7/26/2012 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
7/27/2012 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79310 name: Surface Releases of PCE & TCE |
Mitzi Read |
7/30/2012 |
Site Characterization Workplan Approved |
Staff reviewed and conditionally approved of Alta Geosciences, Inc.’s “Well Installation and Groundwater Sampling Work Plan, KUA Jewel Lake Site, ADEC File No. 2100.38.047”, dated July 20, 2012. Alta proposes to install two groundwater monitoring wells on the Lot 12B-2 north of the 2012 Soil Remediation Area. During well installation, soil samples with the highest field screening headspace reading will be collected and analyzed for VOCs according to CSP approved methods. Once the wells are installed, developed, and purged, groundwater samples will be collected and analyzed for VOCs in accordance with CSP approved methods.
Staff approved of work plan provided an additional monitoring well is installed south of the 2012 soil remediation area. This monitoring well shall be sampled for VOC’s along with the two other newly installed monitoring wells. Groundwater flow is to the south in this area and thus, CSP would like to determine if a chlorinated solvent plume is migrating south off the property. |
Todd Blessing |
2/12/2013 |
Update or Other Action |
Staff reviewed Alta Geosciences "Monitoring Well Installation and Groundwater Monitoring Report", dated December 28, 2012. Alta documented the installation and sampling of three monitoring wells on Lot12B. Soil and groundwater samples were collected during the well installation and were analyzed for volatile organic compounds. No volatile organic compounds were detected above 18 AAC 75 cleanup levels in soil or groundwater. |
Todd Blessing |
6/13/2013 |
Update or Other Action |
DEC received a CSM and a set of drawings showing proposed building locations on the property. DEC issued letter to RP discussing potential steps toward site closure and potential institutional controls for the site. |
Jacob Gano |
9/3/2013 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 79310 Surface Releases of PCE & TCE. |
Meghan Dooley |
9/23/2013 |
Cleanup Complete Determination Issued |
Cleanup Complete with Institutional Controls determination made by ADEC. An NEC will be filed in the Anchorage recording office. |
Meghan Dooley |
9/26/2013 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Meghan Dooley |
8/7/2014 |
Document, Report, or Work plan Review - other |
ADEC approved a work plan to install an asphalt cap to cover the remaining contamination as per the Institutional Controls established in the Cleanup Complete with Institutional Controls determination letter. |
Meghan Dooley |
8/19/2014 |
Institutional Control Compliance Review |
IC compliance review conducted. Reminder system set for a five-year review in 2018 to verify that the cap remains in good condition and that ICs remain protective. |
Evonne Reese |
10/14/2014 |
Institutional Control Update |
ADEC was notified that the asphalt cap will not be installed in 2014 due to contracting issues and freezing temperatures. The RP intends to install the cap in the spring of 2015. |
Meghan Dooley |
2/20/2015 |
Update or Other Action |
Change staff name from Dooley to IC Unit. |
Evonne Reese |
6/8/2015 |
Institutional Control Update |
ADEC received confirmation that the asphalt cap was installed as required as part of the Cleanup Complete - ICs determination. |
Evonne Reese |
4/17/2017 |
Institutional Control Compliance Review |
IC compliance review conducted. Closure/IC Details updated. Reminder system is set to follow-up on land use conditions and the condition of the asphalt cap in 2020. |
Kristin Thompson |
9/14/2017 |
Institutional Control Update |
Contacted by an engineering firm under contract by the landowner to investigate possible property development on this property. They are aware of the asphalt cap which is providing a protective barrier to the historic contamination and plan on leaving the cap in place. Anchorage DEC staff will be meeting with the property owner and engineering firm to discuss the details. |
Evonne Reese |
10/5/2017 |
Institutional Control Periodic Reporting |
Received notice that the property has been sold to a real estate company. Affiliates information updated. The new landowner has been informed of the site's contamination history and the conditions of the site's conditional closure. |
Kristin Thompson |
11/13/2017 |
Institutional Control Update |
A letter was issued to U-Haul clarifying property needs with regards to future construction and verifying institutional controls for this site (Lot 12B). |
Kristin Thompson |
6/11/2018 |
Update or Other Action |
The extent of soil contamination has been defined to an area on the west central portion of the project. Soil transport forms were provided by Anchorage DEC program management to the contractors to move approximately 28,000 cubic yards of non-contaminated soil off the property.
|
Evonne Reese |
6/11/2018 |
Update or Other Action |
A request is submitted from BGES (consultant) to EPA requesting a Contained-In Determination for soils generated during site characterization and the proposed construction activities for property development. |
Kara Kusche |
7/9/2018 |
Update or Other Action |
EPA issues determination that soils and investigation derived wastes associated with planned redevelopment activities at the site meet contained-in levels and do not exhibit a hazardous characteristic. |
Kara Kusche |
7/19/2018 |
Offsite Soil or Groundwater Disposal Approved |
ADEC approves the transport and disposal of 400-500 cubic yards of soil to go to that Anchorage Regional Landfill. |
Kara Kusche |
6/18/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was issued to the landowner. The next review will be in five years’ time. |
Gaige Robinson |