| Action Date |
Action |
Description |
DEC Staff |
| 7/1/1996 |
Update or Other Action |
Field Investigation Report |
Employee Past |
| 3/1/1997 |
Update or Other Action |
Community Relations Plan |
Employee Past |
| 3/1/1997 |
Risk Assessment Workplan Approved |
Work plan approved this date. |
Employee Past |
| 3/1/1997 |
Update or Other Action |
Removal Action Alternatives Memo |
Employee Past |
| 3/1/1997 |
Site Characterization Report Approved |
Remedial Investigation report approved this date. |
Employee Past |
| 4/29/1999 |
Interim Removal Action Approved |
IRA approved this date. |
Anne Marie Palmieri |
| 8/23/2002 |
Site Visit |
Site visit conducted with COA, Sealaska, and Huna Totem. Surface water samples were collected to determine if the inhalation and ingestion DRO cleanup levels would be protective of the migration to groundwater cleanup levels. |
Anne Marie Palmieri |
| 1/15/2003 |
Cleanup Level(s) Approved |
Alternative cleanup levels for DRO approved this date. |
Anne Marie Palmieri |
| 2/24/2003 |
Update or Other Action |
Draft Feasibility Study reviewed - no comments other than approval of ACL. |
Anne Marie Palmieri |
| 9/11/2003 |
Update or Other Action |
Annual landfill inspection conducted by the COE. |
Anne Marie Palmieri |
| 12/12/2003 |
CERCLA Proposed Plan |
Proposed plan for excavation and off-site disposal approved. |
Anne Marie Palmieri |
| 7/20/2006 |
Update or Other Action |
Staff reviewed the Technical Memo prepared by Bristol Environmental for delineating the areas of PCB and POL contamination at the stie. This characterization will occur within the next 2 weeks. Excavation and off-site disposal will occur in summer 2007. |
Anne Marie Palmieri |
| 8/18/2006 |
Update or Other Action |
Decision Document closing out the CON/HTRW project signed by John Halverson. HTRW project remains open pending resolution of: 1) PCB and petroleum contamination at main camp, and 2) contamination at Debris Disposal Area. |
Anne Marie Palmieri |
| 2/20/2007 |
Update or Other Action |
Staff reviewed and responded to the Tech Memo documenting 2006 fieldwork. |
Anne Marie Palmieri |
| 5/15/2007 |
Meeting or Teleconference Held |
Public meeting in Hoonah regarding the proposed 2007 cleanup. |
Anne Marie Palmieri |
| 7/18/2007 |
Cleanup Plan Approved |
Staff approved a cleanup plan for the 2007 removal of PCB contaminated soil and DRO contaminated soil. Field work is scheduled to begin at the end of July and continue through August. Soil will be excavated and sent off-site for treatment by thermal incineration and disposed of in Utah. |
Anne Marie Palmieri |
| 4/29/2008 |
Interim Removal Action Approved |
Removal Action report approved this date. Additional PCB contaminated soil was found at the site and not removed in 2007. The USACE plans to remove the remaining contamination in 2008. |
Anne Marie Palmieri |
| 6/12/2008 |
Update or Other Action |
Comments on the draft work plan provided to USACE and Bristol this date. Fieldwork is scheduled to begin mid-July. |
Anne Marie Palmieri |
| 7/11/2008 |
Meeting or Teleconference Held |
Public meeting held in Hoonah. |
Anne Marie Palmieri |
| 7/11/2008 |
Site Visit |
Site visit. |
Anne Marie Palmieri |
| 2/26/2009 |
Interim Removal Action Approved |
IRA Report (dated 1/09) approved this date. PCB contamination still present at EA 4 and EA 8 at levels greater than 1 mg/kg. |
Anne Marie Palmieri |
| 11/5/2009 |
Meeting or Teleconference Held |
First PRP meeting held this date to address remaining contamination at EA4, EA8, and the Debris Disposal Area. |
Anne Marie Palmieri |
| 5/17/2011 |
Meeting or Teleconference Held |
Meeting with PRPs to discuss site visit. |
Anne Marie Palmieri |
| 6/16/2011 |
Update or Other Action |
Site visit conducted by SLR. |
Anne Marie Palmieri |
| 8/24/2011 |
Meeting or Teleconference Held |
PRP meeting to discuss work plan components. |
Anne Marie Palmieri |
| 9/14/2011 |
Site Characterization Workplan Approved |
Work plan approved for characterizing the remaining contamination at EA4 and the Debris Disposal Area. SLR will be on-site in late September. |
Anne Marie Palmieri |
| 9/23/2011 |
Update or Other Action |
On 9/23/11 the Hoonah Radio Relay Station database entry was divided into four separate records. Original Hazard ID 1452 (Reckey 199211X119701) was renamed from Hoonah Radio Relay Station to Hoonah RRS - Main Cantonment, and additional database records were created for EA 4: PCB Soil Stockpile Area; EA 8: Septic Outfall; and EA 9: Debris Disposal Area. |
Mitzi Read |
| 9/23/2011 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
| 3/9/2012 |
Site Characterization Report Approved |
Field Investigation and Assessment Report (2-12) approved this date. |
Anne Marie Palmieri |
| 9/16/2013 |
Cleanup Plan Approved |
Cleanup plan approved this date. Additional characterization will occur in Sept. 2013 and cleanup in summer 2014. |
Anne Marie Palmieri |
| 11/26/2013 |
Document, Report, or Work plan Review - other |
Staff reviewed the summary report from the 2013 field work. |
Anne Marie Palmieri |
| 6/5/2014 |
Update or Other Action |
AT&T's consultant, SLR, notified DEC that field work is scheduled to begin on July 7, 2014. |
Anne Marie Palmieri |
| 6/26/2015 |
Final Cleanup Report Reviewed |
The final cleanup report was reviewed and approved this date. All PCB contamination greater than 1 mg/kg was excavated and disposed of appropriately. |
Anne Marie Palmieri |
| 6/26/2015 |
Cleanup Complete Determination Issued |
A cleanup complete determination letter was issued on this date. |
Anne Marie Palmieri |