Action Date |
Action |
Description |
DEC Staff |
5/2/2016 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
5/3/2016 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 79910 name: HEA Kenai NWR Utility Poles |
Mitzi Read |
5/6/2016 |
Potentially Responsible Party/State Interest Letter |
DEC sent Homer Electric Association (HEA) a Potentially Responsible Party letter and a letter requesting submittal of a site characterization workplan by not later than June 22, 2016. |
John Halverson |
6/14/2016 |
Update or Other Action |
DEC received a letter from HEA stating it does not believe additional site characterization is necessary and requesting that DEC rescind the Potentially Responsible Party letter and request for site characterization. |
John Halverson |
8/22/2016 |
Meeting or Teleconference Held |
DEC met with staff and contractors working for ADOT, USWFS and HEA regarding a Sterling Highway Improvement Project scheduled for construction in 2017 that will impact contaminated soil at the base of PCP treated utility poles near the East Fork of Moose Creek. DOT will include contract provisions requiring an environmental consultant to develop and implement plans to conduct sampling and analysis around utility poles that will need to be removed and to properly manage contaminated media during the construction project. The plans will be developed in coordination with USFWS, HEA and DEC. Decisions on whether contaminated soil/sediment can be managed in place or will need to be removed will be based on the sample results, design and construction plans, the feasibility of removal and evaluation of potential risks posed. A goal is to conduct the soil sampling this winter so data are available for review in the spring in time to plan any necessary removal and waste management activities for the construction to proceed. |
John Halverson |
7/12/2017 |
Meeting or Teleconference Held |
DEC met with representatives from ADOT, Western Wood Preservers Institute, Tellus (QEP for DOT), Integral Consulting Inc. to answer questions and discuss ADOT Sterling Highway Improvement project schedule. Western Wood Preservers Institute and Consultant (Integral Consulting, Inc.) requested to review the ADOT project Sampling and Analysis Plan being written. The ADOT project has begun, but the schedule for sampling was not clear. |
Wendy Hansen |
8/15/2017 |
Update or Other Action |
DEC corresponded with the Project Engineer who reported that two of the HEA poles planned for sampling (QK-255 and QK-256) fell over during electrical transmission line decommissioning activities at the East Fork Bridge. The length and buried depths were measured and documented. The poles were taken to the HEA yard in Kenai and the areas surrounding QK-254 through QK-257 were secured to mitigate potential disturbance. Photos and communications indicated that the surface area around poles QK-255 and QK-256 had been disturbed, to include the planned surface sample location(s) at QK-255. |
Wendy Hansen |
8/29/2017 |
Meeting or Teleconference Held |
DEC staff attended a teleconference with ADOT, USFWS, Tellus (QEP), and Granite Construction representatives to discuss the status of the site near the East Fork Moose River near MP 71.5 with regard to potentially compromised sample locations around utility poles, water management, path forward, and status of the Sampling & Analysis and Soil Management Plans that were scoped in ADOT contract specifications for the project. |
Wendy Hansen |
8/30/2017 |
Update or Other Action |
DEC Contaminated Sites requested a dewatering permit for management of storm water that had accumulated on site, prior to pumping. The collection of surface soil sample(s) from the water accumulation area prior to the placement of fill material was also requested. |
Wendy Hansen |
9/14/2017 |
Document, Report, or Work plan Review - other |
DEC staff provided comments on surface water and sediment/soil sampling plans. The plans provided details for sampling activities planned in an area of standing water that collected in a low spot adjacent to a power pole where dioxins and pentachlorophenol were detected in previous sampling efforts. |
Wendy Hansen |
9/22/2017 |
Document, Report, or Work plan Review - other |
DEC staff provided comments to Granite Construction on a revised sediment sampling plan, for collection of samples in the ponded water accumulation area. |
Wendy Hansen |
9/25/2017 |
Document, Report, or Work plan Review - other |
DEC staff provided comments to Granite Construction on a revised surface water sampling plan, for collection of samples in the ponded water accumulation area. |
Wendy Hansen |
10/6/2017 |
Enforcement Action |
DEC staff issued an NOV to Granite Construction Company and ADOT, Enforcement Tracking No. 2017-R0871 for conducting regulated activities within an active contaminated site without a work plan. |
Wendy Hansen |
10/16/2017 |
Update or Other Action |
Granite Construction Company issued letter dated October 13, 2017 to the DEC requesting that NOV 2017-R0871 be reversed to a Compliance Letter. |
Wendy Hansen |
10/17/2017 |
Document, Report, or Work plan Review - other |
DEC staff provided comments to Granite Construction on a second revision to each surface water and sediment/soil sampling plans, for collection of soil samples in the ponded water accumulation area and water samples from a lined containment basin. The revised plans were submitted to the DEC on October 9, 2017. |
Wendy Hansen |
10/19/2017 |
Meeting or Teleconference Held |
DEC staff met with representatives from ADOT, Granite Construction, and contractor/QEP Corvid, LLC. to resolve outstanding comments on the soil and surface water sampling plans. Revised plans are anticipated the week of October 23, 2017. The original sampling plan for the ten (10) utility poles is anticipated by December 1, 2017. |
Wendy Hansen |
10/19/2017 |
Update or Other Action |
DEC staff issued a letter to Granite Construction Company denying the reversal of NOV 2017-R0871. |
Wendy Hansen |
11/2/2017 |
Document, Report, or Work plan Review - other |
DEC staff provided comments to Granite Construction on a third revision (Rev.4) to the soil (formerly sediment) sampling plan, for collection of soil samples in the ponded water accumulation area. The revised plan was submitted to the DEC on October 25, 2017. |
Wendy Hansen |
11/3/2017 |
Site Characterization Workplan Approved |
DEC staff approved Rev.5 to the soil (formerly sediment) sampling plan, for collection of soil samples in the ponded water accumulation area. The revised plan was submitted to the DEC on November 3, 2017. |
Wendy Hansen |
3/27/2018 |
Site Characterization Workplan Approved |
Staff approved Work Plan titled Five Pole Site Characterization Work Plan Sterling Highway Rehabilitation Sterling, Highway, Alaska Final, and dated March 23, 2018. The plan was written by Corvid, LLC (on behalf of Granite Construction) and submitted to the ADEC on March 25, 2018. The focus of the site characterization is to delineate the nature and extent of pentachlorophenol (PCP) and polychlorinated dibenzo-p-dioxins (PCDD) and polychlorinated dibenzofurans (PCDF) around five utility poles near the East Fork Moose River in conflict with the Alaska Department of Transportation Sterling Highway Rehabilitation project. The data will be used to support decisions regarding management of soil around the poles. |
Wendy Hansen |
3/27/2018 |
Enforcement Action Closed |
NOV 2017-R0871 was closed. All terms and conditions have been completed to the satisfaction of DEC. |
Wendy Hansen |
4/4/2018 |
Update or Other Action |
DEC staff issued a closure letter to Granite and ADOT for NOV 2017-R0871. |
Wendy Hansen |
5/17/2018 |
Document, Report, or Work plan Review - other |
DEC approved Granite's Final Storm Water Runoff Characterization Sampling work plan submitted May 15, 2018. The focus of the plan is to collect water samples from a constructed and lined containment cell at the construction site to inform decisions regarding discharge or disposal. |
Wendy Hansen |
6/26/2018 |
Update or Other Action |
DEC received surface water sample results from Granite's lined containment cell. One sample and a duplicate were collected. No pentachlorophenol was detected. The Toxic Equivalent Quotient for polychlorinated dibenzo-p-dioxins and dibenzofurans was below Alaska Water Quality Standards. |
Wendy Hansen |
6/29/2018 |
Update or Other Action |
The Department of Water issued Excavation Dewatering Authorization AKG002102 to Granite Construction for the discharge of water in the lined containment cell. The water will be used for dust suppression at Granite's material site at MP 77 of the Sterling Highway. |
Wendy Hansen |
8/1/2018 |
Document, Report, or Work plan Review - other |
DEC received letter report providing summary of data from DOT/Granite 5-pole site characterization. |
Wendy Hansen |
8/6/2018 |
Meeting or Teleconference Held |
DEC staff met with DOT, FWS, HEA, Granite, and Consultant Corvid to discuss data from 5-pole site characterization and path forward for management of utility poles in conflict with DOT/Granite construction project. Soil samples were collected from varying distances around the poles in March of 2018. Data show concentrations of PCP, polychlorinated dibenzo-p-dioxins (PCDDs) and dibenzofurans (PCDFs) above 18 AAC 75.341 cleanup levels are primarily limited to within a radius of 1 to 10 feet of the source poles. The vertical extent of contamination was not determined for three of the five poles. |
Wendy Hansen |
8/8/2018 |
Update or Other Action |
DOT, FWS, and DEC agreed that remaining pole remnants and butts associated with poles in conflict with the DOT/Granite construction project at MP 58-79 will be removed from the ground with minimal disturbance, holes will be backfilled with clean fill, and the contaminated areas will be covered with geo-textile, geo-grid fabric, and a minimum of three feet of clean fill. |
Wendy Hansen |
8/24/2018 |
Update or Other Action |
DEC received draft site characterization report written by Corvid,LLC., and dated August 24, 2018. The report was prepared for Granite Construction under contract to the Alaska DOT. It documented site activities conducted in 2018 to characterize the nature and extent of contamination (pentachlorophenol, polychlorinated dibenzo-p-dioxins, and polychlorinated dibenzofurans) in soil around five utility poles in conflict with a Sterling Highway Rehabilitation project. |
Wendy Hansen |
4/19/2019 |
Site Characterization Report Approved |
DEC approved the final report titled Five Pole Site Characterization and Background Study Report; Sterling Highway Rehabilitation; Sterling, Alaska; Final Revision 1, dated April 1, 2019. A draft report was submitted on August 28, 2018. The draft report was revised to address stakeholder comments. |
Wendy Hansen |