Site Report: Eielson AFB Basewide (AKA Sitewide) PFAS

Site Name: Eielson AFB Basewide (AKA Sitewide) PFAS
Address: Eielson Air Force Base, Eielson AFB, AK 99702
File Number: 107.38.150
Hazard ID: 26773
Status: Informational
Staff: Sara Marshall, 9074512156 sara.marshall@alaska.gov
Latitude: 64.675709
Longitude: -147.091318
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

This database record includes general information about per- and polyfluoroalkyl substances (PFAS) contamination at Eielson Air Force Base (EAFB)and Moose Creek. PFAS are a diverse group of compounds that have been used in many industrial applications and consumer products including fire-fighting foams. Ongoing investigations are gathering information to determine the location of PFAS-contaminated sites on EAFB. Upon completion of the investigations, specific areas may be assigned individual Hazard IDs and tracked separately. Please see site-specific database entries to learn more about an individual EAFB PFAS-contaminated site. Update 2019 This database record will continue to provide updated Action entries regarding the Moose Creek Interim Record of Decision (IROD) and Air Force remedies to address PFAS related groundwater impacts.

Action Information

Action Date Action Description DEC Staff
8/16/2017 Spill Transferred from Prevention Preparedness and Response Program Spill transferred by PPRP staff Jill Stockbridge. Spill no. 17309919801; spill date = 7/17/17; substance = aqueous film forming foam (AFFF) concentrate; quantity = 5 gallons (4.5 gallons recovered); coordinates = 64.670105,-147.094116, WGS84; PPRP file number = 107.02.004. Description: A release of fire fighting foam concentrate occurred while performing maintenance on a fire suppression system at Eielson Air Force Base Building 1176. The 0.5 gallon that was not recovered was released into the sanitary sewer which leads to the wastewater treatment plant pond. Mitzi Read
8/22/2017 Update or Other Action DEC reviewed and provided comments on the Draft Site Inspection Report for Aqueous Film Forming Foam Areas, Eielson Air Force Base, Alaska (June, 2017). The 15 AFFF areas inspected were: Air National Guard (ANG) Hangar (Building 1171) • ANG KC-135 Hangar (Building 1176) • Corrosion Control (Building 1348) • Current Fire Training Area (FTA) (FT009) and Former Base Landfill (LF003) Fire Station 1 (Building 1206) • Former Adak Building Fire • Former Fire Station 1 • Former FTA near Antenna Farm (FT092) • Former FTAs by Current Entomology Building (Building 4335) • Fuel Pump House (Building 1246) • Garrison Slough • Hangar (Building 1344) • Power Plant Cooling Pond • Thunderdome (Building 1140) • Wastewater Treatment Plant (WWTP) and Biosolids Land Spreading Area John O'Brien
9/1/2017 Site Added to Database A new site has been added to the database Mitzi Read
10/26/2017 Update or Other Action DEC approved the Final Addendum #5 to the Final Perfluorinated Compounds Investigations Work Plan, Eielson Air Force Base, Alaska, Perfluorinated Compounds Moose Creek Area Drinking Water Sampling, Surface Water and Sediment Sampling at Eielson Air Force Base, Alaska. The WP outlines the objectives, methodology, and quality assurance (QA) and quality control (QC) procedures for the surface water and sediment investigation to be performed as part of the Moose Creek Area Drinking Water Sampling, Analysis, and Treatment project supporting EAFB. The purpose of the investigation is to determine the concentrations of the perfluoroalkyl substances (PFAS) perfluorooctanoic acid (PFOA) and perfluoro-octanesulfonate (PFOS) in surface water bodies and in sediment at Eielson AFB and selected offsite locations. The PFAS concentrations in sediment and surface water will be used to coordinate and/or guide future surface water, sediment, and fish tissue sampling. John O'Brien
8/28/2018 Site Visit Site visit to the Eielson AFB to view current status of work in F-35 construction area, visit power plant, Garrison Slough pond, Garrison slough, and the fish gate. Also visited stockpile areas for PFAS contaminated soil. Dennis Shepard
8/29/2018 Meeting or Teleconference Held A remedial project manager (RPM) meeting was held and the main topic was a SS062/SS067 Garrison Slough Risk Assessment (RA) Scoping Session. DEC, EPA and AFCEC risk assessors discussed contractor presented approach to the Risk assessment. Concerns over the proposed exposure areas were raised by the risk assessors present. Dennis Shepard
9/13/2018 Update or Other Action DEC Technical Memorandum for Action Levels for PFAS in Water and Guidance on Sampling Groundwater and Drinking Water, dated August 20, 2018, issued with notification letter to AFCEC regarding all Eielson/Moose Creek PFAS sites. The tech memo establishes drinking water for six PFAS compounds when detected in groundwater or surface water used for drinking water: PFOS, PFOA, PFNA, PFHxS, PFHpA, and PFBS and requests that all future sampling results for PFAS-impacted groundwater, surface water, and pore water include results for all six UCMR3 PFAS compounds. Bri Clark
9/24/2018 Meeting or Teleconference Held A remedial project manager (RPM) meeting was held and the main topic was the SS062/SS067 Garrison Slough Risk Assessment (RA) Scoping Session. DEC, EPA and AFCEC risk assessors discussed contractor presented data quality objectives for the Risk assessment. Concerns over the proposed sampling of soils sediments, surface waters and biota were raised by the risk assessors present. Dennis Shepard
9/27/2018 Update or Other Action DEC issued a letter to the USAF regarding the use and discharge of PFAS contaminated groundwater originating from Eielson Air Force Base. The letter expressed concern about untreated water being discharged into septic systems or to the ground surface via outdoor spigots. The letter stipulates that all water be treated or provided to prevent discharge of PFAS contaminated water and requested a plan and schedule to do so by October 25, 2018. Bri Clark
9/27/2018 Update or Other Action The USAF issued a response to DEC regarding the technical memorandum for PFAS compounds. The USAF stated that it follows the federal Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) process in investigations and response actions. They sited PFOS and PFOA as having promulgated cleanup levels under the State's formal rule-making process and as such, they are the two PFAS compounds evaluated as potential applicable or relevant and appropriate requirements (ARARs) on a site-specific basis. The USAF stated, as the additional four PFAS compounds listed in the PFAS tech memo are not promulgated at this time, they do not meet the CERCLA definition of an ARAR. Bri Clark
10/2/2018 CERCLA ROD Periodic Review DEC provided comments on the Draft Interim Record of Decision for Community of Moose Creek, Alaska, Long-Term Water Supply, Eielson Air Force Base, Alaska, dated August 2018. This document summarizes the assessment of the groundwater in Moose Creek as related to PFOS and PFOA contamination and discusses interim and final remedies. Bri Clark
10/4/2018 Update or Other Action The Air Force PBR contractor provided meeting minutes from the August 29, 2018 Scoping meeting for Garrison Slough (SS062 AND SS067) Human Health and Ecological Risk Assessment. The minutes were submitted for review and comment by the regulatory agencies in order to document concerns for the risk assessment approach. Dennis Shepard
10/9/2018 Report or Workplan Review - Other The Air Force PBR contractor provided meeting minutes from the September 24, 2018 Scoping meeting for Garrison Slough (SS062 AND SS067) Human Health and Ecological Risk Assessment. The minutes were submitted for review and comment by the regulatory agencies in order to document concerns for the risk assessment data quality objectives. Dennis Shepard
10/30/2018 Meeting or Teleconference Held A two day remedial project manager (RPM) meeting was held on October 29 and 30, 2018. Topics of discussion included Garrison Slough RI/FS and Risk Assessment Scoping. The status of PFAS treatability testing was also discussed and a new treatability study was proposed for soil washing of PFAS contaminated soil. Dennis Shepard
2/6/2019 CERCLA ROD Periodic Review DEC issued comments on the Draft Final Interim Record of Decision for Community of Moose Creek, Alaska, Long-Term Water Supply, Eielson Air Force Base, Alaska, dated August 2018. Bri Clark
4/3/2019 Meeting or Teleconference Held A meeting was held amongst remedial project managers (RPMs) to resolve outstanding comments for the Draft Final Interim Record of Decision for Community of Moose Creek, Alaska, Long-Term Water Supply, Eielson Air Force Base, Alaska, dated August 2018. Bri Clark
4/3/2019 Public Notice On April 3, 2019, the Alaska Department of Fish and Game (ADF&G) issued emergency order No. 3-R-U-01-19 closing sport fishing at Polaris Lake on Eielson AFB. The Emergency order is in response to concentrations of per and poly fluorinated alkyl substances (PFAS)identified above the EPA lifetime health advisory level of 70 parts per trillion. Dennis Shepard
4/12/2019 Update or Other Action A letter was sent to the U.S. Air Force regarding the language in the Moose Creek IROD describing modification/termination of LUCs. DEC requested the Air Force take immediate action to revise, or make exceptions to, its “Air Force Land Use Control Checklist for Active-Duty Bases on the NPL” to include language that allows the checklist user to require state concurrence for the modification/termination of LUCs when appropriate due to state law, existing federal facilities agreements, or other compliance agreements. Dennis Shepard
5/22/2019 Report or Workplan Review - Other DEC provided comments on a Draft Expanded PFOA and PFOS Site Inspection at Eielson Air Force Base and Moose Creek, Alaska, Uniform Federal Policy-Quality Assurance Project Plan Work Plan, Eielson Air Force Base, Alaska, May 2019. The plan includes installation of 24 monitoring well, groundwater sampling and stepout borings to identify monitoring well locations. Dennis Shepard
6/4/2019 Update or Other Action DEC sent a letter request for surface water sampling to be included in the Expanded Perfluorooctanoic Acid (PFOA) and Perfluorooctanesulfonic Acid (PFOS) Site Inspection at Eielson Air Force Base and Moose Creek, Alaska. DEC is requesting surface water sampling of the lakes, streams, creeks, sloughs and ponds that are adjacent to and within the Eielson AFB-Moose Creek PFAS plume. Dennis Shepard
6/12/2019 CERCLA ROD Approved On June 11, 2019, the Air Force Civil Engineer Center provided a signed Final Interim Record of Decision for Community of Moose Creek, Alaska, Long-Term Water Supply, Eielson Air Force Base, Alaska. The Interim Action is undertaken to address perfluorooctanoic acid (PFOA) and perfluorooctane sulfonate (PFOS) impacted groundwater with concentrations exceeding the EPA’s 2016 lifetime drinking water health advisory. The Interim Record of Decision (I-ROD) presents the selected interim remedy for the community of Moose Creek, Alaska. This interim action is limited in scope and addresses only provision of an alternative drinking water supply to the community of Moose Creek. Remediation of the contaminated groundwater will also be addressed in a Final Record of Decision (ROD). The selected interim action is required to protect human health in the short-term while a final remedial solution is being developed. This I-ROD will be followed by a Final ROD. Dennis Shepard
9/20/2019 Report or Workplan Review - Other U.S. EPA and DEC provided Joint Approval of the Expanded PFOA and PFOS Site Inspection at Eielson Air Force Base (AFB)and Moose Creek UFP QAPP WP (September 2019). The work plan objective is to laterally and vertically delineate PFOA and PFOS contamination in groundwater on Eielson AFB and in the adjacent community of Moose Creek. Activities include Sampling of existing groundwater monitoring wells on Eielson AFB, the perimeter of Eielson AFB, within the Chena River Flood Control Project, and in the area of Moose Creek, AK. Installation and sampling of temporary wells around the perimeter of Eielson AFB, within the Chena River Flood Control Project, and in Moose Creek, AK. Installation and sampling of step out soil borings to delineate soil above ADEC Human Health Cleanup Level and EPA Risk Based Screening Level exceedances of PFOA and/or PFOS. Dennis Shepard
9/20/2019 CERCLA SI The U.S. Environmental Protection Agency (EPA) and Alaska Department of Environmental Conservation (DEC)jointly approved the Expanded Perfluorooctanoic Acid (PFOA) and Perfluorooctanesulfonic Acid (PFOS) Site Inspection at Eielson Air Force Base and Moose Creek Uniform Federal Policy-Quality Assurance Project Plan Work Plan (September 2019). Soil and groundwater delineation activities for PFOS and PFOA on Eielson AFB and in the areas in and around Moose Creek, Alaska will be undertaken.. Dennis Shepard
10/15/2019 Offsite Soil or Groundwater Disposal Approved 480 cubic yards of soil containing PFOS, PFOA, and Chromium (VI) generated from the EIE406 Arctic Utilidors Phases B&C construction project was transferred to US Ecology in Grand View, Idaho. Sara Marshall
10/16/2019 Offsite Soil or Groundwater Disposal Approved 6 cubic yards of soil containing PFOS generated from the EIE423 Nose Dock construction project was transferred to OIT in Moose Creek, Ak for thermal remediation. Sara Marshall
10/21/2019 Offsite Soil or Groundwater Disposal Approved 156.7 cubic yards of soil containing PFOS, Trichloroethane, and cis-1,3-Dichloropropene generated from the EIE385 construction project was transferred to the Columbia Ridge Landfill in Arlington, Oregon for disposal. Sara Marshall
10/21/2019 Offsite Soil or Groundwater Disposal Approved 367 cubic yards of soil containing cis-1,3-Dichloropropene and hexachlorobutadiene generated from the EIE385 construction project was transferred to the Columbia Ridge Landfill in Arlington, Oregon for disposal. Sara Marshall
10/21/2019 Offsite Soil or Groundwater Disposal Approved 20 cubic yards of soil containing Trichloroethene and PFOS generated from the EIE405 construction project was transferred to the Columbia Ridge Landfill in Arlington, Oregon for disposal. Sara Marshall
10/21/2019 Offsite Soil or Groundwater Disposal Approved 40 cubic yards of soil containing 1,2,3-Trichloropropane (TCP) and PFOS generated from the EIE405 construction project was transferred to the Columbia Ridge Landfill in Arlington, Oregon for disposal. Sara Marshall
11/12/2019 Offsite Soil or Groundwater Disposal Approved 300 cubic yards of soil containing Naphthalene generated from the EIE405 construction project was transferred to OIT in Moose Creek, Ak for thermal remediation Sara Marshall
11/13/2019 Offsite Soil or Groundwater Disposal Approved 235.4 cubic yards of soil containing PFOS, 1,1,2,2-Tetrachloroethane , 1,1,2-Tricholorethane, 1,2-Dibromoethane, 1,2-Dichloroethane, bromodichloromethane, chloroform, dibromochloromethane, TCE, vinyl chloride, 1,2,3-trichlorobenzene, carbon tetrachloride generated from the EIE385 construction project was transferred to the Columbia Ridge Landfill in Arlington, Oregon for disposal. Sara Marshall
11/25/2019 Report or Workplan Review - Other The Alaska Department of Environmental Conservation (DEC) provided review comments for the Eielson Surface Water and Sediment Sampling Addendum to the Work Plan for Expanded PFOA and PFOS Site Investigation, Eielson AFB, Alaska. The work plan addendum was prepared by Sundance-EA II, LLC (Sundance-EA) to define the objectives, methodology, and the quality assurance (QA) and quality control (QC) procedures for an investigation of PFOA and PFOS in surface water and sediment at Eielson Air Force Base (AFB), and at Bathing Beauty Lake within the community of Moose Creek. The PFOA and PFOS concentrations in sediment and surface water will be used to coordinate and/or guide future surface water and sediment sampling. Dennis Shepard
11/25/2019 Report or Workplan Review - Other Alaska Department of Environmental Conservation (DEC)provided comments for the Draft Birch Lake Surface Water, Sediment, and Soil Sampling Addendum to the Work Plan for Expanded Perfluorooctanoic Acid (PFOA) and Perfluorooctane Sulfonate (PFOS) Site Investigation, Eielson Air Force Base (AFB), Alaska. The purpose of the investigation is to determine the concentrations PFOA and PFOS in surface water and sediment from Birch Lake, and in soil from the vicinity. The PFOA and PFOS concentrations in sediment and surface water will be used to coordinate and/or guide future surface water and sediment sampling. The PFOA and PFOS concentrations in soil will be used to identify the presence of potential source areas. Dennis Shepard
12/5/2019 Meeting or Teleconference Held An annual meeting occurred at EPA Region 10 offices (1200 6th Ave., Seattle, WA 98101) to discuss the Installation Restoration Program at Eielson Air Force Base. Representatives from the Air Force, U.S.EPA, Alaska Department of Natural Resources (DNR) and DEC met with their respective Attorneys and contractors to discuss the implementation of a Critical Water Management Area (CWMA) in the Community of Moose Creek. The CWMA is needed to prevent the use of, and protect against exposure to, perfluorooctanoic acid (PFOA) and perfluoro-octanesulfonate (PFOS) contaminated groundwater. The Air Force announced that a petition for the CWMA had been submitted to DNR. DNR staff clarified the process for establishing the CWMA and timelines for public notification and public comment. Dennis Shepard
12/31/2019 Report or Workplan Review - Other DEC provided comments for the Draft Final Sampling and Analysis Plan (SAP), Project: F-35 Renovate Weapons Load Training Office & Hangar (B1340), Eielson Air Force Base, Revised December 11, 2019 (v4). The SAP is for a planned excavation for the F-35 project and is within the Eielson AFB 100% stockpile area due to the underlying PFAS plume. Dennis Shepard
1/10/2020 Public Notice On January 10, 2020 the Alaska Department of Fish and Game (ADF&G) issued Emergency Order No. 3-R-U-01-20 closing sport fishing at Polaris Lake on Eielson AFB and Kimberly Lake in North Pole. The Emergency order is in response to concentrations of per and poly fluorinated alkyl substances (PFAS)identified above the EPA lifetime health advisory level of 70 parts per trillion. Dennis Shepard
2/20/2020 Report or Workplan Review - Other EPA and DEC jointly approved the Final Addendum #1, Perfluorinated Compounds Eielson Air Force Base and Moose Creek Quality Assurance Project Plan, Eielson Air Force Base (December 2019). The amended Uniform Federal Policy (UFP) Quality Assurance Project Plan (QAPP) Addendum has been prepared to update the Final Perfluorinated Compounds Eielson-Moose Creek Quality Assurance Project Plan Eielson Air Force Base, Alaska (USAF 2018a). This addendum provides revisions to the following UFP-QAPP work sheets:#1 - #7/8 and #16. The Addendum #1 also provides revised tables for the Proposed Field Sampling Program for: Plume Boundary Properties, Granulated Active Carbon (GAC) Treatment Systems, Public Water Supply (PWS) Systems, and Focused System Sampling. Dennis Shepard
3/5/2020 Report or Workplan Review - Other DEC received the Draft Interim Technical Information Report (ITIR) for Fall 2019 Soil Stockpile Characterization Sampling Eielson Air Force Base, Alaska. The interim report documents the results of the sampling of nine of the F35 soil stockpiles located at Eielson AFB performed in late October and early November 2019. DEC also received the laboratory data deliverables including chromatograms and reports for the full suite of Per and poly fluorinated substances (PFAS)analyzed by method 537.1M. Dennis Shepard
3/18/2020 Report or Workplan Review - Other DEC provided review comments for the Draft Interim Technical Information Report, Fall 2019 Soil Stockpile Characterization Sampling March, 2020. The report documents the results of the perfluorooctanoic acid (PFOA) and/or perfluorooctane sulfonate (PFOS) sampling of nine of the F35 soil stockpiles located at Eielson AFB. The stockpile sampling was performed in late October and early November 2019. The interim sampling was completed in order to evaluate the incremental sampling methodology (ISM) approach and revise the integrated Work Plan and Uniform Federal Policy for Quality Assurance Project Plan if needed. Dennis Shepard
3/18/2020 Report or Workplan Review - Other DEC provided comments for the Draft Final Project-Specific Work Plan and Uniform Federal Policy for Quality Assurance Project Plan, Perfluorooctanoic acid (PFOA) and Perfluorooctanesulfonic Acid (PFOS) and Comingled PFOA/PFOS and Petroleum F-35 Soil Stockpiles Characterization Sampling Eielson Air Force Base, Alaska. The integrated Work Plan and Uniform Federal Policy for Quality Assurance Project Plan (UFP-QAPP) is part of the larger F-35A Beddown Program at Eielson Air Force Base (AFB), Alaska. The Work Plan addresses the chemical characterization of soil stockpiles generated during the F-35A Beddown Program. Dennis Shepard
4/9/2020 Update or Other Action On April 9, 2020, the Alaska Department of Fish and Game (ADF&G) issued emergency order No. 3-R-U-02-20. The emergency order rescinds Emergency Order No. 3-R-U-01-20, and opens Polaris Lake to catch-and-release sport fishing. The Emergency order is in response to concentrations of per and poly fluorinated alkyl substances (PFAS)identified above the EPA lifetime health advisory level of 70 parts per trillion. In December 2019, the Board of Fisheries adopted a regulation that allows catch-and-release fishing in stocked waters that have become contaminated. Polaris Lake is a popular sport fishery among residents of Eielson Air Force Base. Dennis Shepard
4/21/2020 Meeting or Teleconference Held A monthly remedial project manager (RPM) meeting was held to discuss various Eielson restoration projects. Garrison Slough remedial investigation and risk assessment step out sample locations were discussed. Status of PFAS investigations and a critical water management area for Moose Creek were also discussed.. Dennis Shepard
4/23/2020 Report or Workplan Review - Other The U.S. Environmental Protection Agency (EPA) and Alaska Department of Environmental Conservation (DEC) jointly approved the Final Project-Specific Work Plan and Uniform Federal Policy for Quality Assurance Project Plan (UFP-QAPP), Perfluorooctanoic acid (PFOA) and Perfluorooctanesulfonic Acid (PFOS) and Comingled PFOA/PFOS and Petroleum F-35 Soil Stockpiles Characterization Sampling Eielson Air Force Base (AFB), Alaska (April 2020). This is an integrated Work Plan and UFP-QAPP for the larger F-35A Beddown Program at Eielson AFB, Alaska. Dennis Shepard
6/9/2020 Report or Workplan Review - Other DEC completed a backcheck review and accepted all revisions to the Draft Final Groundwater Model Summary and Quality Report, Eielson Air Force Base, Alaska, May 2020. Dennis Shepard
6/17/2020 Report or Workplan Review - Other DEC contaminated Sites program received the approved Final Groundwater Model Summary and Quality Report, June 2020, Eielson Air Force Base, Alaska. The numerical groundwater flow model was constructed and calibrated for Eielson Air Force Base in Alaska. The calibrated groundwater flow model was then used for simulation of contaminant fate and transport. The model will provide a tool to evaluate known and suspected groundwater contamination for selected contaminants of concern (COCs), including per- and polyfluoroalkyl substances (PFAS). This model will be updated by the Air Force as additional information concerning permafrost areas and hydro geological conditions become available. Dennis Shepard
6/18/2020 Report or Workplan Review - Other EPA and DEC provided Joint Approval of the Final Groundwater Model Summary and Quality Report, Eielson Air Force Base, Alaska (June 2020). The numerical groundwater flow model was constructed and calibrated for Eielson Air Force Base(EAFB)in Alaska. The calibrated groundwater flow model was then used for simulation of contaminant fate and transport. The model will provide a tool to evaluate known and suspected groundwater contamination for selected contaminants of concern, including per- and polyfluoroalkyl substances (PFAS). It can also be used to support and guide the identification of priority sites at EAFB for additional investigations, remedial activities, programmatic planning, and evaluation of health and environmental impacts on potential receptors. Dennis Shepard
6/18/2020 Update or Other Action EPA and DEC provided Joint Approval of the Interim Technical Information Report, Fall 2019 Soil Stockpile Characterization Sampling, Eielson Air Force Base, Alaska, dated May 31, 2020. The report provides a discussion of field activities performed for stockpiled soils from the Eielson F-35A Beddown Program that may contain PFOA/PFOS or comingled PFOA/PFOS/POL. The report presents the results of the sampling of nine of the F35 soil stockpiles in late October and early November 2019. Dennis Shepard
8/11/2020 Meeting or Teleconference Held DEC, EPA and Air Force remedial project managers met to scope a remedial investigation for the per and poly fluorinated alkyl substances (PFAS) contaminated source areas on Eielson Air Force Base. Sample collection of soil, groundwater, surface water, sediments and biota were discussed. The Air Force confirmed that a contract for the work was awarded on August 4, 2020, and work plans are being prepared. Dennis Shepard
8/25/2020 Meeting or Teleconference Held An Eielson AFB Senior Leaders’ Annual Meeting was held to provide updates to the status of the Environmental Remedial Program at Eielson. Topics for discussion included: Moose Creek water distribution system,PFAS investigation results, DNR Critical Water Management Area, and Environmental Covenant packages for the Community of Moose Creek private properties. Dennis Shepard
9/10/2020 Report or Workplan Review - Other The Alaska Department of Environmental Conservation (DEC) has provided review comments for a Draft Quality Assurance Project Plan, Addendum for Remedial Investigation for PFAS at Various Sites, Eielson Air Force Base and Moose Creek, Alaska, September 2020. The work plan describes proposed field activities associated with an initial groundwater sampling event for a PFAS remedial investigation, and includes collecting groundwater samples for laboratory analysis from 50 existing monitoring, water supply, or drinking water wells located throughout the Eielson Air Force Base installation. Dennis Shepard

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close