| Action Date |
Action |
Description |
DEC Staff |
| 8/12/2016 |
Potentially Responsible Party/State Interest Letter |
Potentially Responsible Party / State Interest Letter sent by PPRP staff Allison Natcher to Wards Cove Packing Company. |
Mitzi Read |
| 8/22/2016 |
Spill Transferred from Prevention Preparedness and Response Program |
Spill transferred by PPRP staff Allison Natcher. Spill no. 90119936501; spill date = 1/1/1990; discovery date = 7/17/15; substance = petroleum; quantity = unknown. |
Mitzi Read |
| 8/25/2016 |
Site Added to Database |
A new site has been added to the database |
Mitzi Read |
| 9/20/2016 |
Potentially Responsible Party/State Interest Letter |
PRP letter sent electronically today to Dan Carrier with the Chevron Environmental Management Company. Dan stated that he would look into this with Jan Supler at Wards Cove Packing. |
Bruce Wanstall |
| 9/20/2016 |
Potentially Responsible Party/State Interest Letter |
PRP letter sent electronically today to Jan Supler at Wards Cove Packing Company |
Bruce Wanstall |
| 10/3/2016 |
Document, Report, or Work plan Review - other |
DEC approved by letter today Notification of a Petroleum Release from a Former Tank Farm letter/report submitted by G-Logics Inc. for Wards Cove Packing (WCP) regarding a tank farm reportedly formerly operated by Chevron from the 1940s to the 1980s. WCP also has had an interest in the site since the mid-1970s. Six above ground storage tanks (ASTs) and related appurtenances, including a truck rack pump station entered as a separate site on the CS Database. Site investigation indicates soil contamination by release of leaded gasoline and diesel to surface soil. Groundwater was encountered on average at two feet below ground surface. |
Bruce Wanstall |
| 10/21/2016 |
Document, Report, or Work plan Review - other |
DEC approved by letter sent electronically today to G-Logics to collect samples and remove soil at the Wards Cove Packing/Former Chevron Truck Rack site in Hoonah. |
Bruce Wanstall |
| 11/3/2016 |
Site Visit |
Travel to Hoonah to meet with G Logics Stuart Hyde. A removal action and site characterization was conducted at the truck rack site. |
Bruce Wanstall |
| 2/3/2017 |
Document, Report, or Work plan Review - other |
DEC has reviewed and approved: Technical Assistance and Soil Sampling ,Former Chevron Truck Loading Truck Property, 147 Front Street Hoonah AK 99826 Report (Report), dated January 11, 2017. G-Logics submitted the Report to DEC by electronic mail on January 24, 2017 documenting soil removal and sampling activity at the referenced Site for Wards Cove Packing. DEC requested a removal action be hand-performed at the piping bulkhead, follow the approved work plan to characterize the piping bulkhead and the truck rack removal site for benzene, toluene, ethylbenzene, and total xylenes and/or polycyclic aromatic hydrocarbons, conduct sub-slab sampling under the maintenance building at the truck rack, and submit the condition and location of the ten super sacks loaded with DRO contaminated soil. |
Bruce Wanstall |
| 2/3/2017 |
Document, Report, or Work plan Review - other |
DEC has reviewed and approved: Technical Assistance and Soil Sampling ,Former Chevron Truck Loading Truck Property, 147 Front Street Hoonah AK 99826 Report (Report), dated January 11, 2017. G-Logics submitted the Report to DEC by electronic mail on January 24, 2017 documenting soil removal and sampling activity at the referenced Site for Wards Cove Packing. DEC requested a removal action be hand-performed at the piping bulkhead, follow the approved work plan to characterize the piping bulkhead and the truck rack removal site for benzene, toluene, ethylbenzene, and total xylenes and/or polycyclic aromatic hydrocarbons, conduct sub-slab sampling under the maintenance building at the truck rack, and submit the condition and location of the ten super sacks loaded with DRO contaminated soil. |
Bruce Wanstall |
| 5/5/2017 |
Document, Report, or Work plan Review - other |
DEC has reviewed and approved by electronic mail: Workplan to Provide Remediation and Site-Closure Assistance, Former Chevron Truck-Loading Rack, 147 Front Street (Plan), dated April 11, 2017 and received by DEC by electronic mail on May 2, 2017. G-Logics Inc. submitted the Plan to DEC for approval regarding additional site characterization sampling and environmental cleanup at the referenced Site. Sub-slab probes will be installed and sampled in accordance with DEC’s Vapor Intrusion Guidance for Contaminated Sites dated January 2017. A tracer leak test will be performed on each probe prior to sample collection to assess the seal between the probe and the soil slab. Soil gas samples will be collected in 1 liter summa canisters fitted with 15 minute flow regulators. Shut in tests will be performed on the sampling train (and before sample collection) to assess the seal between the summa canister and the sample tubing. Soil removal will take place in the fuel pipe area at the shoreline bulkhead. Soils with odor or staining will be hand excavated and placed into super sacks. Confirmation samples will then be collected after removal or an obstruction is reached.
|
Bruce Wanstall |
| 10/3/2017 |
Document, Report, or Work plan Review - other |
Characterization report received |
Erin Gleason |
| 11/27/2017 |
Document, Report, or Work plan Review - other |
ADEC reviewed the 10/3/2017 report. Revisions are needed prior to ADEC approval. Sent letter to Doug Brindle of Wards Cove. |
Erin Gleason |
| 12/5/2017 |
Meeting or Teleconference Held |
Teleconference with ADEC, Wards Cove, and G-Logic to discuss report revisions and site conditions. |
Erin Gleason |
| 12/8/2017 |
Meeting or Teleconference Held |
Teleconference held between ADEC, Wards Cove, and ADOL to discuss responsible parties for the site. |
Erin Gleason |
| 2/8/2018 |
Document, Report, or Work plan Review - other |
ADEC received the revised Technical Assistance, Former Chevron Truck-Loading Rack Report on January 24, 2018 from G-Logic. Upon review, ADEC has some additional comments and questions. Letter sent to Wards Cove requesting meeting to discuss additional comments and questions. ADEC's Kara Kusche and Todd Blessing will now assist with the site due to its complex nature. |
Erin Gleason |
| 4/3/2018 |
Meeting or Teleconference Held |
Teleconference held with G-Logic, WArds Cove, and ADEC to discuss the comment matrix, final draft report, and future work at the site. G-logic will incorporation ADEC comments and today's discussion into the report and make a final draft. ADEC will provide direction of water pathways at site by April 30, 2018 and information about creosote from dock pilings in Alaska. Jan Suppler will provide an ADOT contact so ADEC may coordinate with ADOT on the oil water separator use. G-Logic will prepare and submit a work plan to be approved by ADEC. The work will be conducted in fall 2018. |
Erin Gleason |
| 4/3/2018 |
Workplan Requested |
ADEC has extended the report deadline to July 1, 2018. |
Erin Gleason |
| 4/30/2018 |
Update or Other Action |
ADEC understands from G-Logic that the site has a confining layer of bedrock underneath the entire site and has determined that the migration to ground water pathway is closed. the migration to surface water pathway is still open. |
Erin Gleason |
| 10/17/2018 |
Update or Other Action |
Revised site characterization report is overdue as of 7/1/2018. ADEC sent email to G-logic and Wards Cove today inquiring about status of report. ADEC understands that the report is delayed due coordination with other PRP and insurance company. G-logic anticipates the report will be submitted in November 2018. |
Erin Gleason |
| 3/27/2019 |
Document, Report, or Work plan Review - other |
Received site characterization work plan from G-logic on behalf of Wards Cove. ADEC will review and respond. |
Erin Gleason |
| 5/28/2019 |
Document, Report, or Work plan Review - other |
ADEC reviews and provides comment on the "Work Plan to Conduct an Additional Environmental Exploration, Former Chevron Truck-Loading Rack" on 5/28/2019. Revised work plan is due May 31, 2019. Deadline extended to 6/14/2019 per request of G-Logic. |
Erin Gleason |
| 6/4/2019 |
Site Characterization Report Approved |
Received site characterization report from G-logic on behalf of Wards Cove on March 27th, 2019. The report details the 2017 characterization of the Truck Rack and Fuel pump island area. GRO is present in surface soil above human health cleanup levels. DRO is present in surface soils above ingestion cleanup levels. Naphthalene and xylene are present above migration to groundwater cleanup levels in surface soil. PAH were detected above NOAA SQUIRTs values in sediment at the fuel pump island. ADEC received revised report on 6/17/2019 because of delays from the insurance company. ADEC has reviewed the revised report and it is now approved. |
Erin Gleason |
| 7/1/2019 |
Site Characterization Workplan Approved |
The 2019 characterization work plan includes sampling of the pore water, sediment and soil at the truck loading rack area and fuel pipe area. Samples will be analyzed for GRO, DRO, VOCs, and PAH. The objective of this work plan is to define the full nature and extent of the contamination on site. |
Erin Gleason |
| 11/21/2019 |
Update or Other Action |
2019 Site Characterization report deadline has been extended to 12/31/2019. |
Erin Gleason |
| 2/24/2020 |
Update or Other Action |
Sent overdue report letter to Wards Cove. |
Erin Gleason |
| 5/15/2020 |
Document, Report, or Work plan Review - other |
Received report of summer 2019 field work from g-logic on behalf of Ward Cove. ADEC will review and provide comment. |
Erin Gleason |
| 10/26/2020 |
Document, Report, or Work plan Review - other |
ADEC has reviewed the report from May 2020 and requests that some revisions and additions be made. Revised report is due November 30th, 2020. |
Erin Gleason |
| 12/9/2020 |
Update or Other Action |
Received comment response matrix from g-logic. ADEC will review and discuss with g-logic and RP at meeting on 12/10 |
Erin Gleason |
| 12/10/2020 |
Meeting or Teleconference Held |
Meeting held on this date with ADEC, Wards Cove, Top Notch Holding, and G-logic to discuss the requested revisions (as listed in the October 27th, 2020 letter) to the May 19, 2020 Report. |
Erin Gleason |
| 2/1/2021 |
Update or Other Action |
ADEC emailed response to comments to g-logic and requested the final draft report be submitted for review and approval. |
Erin Gleason |
| 2/22/2021 |
Document, Report, or Work plan Review - other |
Received revised report from G-Logic on behalf of Wards Cove. ADEC has reviewed the report and it is now approved. Report includes data for the fuel pipe area of the tank farm site and also the entire truck rack site. Fuel pipe area is nearly delineated. ADEC recommends no further sampling in this area until up gradient sources have been removed. Truck rack area has been delineated and will be evaluated for closure. Letter sent on this date. |
Erin Gleason |
| 3/10/2021 |
Update or Other Action |
ADEC has reviewed the file and determined that this site is not eligible for closure. Letter sent to Wards Cove on this date. |
Erin Gleason |
| 3/18/2021 |
Meeting or Teleconference Held |
Meeting with ADEC, Wards Cove, and G-Logic to discuss 3/10/21 ADEC letter. G-logic does not concur with the ADEC letter and will write a rebuttal letter stating why they believe the site is ready for closure. |
Erin Gleason |
| 7/14/2021 |
Update or Other Action |
Received letter from G-Logic on behalf of Wards Cove Packing in response to March 10th, 2021 letter. |
Erin Gleason |
| 10/5/2021 |
Workplan Requested |
ADEC has reviewed the site for closure with the additional information from G-Logic provided in July 2021. Based on all the information to date, the contamination has not been delineated around TRB7. Additional soil samples are needed in this area. Letter sent to Wards Cove on this date requesting a work plan. |
Erin Gleason |
| 10/13/2021 |
Meeting or Teleconference Held |
Meeting with ADEC managers, Wards Cove, and TNH to discussion other possible closure options. |
Erin Gleason |