Action Date |
Action |
Description |
DEC Staff |
5/24/2011 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
5/24/2011 |
Update or Other Action |
Staff recieved a draft work plan for 2011 work but has not received a final report for the 2010 work nor a final work plan for last year’s work. |
Debra Caillouet |
5/24/2011 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79090 name: Fort Wainright Montgomery Road Extension |
Debra Caillouet |
6/10/2011 |
Document, Report, or Work plan Review - other |
Work Plan Addendum, Montgomery Road Planned Excavation Activities, Fort Wainwright May 2011
DEC has no objection to the implementation of this work but is concerned that the diesel range organic contamination that was documented to exist at the location of SB09 in 2010 is not being addressed. Nor any of the geophysical anomalies that were detected outside of the road footprint. Please make arrangements to completely characterize this area.
|
Debra Caillouet |
7/21/2011 |
Site Characterization Report Approved |
Final After-Action Report, Montgomery Road, 2010 Construction Support, Fort Wainwright, June 2011
Contamination remains on-site; DRO with results of 8,730 mg/kg, 4,050 mg/kg, and 293 mg/kg, respectively. Results from Test Pit 2 also showed exceedances for RRO (28,800 mg/kg and 23,600 mg/kg), lead (528 mg/kg and 1990 mg/kg), tetrachloroethene (PCE) (0.0487 mg/kg), and benzene (0.0561 mg/kg).
|
Debra Caillouet |
10/10/2011 |
Document, Report, or Work plan Review - other |
Doyon Utilities, Services to Montgomery Road Extension, Addendum to the Post-Wide Sampling and Analysis Plan, non-objection letter
|
Debra Caillouet |
12/13/2011 |
Document, Report, or Work plan Review - other |
Doyon Utilities, Services to Montgomery Road Extension, notice of no contamination found recieved. |
Debra Caillouet |
3/23/2012 |
Document, Report, or Work plan Review - other |
reviewed and commented on Preliminary Draft 2012 Work Plan, Assessment and Monitoring at Various Post-Construction Sites, Fort Wainwright, March 2012 |
Debra Caillouet |
3/28/2012 |
Document, Report, or Work plan Review - other |
2011 Montgomery Road Extension After-Action Report, Draft, March 2012 |
Debra Caillouet |
7/17/2012 |
Interim Removal Action Approved |
2011 Montgomery Road Extension After-Action Report (FINAL)
The report documents a removal of 24 cubic yards of contaminated soil within the area of the Montgomery Road Extension. This was a limited action and did not address all of the contamination that was identified in 2010.
|
Debra Caillouet |
3/16/2015 |
Document, Report, or Work plan Review - other |
Draft Work Plan Environmental Investigations various Sites, Fort Wainwright Alaska January 2015 was reviewed. This this work plan addresses 17 sites at Fort Wainwright. The plan was written in UFP-QAPP but has major deficiencies requiring a complete rewrite of the document. Detailed comment was sent to the Army. |
Debra Caillouet |
6/15/2015 |
Update or Other Action |
The Army was sent a review of the response to comment that was provided for the comments sent in March on the draft work plan. DEC has remaining concerns for the Conceptual Site Model, site specific DQO's and the site history provided. |
Debra Caillouet |
12/13/2016 |
Meeting or Teleconference Held |
A two day Federal Facilities Agreement (FFA) and Stakeholders meeting was held on December 13 & 14, 2016. The main focus of the meeting was to develop a site discovery and site intake process that would satisfy requirements of the Fort Wainwright FFA, RCRA Permit, and two party agreements. The Army, EPA and DEC committed to a flowchart of the preliminary source evaluation process. Timelines were established for scoping a land use control implementation plan (LUCIP) and developing a contracting schedule for Fort Wainwright contaminated site investigations and remedial actions. Seven sites were proposed for inclusion into the FFA (three party agreement) by the Army and the RPMs documented the assignment of the regulatory path for these sites using a newly developed and agreed to signature form. |
Dennis Shepard |
1/1/2017 |
Document, Report, or Work plan Review - other |
DEC approved the 2015 Annual Institutional Controls Report, Fort Wainwright, Alaska (August 2016). |
Dennis Shepard |
2/19/2020 |
Update or Other Action |
The Montgomery Road concrete vault site (108.38.134) was changed to non-qualifying on 2/19/2020. It has been merged with this site. |
Kevin Fraley |
9/8/2021 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 80550 name: Montgomery Road Concrete Vault |
Erica Blake |
6/9/2023 |
CERCLA RI Plan Approved |
DEC completed a backcheck and partial approval of the Final Supplemental Remedial Investigation (SRI) Work Plan for 33B Barracks, Building 1054, Building 3014, and the Montgomery Road Extension. The objective of each SRI is to characterize the nature and extent of contamination and evaluate the human health and ecological risk. The SRI results will be used to develop preliminary remediation goals and identify remedial alternatives that will be further evaluated in a feasibility study (FS). The work plan is intended for use in conjunction with the Risk Assessment Work Plan, which is currently under regulatory review.
Several comments on the draft work plan requested contamination in soil to be delineated to at least the most stringent of DEC’s promulgated cleanup levels, typically the migration to groundwater cleanup levels. DEC recognizes the importance of the intended field sampling, and the Army’s commitment to ensureanalytical methods have limits of detection that are able to achieve the DEC migration to groundwater cleanup levels. As the Army did not identify the fate and transport model that will be used to evaluate the migration to groundwater pathway, DEC will evaluate the results of this field effort as presented in the draft report to evaluate whether the nature and extent of the contamination has been delineated. DEC will identify at that point if sufficient information has been gathered to determine the fate and transport of contamination over time. Data gaps may persist after the SRI effort due to this oversight.
Additionally, due to the recent DEC Bulk Petroleum Hydrocarbon Noncancer Toxicity for Human Health Risk Assessments Technical Memorandum (DEC, May 2023), DEC does not find the language in Section 1.3 regarding bulk petroleum risk to be in accordance with guidance, and the Army must address this issue further during comment resolution of the Risk Assessment Work Plan. All other responses to comments have been incorporated into the final document and are accepted.
Lastly, on May 24, 2023, DEC was informed that the US Army Corps of Engineers (USACE) had begun conducting sampling without DEC approval of the SRI work plan. In accordance with 18 AAC 75.335(b) and 18 AAC 75.360(2), work may not begin at a site until the work plan has been approved. This formally documents the Army’s non-compliance with the above-referenced regulations and provides notice that future non-compliance with state regulations may result in a Compliance Advisory Letter or formal enforcement actions, as appropriate. |
Tim Sharp |