Skip to content Skip to content

Site Report: Eielson AFB (SS534) Hydrant Fuel System Bldg 1211

Site Name: Eielson AFB (SS534) Hydrant Fuel System Bldg 1211
Address: 2755 Flightline Avenue; Building 1211, Eielson AFB, AK 99702
File Number: 107.38.109
Hazard ID: 25653
Status: Active
Staff: Axl LeVan, 9074512156 axl.levan@alaska.gov
Latitude: 64.664444
Longitude: -147.090833
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

According to spill reports, there have been two spills at this site: 50 gallons of JP-8 on 09 May 2008 (spill no. 08309913001) and 60 gallons of JP-8 on 19 October 2009 (spill no. 09309929201). Based on the dead vegetation on the sides of the engineered ditch adjacent to Building 1211, DEC expects that the quantity of fuel spilled was greater than the reported 110 gallons. Site characterization in May 2010 was followed by an interim removal action in September 2010. Approximately 378 loose cubic yards of soil were excavated at three areas. A soil amendment (Micro Blaze) was applied to the bottom of each excavation area before the areas were backfilled with clean soil. Excavated soil with PID readings above 50 ppm was incinerated. Soil with PID readings between 10 and 50 ppm was stockpiled. Eielson plans to address the stockpile and conduct additional groundwater and soil sampling during the 2011 field season. The impacted area is within an engineered drainage channel that flows into the Water Treatment Plant pond, which is Installation Restoration Program (IRP) source area SS35 (see DEC hazard ID 392, file number 107.38.018). A third spill (spill no. 11309913202) occurred at this site on 12 May 2011. Approximately 150 gallons of JP-8 spilled in the same area as the other spills. 10-30 gallons of product were recovered and at least 50 cubic yards of contaminated soil excavated. Excavation of contaminated soil was limited due to the building foundation and adjacent concrete pad, as well as buried cathodic protection and electrical lines. Sampling for this site was planned for 2012 and future years.

Action Information

Action Date Action Description DEC Staff
4/15/2011 Spill Transferred from Prevention Preparedness and Response Program Spill transfered by PERP staff Brian Jackson. Spill no. 08309913001; spill date = 5/9/08; substance = JP-8 aviation fuel; quantity = ~50 gallons; PERP file no. 107.02.018; LC 14280660; description: gasket failed on return pump to product recovery tank during fuel transfer from E-2. Mitzi Read
4/15/2011 Spill Transferred from Prevention Preparedness and Response Program Spill transfered by PERP staff Brian Jackson. Spill no. 09309929201; spill date = 10/19/09; substance = JP-8 aviation fuel; quantity = ~60 gallons; PERP file no. 107.02.018; LC 14280660. Mitzi Read
5/4/2011 Site Added to Database A new site has been added to the database Mitzi Read
5/5/2011 Update or Other Action Interim Removal Action report (January 2011): approximately 400 cubic yards of contaminated soil were removed, a soil amendment designed to improve degradation was applied and soil sampling was conducted at three areas. At the main excavation area, soil removal was limited by a fence and buried utilities. Benzene- and DRO-contaminated soils remain and groundwater monitoring is recommended. At SB-23, soil samples from the base and sidewalls of the excavation were below cleanup levels. At SB-29, DRO-contaminated soil was identified at the base and sidewalls of the excavation. Additional soil sampling is recommended. This interim removal was completed before this site was transferred to CS. Kathleen Beutel
5/9/2011 Document, Report, or Work plan Review - other Contaminated Sites staff commented on a letter work plan for soil and groundwater sampling at Building 1211 on Eielson AFB. Proposed 2011 activities include additional horizontal soil delineation near the SB-29 excavation area and groundwater monitoring downgradient of the main and SB-29 excavation areas. CS staff requested that soil samples be analyzed for PAHs and GRO in addition to DRO and RRO and also asked for explanation of what will be done if soil contamination is found in the SB-29 area. Kathleen Beutel
5/13/2011 Site Visit A spill of approximately 150 gallons JP-8 was reported on 12 May 2011. The spill occurred on the south side on the building in the same location as the 2008 and 2009 spills. An estimated 10-30 gallons of free product were recovered immediately adjacent to the building. Approximately 30 cubic yards of contaminated soil were removed on 12 May and taken to the already-existing Building 1211 stockpile. Excavation continued on 13 May but was limited in many areas by buried utility lines. PID readings of up to 1120 ppm were recorded adjacent to the building (where no further excavation can take place). CS declined approval to add a soil amendment (MicroBlaze) to the excavation. PERP and/or CS staff visited the site on both 12 May and 13 May. Kathleen Beutel
5/23/2011 Site Visit CS and PERP staff visited the spill site and stockpiles. Approximately 48 cubic yards of contaminated soil have been stockpiled. There are also two drums of soil from the excavation. This stockpile, as well as the stockpile from the 2010 interim removal action, will be transported to OIT when funding is available. Stained soil is still visible at the spill site and additional excavation will occur this week. The excavation will be backfilled with clean soil when no additional soil can practicably be excavated. Kathleen Beutel
5/27/2011 Document, Report, or Work plan Review - other Contaminated Sites staff approved a work plan to perform additional delineation at this site. Three soil borings will be taken just outside the SB-29 excavation area, where, during the 2010 interim removal, soil samples from the walls of the excavation area had DRO concentrations above cleanup levels. In addition, one groundwater monitoring well will be installed downgradient of SB-29 and two monitoring wells will be installed downgradient of the main excavation area, where soil removal has been limited by concrete and buried utilities. Monitoring wells will be sampled biannually for the next two years. Stockpiled soil from the 2010 interim removal will be characterized for disposal. Kathleen Beutel
8/10/2011 Spill Transferred from Prevention Preparedness and Response Program Spill transferred by PERP staff Ashley Anderson. Spill no. 11309913202; spill date = 5/12/11; substance = JP8 fuel; quantity = ~150 gallons; description: source of release was a fuel pipe falve at Building 1211 caused by a pressure relief valve gasket failure. Mitzi Read
1/3/2012 Update or Other Action DEC requested submission of soil and groundwater data collected in 2011. Kathleen Beutel
6/20/2012 Document, Report, or Work plan Review - other Letter is addressed to Eielson from ADEC. Letter outlines a series of deadlines that have been missed for document submission by Eielson. Letter outlines missed deadlines and the documents that were to be submitted at that time, as well as warns of enforcement actions should future deadlines be missed. The letter concludes with a reminder about an upcoming deadline for the AAFES Service Station IRA report and the building 1211 October 2011 groundwater monitoring report on July 15th, 2011. Hannah Harrison
10/1/2012 Document, Report, or Work plan Review - other Field Change Form for Installation-Wide Monitoring Program for Eielson Air Force Base. For for missing or damaged wells. Submitted October 1st, 2012 by Eielson to ADEC and EPA. Form states: the following monitoring wells have been identified in the field as either missing or damaged to the extent that it is no longer suitable for sampling: St13/DP26, DP44, SS61, DP25. Proposed changes as stated on the form: At source areas ST13/DP26, DP44, and SS61, existing mintoring wells are beign sampled under the IWMP, therefore no new suitable wells are available. At source area DP25, a different monitoring well will bes ampled as an alternative to the original well. Figures are attached with missing/damaged wells marked. Hannah Harrison
10/4/2012 Document, Report, or Work plan Review - other Field change form No. 10, Revision 0. Allows for additional PSG samplers to be installed at WP38. Request submitted by Eielson, approved ADEC RPM. Reason for action: at source area WP38, three additional PSG sample locations will be added to the area of storage Tank 1. The addtional locations were agreed to during the monthly RPM meeting on 26 September 2012 attended by RPMs representing the USAF, EPA, and ADEC. Project: Installation-Wide Monitoring Program. Eielson. Hannah Harrison
4/4/2013 Update or Other Action Staff reviewed the Draft Source Evaluation Report for Multiple Sites at Eielson AFB, of which Bldg 1211 is a part. In a letter dated March 4th, 2013, ADEC noted that the report does not meet the requirements of a Release Investigation, nor complete a full Site Characterization under State regulations. The letter also notes that completed sampling has thus far been limited, and that there are still data gaps to be addressed. Specific to Bldg 1211, the sampling done thus far finds levels of DRO in the soil to be below cleanup levels. Hannah Harrison
6/13/2014 Update or Other Action On April 23, 2014, the Alaska Department of Environmental Conservation and the United States Air Force reached agreement on the State-Eielson Air Force Base Petroleum Site Restoration Agreement (Two-party Agreement). This agreement was established to perform any necessary assessment, monitoring, remediation and cleanup determinations for petroleum contaminated sites at Eielson Air Force Base. This site was identified as a petroleum contaminated site requiring a response action and its cleanup will continue under Alaska regulations, following the procedures established in the agreement. Monte Garroutte
3/17/2015 Exposure Tracking Model Ranking Initial ranking with ETM completed for source area, ranking based off 2012 monitoring report. Anna Iverson
6/10/2015 Site Characterization Workplan Approved Approval issued for the "Final Workplan for Additional Well Installations, Eielson Air Force Base, Alaska" dated 26 May 2015. The workplan describes the installation of 20 new monitoring wells at ten source areas (i.e. ST10/SS14, ST13/DP26, ST18, ST19, DP44, SS61, SS37, ST58, LF04, and SS534)across Eielson, as well as the redevelopment of drinking water well NWS56WH at Source Area ST56 (Engineer Hill). Melinda Brunner
8/7/2015 Document, Report, or Work plan Review - other DEC provided comments to the Defense Logistics Agency on the "Draft Tanker Row Additional Site Assessment Work Plan, Source Area SS534 and SS535, Eielson Air Force Base, Alaska" dated July 2015 (Tanker Row work plan). The Tanker Row work plan describes further planned site characterization work at two sites on Eielson Air Force Base: SS534 (Building 1211) and SS535 (Tank 5), where JP8 is the primary contaminant. Melinda Brunner
8/17/2015 Site Characterization Workplan Approved DEC approved the "Final Tanker Row Additional Site Assessment Work Plan, Source Area SS534 and SS535, Eielson Air Force Base, Alaska." The purpose and objectives of the planned work are to characterize the extent of soil and groundwater contaminated by petroleum at source areas SS534 and SS535. The proposed work includes: (1) mobilizing a drilling rig to the site to sample up to 16 boreholes and to install eight monitoring wells; (2) developing and sampling the newly installed monitoring wells; (3) sampling two existing monitoring wells; and (4) preparing an assessment report and feasibility study for the sites. Field work is scheduled to begin in August 2015. Melinda Brunner
8/19/2015 Site Visit Brunner and Breitenberger visited the site to inspect the implementation of the work plan approved on 8/17/15. Activities underway include taking soil borings, installing monitoring wells, and sampling existing monitoring wells. Melinda Brunner
10/9/2015 Document, Report, or Work plan Review - other DEC reviewed the draft "2014 Site Characterization Of Source Area SS534 And Source Area SS535, Eielson Air Force Base, Alaska" dated April 2015 (the SS534/SS535 Report) and provided comments to the USAF. The SS534/SS535 Report describes sampling activities completed in 2014 at SS534 and SS535, two adjacent petroleum-contaminated sites at Eielson Air Force Base. Sampling of soil and groundwater was conducted to evaluate data gaps, delineate the nature and extent of soil and groundwater contamination, and determine the need for further investigation at each site. Melinda Brunner
10/27/2016 Site Characterization Report Approved DEC approved the 2014 Site Characterization of Source Area SS534 and Source Area SS535. Contamination remains under the Tank 5 containment area at SS535. Additional investigation was recommended for SS535 outside of the containment area. Contamination was delineated at SS534, and an excavation of shallow soil was recommended. Monte Garroutte
10/27/2016 Site Characterization Report Approved DEC approved the 2014 Site Characterization of Source Area SS534 and Source Area SS535, Eielson Air Force Base, Alaska. Contamination remains under the Tank 5 containment area at SS535. Additional investigation was recommended for SS535 outside of the containment area. Contamination was delineated at SS534, and an excavation of shallow soil was recommended. John O'Brien
5/4/2017 Document, Report, or Work plan Review - other DEC approved the Tanker Row 2015 Additional Site Assessment Report and Feasibility Study, dated November 2015, for Source Area's SS534 and SS535. The report documents soil and groundwater sampling activities at the two source areas. Analytical results showed contamination remaining in the soil and groundwater. At SS535, contamination still remains beneath the lined containment area. Erica Blake
10/23/2017 Document, Report, or Work plan Review - other DEC approved the 2017 Work Plan for groundwater sampling in late November at the Tanker Row (SS535 and SS534) sites on October 11, 2017. A final work plan was received on October 23, 2017 describing groundwater sampling activities at ten monitoring wells at the Tanker Row sites. Groundwater samples will be submitted for gasoline range organics (GRO), diesel range organics (DRO)/residual range organics (RRO), benzene, toluene, ethylbenzene, xylenes (BTEX) and total lead. Additional analyses collected at SS535-MW05 will be polynuclear aromatic hydrocarbons (PAHs). Erica Blake
10/27/2017 Site Characterization Report Approved DEC Approval of the 2014 Site Characterization of Source Area SS534 and Source Area SS535, Eielson Air Force Base, Alaska Monte Garroutte
9/28/2018 Document, Report, or Work plan Review - other DEC approved the 2017 Tanker Row Eielson Air Force Base, Alaska Groundwater Monitoring Report, dated June 21, 2018. The document describes 2017 groundwater sampling activities at the Eielson Air Force Base, Defense Logistics Agency (DLA) Tanker Row Building 1211 (Source Area SS534) and Tank 5 (Source Area SS535). During the 2017 sampling event, only seven of the ten wells were sampled for the following analysis; gasoline range organics (GRO), diesel range organics (DRO), residual range organics (RRO), benzene, toluene, ethylbenzene, xylenes (BTEX) and total lead. Polycyclic aromatic hydrocarbons (PAHs) were only collected from one well (SS535-MW05). The only analyte to exceed DEC cleanup levels during the 2017 groundwater sampling was total lead. Benzene was detected, but below the cleanup level. Samples were not collected from the following wells: 1211-MW05, 1211-MW06 (SS534) and SS535-MW01 because they could not be located under the snow piles. The next round of sampling is planned for September/October 2018. Erica Blake
8/2/2019 Document, Report, or Work plan Review - other DEC provided comments for a draft Decision Document for Eielson Take-Off Pad, Eielson Air Force Base, Alaska. The site formerly hosted the Eielson Take-Off facility (ETOP), a fuel transfer building, which was removed in 2004. Currently, a pipeline and associated access road traverse the site, and are the only infrastructure present within the area of contamination. The draft Decision Document (DD) presents the remedy selected to address petroleum hydrocarbon contamination in soil and groundwater at the ETOP site at Eielson Air Force Base, Alaska. Dennis Shepard
3/20/2020 Document, Report, or Work plan Review - other DEC provided comments on the "Tanker Row Eielson Air Force Base, Alaska 2019 Groundwater Monitoring Report Draft January 2020." Sara Marshall
4/16/2020 Document, Report, or Work plan Review - other DEC approved "Tanker Row Eielson Air Force Base, Alaska 2019 Groundwater Monitoring Report Draft January 2020." The Groundwater Monitoring Report presents the results of the groundwater monitoring and sampling activities conducted at the Tanker Row Release Site on Eielson Air Force Base, Alaska. Eight monitoring wells were sampled and the results were compared against the state regulatory criteria and previous sampling events. Sara Marshall
11/30/2020 Cleanup Plan Approved DEC provided approval and signed a Decision Document for Eielson Take-Off Pad, Eielson Air Force Base, Alaska. The Decision Document (DD) presents the remedy selected to address petroleum hydrocarbon contamination in soil and groundwater at the Eielson Take-Off Pad site at Eielson Air Force Base, Alaska. Dennis Shepard
3/17/2021 Document, Report, or Work plan Review - other DEC provided comments on "Tanker Row Eielson Air Force Base, Alaska 2020 Groundwater Monitoring Report Draft March 2021." The Groundwater Monitoring Report presents the results of the groundwater monitoring and sampling activities conducted at the Tanker Row Release Site on Eielson Air Force Base, Alaska. Seven out of the Eight planned monitoring wells were sampled and the results were compared against the state regulatory criteria and previous sampling events. Axl LeVan
4/15/2021 Document, Report, or Work plan Review - other DEC approved "Final Tanker Row Eielson Air Force Base, Alaska 2020 Groundwater Monitoring Report, March 2021." The Groundwater Monitoring Report presents the results of the groundwater monitoring and sampling activities conducted at the Tanker Row Release Site on Eielson Air Force Base, Alaska. Seven out of the Eight planned monitoring wells were sampled and the results were compared against the state regulatory criteria and previous sampling events. Axl LeVan
7/23/2021 Site Visit DEC conducted a site visit with Defense Logistics Agency (DLA) staff. DEC and DLA walked the site to inspect the monitoring wells. Everything was observed to be in good condition. Axl LeVan

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

Hazard ID Site Name File Number
392 Eielson AFB (OU-4) (SS035) Asphalt Mix Area 107.38.018

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close