Action Date |
Action |
Description |
DEC Staff |
4/19/1995 |
Site Characterization Report Approved |
Phase 1 Remedial Investigation report approved this date. |
Employee Past |
9/1/1995 |
Update or Other Action |
Community Relations Plan |
Employee Past |
7/3/1996 |
Risk Assessment Workplan Approved |
Risk Assessment work plan approved this date. |
Employee Past |
8/1/1996 |
Site Characterization Report Approved |
Phase 2 Remedial Investigation Report approved. |
Employee Past |
3/1/1998 |
Update or Other Action |
EE/CA submitted. |
Employee Past |
8/1/1998 |
CERCLA FS |
Feasilibility Study submitted. |
Employee Past |
11/20/1998 |
Risk Assessment Report Approved |
Risk Assessment Report approved this date. |
Employee Past |
2/23/1999 |
Cleanup Plan Approved |
Cleanup Plan approved this date. Cleanup levels approved as interim removal action screening levels. |
Anne Marie Palmieri |
2/24/2000 |
Interim Removal Action Approved |
Interim Removal Action approved this date. Over 700 tons of fuel and lead-contaminated soil was removed from three excavations. Four monitoring wells installed in 1995 were sampled in 2001; no exceedences were found. |
Anne Marie Palmieri |
9/27/2002 |
Cleanup Level(s) Approved |
DEC approves the 10x groundwater alternative cleanup level based upon a determination that the groundwater is not a current or future source of drinking water. |
Anne Marie Palmieri |
6/8/2004 |
Cleanup Level(s) Approved |
Soil cleanup levels approved this date. Cleanup levels correspond with the groundwater 10X rule. |
Anne Marie Palmieri |
4/2/2007 |
CERCLA ROD Approved |
John Halverson signed the Declaration of Project Closure Decision and No Dept. of Defense Action Indicated for the CON/HTRW project this date. |
Anne Marie Palmieri |
9/29/2008 |
Site Characterization Report Approved |
Final RI Report Addendum approved this date. The report summarizes all of the past information (characterization and cleanup) of the site. No significant areas of contamination remain. No Feasibility Study will be prepared. Preferred alternative is no action. |
Anne Marie Palmieri |
9/24/2009 |
CERCLA ROD Approved |
Decision Document signed this date; no additional action is necessary. |
Anne Marie Palmieri |
9/27/2011 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
9/27/2011 |
Update or Other Action |
On 9/27/11 the Sitka Naval Operations Base database entry was divided into seven separate records. Original Hazard ID 1992 was renamed from Sitka Naval Operating Base to Sitka NOB - Area F - Tank Farm No. 2, and additional database records were created for Area A - Power Plant; Areas B/C/D/I/J - Frmr Army Navy Service Station, Water Tower TF, TF Nos. 1/4/5; Area E - Millerville Housing; Area G -Igarotte Housing Area; Area H - Seaplane Dock; and Area K Tank Farm No. 3. |
Mitzi Read |
9/29/2011 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79177 name: Sitka NOB - Area E - Millerville Housing |
Anne Marie Palmieri |
10/21/2011 |
Cleanup Complete Determination Issued |
John Halverson signed the USACE Decalaration of Project Closure Decision this date. |
Anne Marie Palmieri |
11/17/2011 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 79177 Sitka NOB - Area E - Millerville Housing. |
Anne Marie Palmieri |
4/17/2020 |
Site Characterization Workplan Approved |
Staff reviewed and approved a characterization work plan provided by SEARHC intended to identify potential contamination which could impact future land development plans. Fieldwork is scheduled for late spring/early summer 2020. |
Anne Marie Palmieri |
9/4/2020 |
Site Characterization Report Approved |
Staff approved a copy of the SEARHC site characterization report on this date. A copy of the letter is included in the attachments. |
Anne Marie Palmieri |
7/9/2021 |
Document, Report, or Work plan Review - other |
Reviewed the June 24, 2021 SEARHC Millerville Phase II ESA work plan on this date. This is a landowner driven investigation so DEC did not provide comments/recommendations on the work plan, but is aware that the work is being done later in the month. |
Evonne Reese |
11/23/2021 |
Document, Report, or Work plan Review - other |
As a landowner driven investigation and cleanup, in September 2021, RSE worked with Marble Construction to excavate approximately 2,015 tons of hydrocarbon impacted soil from the area surrounding boreholes BH-10, BH-10S, and BH-10S2 at the subject property. Soil was transported to Bicknell in Juneau for thermal treatment and to Republic Services landfill for disposal. The excavation did not reach the extent of the contaminated soil in all directions, but due to project constraints, the excavation was completed and backfilled. A report detailing this effort should be issued in the near future. An additional work plan which describes the methods for installing approximately 30 soil borings with as many as 10 completed as temporary monitoring wells to further delineate contamination in the proposed hospital building footprint area. RSE will collect soil and groundwater samples from these soil borings and monitoring wells. The data collected will be used to further delineate areas of hydrocarbon impacted soil at the site to support planning efforts for the new hospital construction project. DEC has reviewed both work plans but formal approval DEC approval is not required because the investigation is landowner driven.
|
Evonne Reese |
3/16/2023 |
Update or Other Action |
In preparation for the constructions of a new SEARHC hospital and parking lots, a total of 6,669.53 tons of hydrocarbon impacted soil was transported under ADEC approval to Bicknell, Inc in Juneau, Alaska for thermal treatment in November 2022. A large portion of the project site was excavated down to bedrock to meet the MEMCC project structural requirements. Contaminated soil was left in place at the site in the southern and southeastern portion of the project limits at depths of approximately 5 to 20 feet below ground surface. This contaminated soil was later covered with 5 to 10 feet of clean overburden soil. All impacted material at the site was either removed down to bedrock or will be left in place under parking lots. No impacted material underlies the current new hospital building location or within a minimum of approximately 30 feet horizontally of the new hospital location. A site diagram of the excavations and remaining contaminated soil is attached to this database record. |
Evonne Reese |