of utility locates) discussed and approved today; final revised work plan received. |
Jim Fish |
7/25/2018 |
Document, Report, or Work plan Review - other |
Received 2018 groundwater monitoring well installation and sampling report. Petroleum hydrocarbons were detected at concentrations above ADEC cleanup levels in both soil and groundwater at all three well locations (MW18-01, MW18-02,and MW-01). Consultant recommends additional delineation. |
Jim Fish |
4/22/2019 |
Update or Other Action |
Received draft work plan for additional site characterization - soil borings, groundwater sampling, groundwater elevation, soil gas sampling, and possible VI evaluation in residential buildings (if warranted). |
Jim Fish |
5/2/2019 |
Update or Other Action |
Received responses to work plan questions - two monitoring wells will be installed down-gradient of the pump house in 2019 (DEC had recommended additional delineation of groundwater using temporary well points); an assumption is being made that contamination exists beneath the building, but no assessment of vapor intrusion risk is being proposed at this time (although it is acknowledged as an open pathway in the CSM), instead assessment of vapor intrusion risks is being proposed for down gradient residences. |
Jim Fish |
5/21/2019 |
Document, Report, or Work plan Review - other |
Work plan approved (additional monitoring well installation was included down-gradient of the pump house). |
Jim Fish |
4/14/2020 |
Document, Report, or Work plan Review - other |
Received 2019 Site characterization report |
Jim Fish |
8/14/2020 |
Document, Report, or Work plan Review - other |
Work plan received and approved for vapor intrusion investigation at residences located down gradient from the pump house (within 100 feet). Indoor air, outdoor air, and sub-slab (or near-slab or exterior soil gas) samples will be collected, depending on access permission. |
Jim Fish |
11/23/2020 |
Document, Report, or Work plan Review - other |
Received 2020 report for vapor intrusion evaluation of down-gradient residences. Soil gas and indoor air data indicate vapor intrusion was not occurring. |
Jim Fish |
11/23/2020 |
Update or Other Action |
DEC received copies of letters sent to residences whose properties were sampled for vapor intrusion, and provided with sampling data by the consultant. |
Jim Fish |
3/22/2021 |
Update or Other Action |
Approved work plan addendum, outlining recovery well decommissioning, and new monitoring well installation and proposed sampling. DEC encouraged consultant to consider a one-time substrate injection in the recovery well prior to decommissioning. Such action is still pending, awaiting vendor response. Work plan addendum was approved so consultant can move forward with proposed work. An update work plan addendum may be submitted if substrate addition materializes. |
Jim Fish |
6/1/2021 |
Cleanup Plan Approved |
Approved one-time injection of PetroFix into the recovery well (prior to decommissioning) at the CONP Firewell Pump House site. |
Jim Fish |
9/3/2021 |
Document, Report, or Work plan Review - other |
Received Summer 2021 Site Characterization report from consultant. Recovery well RW-1 was decommissioned and PetroFix and commerical electron acceptor blend for hydrocarbon remediation was injected. A soil boring was advanced and sampled and later completed as a new groundwater monitoring well (MW-21-01); groundwater was sampled from all monitoring wells; wells were surveyed and groundwater flow direction and gradient were determined. |
Jim Fish |
9/14/2021 |
Site Characterization Report Approved |
Approved Summer 2021 Site Characterization report |
Jim Fish |
11/18/2021 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78828 Day Tank Overfill. |
Jim Fish |
12/9/2021 |
Document, Report, or Work plan Review - other |
Received Fall 2021 Summary Report from consultant |
Jim Fish |
12/16/2021 |
Site Characterization Report Approved |
Approved Sept 2021 Groundwater sampling & assessment reprot. Recommeded consultant and RP consider the PetroFix treatment for Mw-21-01 as had been done for the former recovery well. |
Jim Fish |
5/26/2022 |
Update or Other Action |
Receive update from contractor for spring sampling event; MW-18-02 was frozen, so sampling will be delayed until fall 2022. Agreed to subsequent sampling events being scheduled for late June. |
Jim Fish |
8/22/2022 |
Document, Report, or Work plan Review - other |
Approved work plan amendment for substrate injection (PetroFix) |
Jim Fish |
9/1/2022 |
Update or Other Action |
Contacted consultant to notify EPA Region 10 UIC Program about planned substrate injection |
Jim Fish |
9/14/2022 |
Update or Other Action |
Received notification that monitoring well in ROW (MW21-01) was paved over this summer. CONP crew cut the pavement around the well and it now useable (will be receiving substrate injection). |
Jim Fish |
11/4/2022 |
Update or Other Action |
Received a Spring 2022 Summary Report Submittal from consultant for review. |
Jim Fish |
8/21/2023 |
Document, Report, or Work plan Review - other |
Received the Fall 2022 summary report from consultant today. |
Jim Fish |
8/31/2023 |
Long Term Monitoring Workplan or Report Review |
Fall 2022 8th Avenue monitoring report approved. |
Jim Fish |
7/1/2024 |
Long Term Monitoring Workplan or Report Review |
Received 2023 sampling report from consultant and concur with recommended sampling schedule:
Semiannual sampling from the on-site and off-site monitoring wells downgradient of the
former recovery well and UST (MW-1, MW18-01, MW18-02, MW19-01, MW19-02, and MW21-01);
Sampling at a reduced frequency (e.g., once every two years) from monitoring wells upgradient of the release area, (MW-2, MW19-03, and MW19-04); and
Monitoring the presence of PetroFix during sampling events. |
Jim Fish |