Action Date |
Action |
Description |
DEC Staff |
2/25/2016 |
Site Added to Database |
A new site has been added to the database |
Nathan Maxwell |
2/26/2016 |
Update or Other Action |
Bethel Environmental is under contract with the Aleutian Pribilof Islands Association to submit a work plan for the clean up of the Puganax Creek Buried Drum Site with NALEMP funding. |
Holly Weiss-Racine |
3/21/2016 |
Meeting or Teleconference Held |
Project kickoff meeting held at the Aleutian Pribilof Islands Association Office. |
Holly Weiss-Racine |
4/12/2016 |
Potentially Responsible Party/State Interest Letter |
PRP Letter sent to the Aleutian Pribilof Islands Association and the Atka IRRA Council on 4/4/16. |
Holly Weiss-Racine |
4/19/2016 |
Site Visit |
ADEC, USACE, APIA and Bethel Environmental Solutions visited the project site in Atka. An open-house style public meeting was held at the Atka School from 6-8 pm. The community was in support of the project. |
Holly Weiss-Racine |
7/8/2016 |
Document, Report, or Work plan Review - other |
ADEC approved the “Puganax Creek Buried Drum Removal - Former Atka Air Force Auxiliary Field - Atka, Alaska” Work Plan. Field work is scheduled to occur at the end of July/early August with the objective of removing all buried drums and associated soil contamination (up to the 100 ton contract maximum). The removal objective is Cleanup Complete (without ICs).
|
Holly Weiss-Racine |
3/24/2017 |
Document, Report, or Work plan Review - other |
The work at Puganax Creek scheduled for 2016 was postponed until 2017 due to unavailability of equipment and lodging during the scheduled work timeframe. ADEC received an update, Puganax Creek Buried Drum Removal Work Plan Update, dated 3-23-2017. The updates to the approved 2016 Work Plan were administrative changes and do not change the scope of the approved 2016 Work Plan. The field work is currently scheduled for April 2017. |
Darren Mulkey |
5/15/2018 |
Document, Report, or Work plan Review - other |
ADEC approves the 'Final Removal Action Report, Puganax Creek Buried Drum Removal, Former Atka Air Force Auxiliary Field, Atka, Alaska, May 2018' in a letter dated May 15, 2018. This report details the excavation of 105.39 tons of heavily contaminated soil, and the removal of approximately 1.6 tons of corroded drums and drum carcasses, some containing residual product, from the subsurface. Analytical data from confirmation soil samples collected from the excavation sidewalls and floor showed that DRO, RRO, arsenic, chromium, lead, VOCs, and PAHs remain at the site in concentrations exceeding ADEC Method Two most stringent cleanup levels. |
Sammi Castle |
8/8/2019 |
Update or Other Action |
Site location was updated on this date. Coordinates for this site are used to determine the presence and position of the site on BLM’s ANCSA Conveyed Land web map. |
Rebekah Reams |
6/21/2021 |
Document, Report, or Work plan Review - other |
Final Contaminated Site Characterization Report, Puganax Creek Buried Drum Site, Native Village of Atka, Atka IRP Council, June 2021. The project objectives addressed in this report are: Completion of a geophysical investigation of the site to determine where buried drums may
still be present; Digging test pits for the collection of field and analytical data to determine extent of
contamination remaining at the site; and Approximating the extent and tonnage of contaminated soil. |
Darren Mulkey |
8/24/2021 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79889 name: Drum Storage Area |
Darren Mulkey |
5/2/2022 |
Update or Other Action |
On May 02, 2022 ADEC approved the Final 2022 Puvaankix Creek, Cleanup Workplan 2022, Native Village of Atka, NALEMP, Atka Island. |
Daniela Fawcett |
11/28/2022 |
Document, Report, or Work plan Review - other |
On 11/28/2022 DEC emailed the comment letter and table to Atka Tribe for the Puvaankix Creek: Cleanup Work Plan 2022 Addendum – Additional Site Characterization Draft Work Plan, Dated November 2022.
This work plan addendum is intended to supplement the Final 2022 Puvaankix Creek, Cleanup Work Plan (Chilkat Environmental 2022) and guide the additional site characterization activities to better delineate the soil contamination and determine the extent of free-flowing product prior to proceeding with removal activities. |
Daniela Fawcett |
1/20/2023 |
Update or Other Action |
On 01/20/2023 DEC requested the United States Army Corps of Engineers (USACE) to make a finding of determination of eligibility for newly discovered contamination during the 2022 site investigation work near the Atka Puganax Creek NALEMP site located on Atka Island, Alaska. |
Daniela Fawcett |
3/3/2023 |
Document, Report, or Work plan Review - other |
DEC emailed an approval letter for the Puvaankix Creek: Cleanup Work Plan 2022 Addendum – Additional Site Characterization Draft Work Plan, Dated March 2023.
This technical memorandum work plan is intended to supplement the Final 2022 Puvaankix Creek, Cleanup Work Plan (Chilkat Environmental 2022) and guide the additional site characterization activities to better delineate the soil contamination and determine the extent of free-flowing product prior to proceeding with removal activities. |
Daniela Fawcett |
12/14/2023 |
Meeting or Teleconference Held |
DEC project manager (PM) had a teleconference to discuss the site with the USACE FUDS PM. |
Sarah Bernhardt |
1/7/2025 |
Update or Other Action |
Site name has been updated from Puganax Creek to Puvaankix Creek. 2024 site documents reflect the updated place name. |
Sarah Durand |
4/17/2025 |
Site Characterization Workplan Approved |
2024 Workplan Addendum approved for remediation work associated with the Puvaankix Creek NALEMP project. |
Sarah Durand |
4/18/2025 |
Site Characterization Report Approved |
2023 Additional Site Characterization report approved for the NALEMP Puvaankix Creek project. |
Sarah Durand |