Site Report: Hill Fuel Hoonah Airport
| Site Name: | Hill Fuel Hoonah Airport |
|---|---|
| Address: | 808 Airport Drive; Hoonah Airport, Hoonah, AK 99829 |
| File Number: | 1510.38.014 |
| Hazard ID: | 26785 |
| Status: | Active |
| Staff: | Robert Burgess, 9074512153 robert.burgess@alaska.gov |
| Latitude: | 58.099196 |
| Longitude: | -135.411357 |
| Horizontal Datum: | WGS84 |
| ![]() |
![]() | ![]() |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
In September 2017, a Phase II-type investigation at the subject property indicated the presence of diesel range organics and gasoline range organics in soil at concentrations above cleanup levels. The results of the investigation found all GRO concentrations at 1,000 mg/kg or less and DRO was 3,100 mg/kg or less. There is GRO contamination exceeding the cleanup level in between the 2 tanker trailers on the north end of the property. The DRO contamination exceeding ADEC cleanup levels is more widespread, but the majority is on the north side of the metal framed building. Additional DRO contamination above ADEC cleanup levels exists on the west side of the larger tanker trailer and between the 2 tanker trailers. The investigation is underway. The property is used for aircraft fueling with an Av-gas aboveground storage tank (AST) and jet-A AST. A fuel tanker truck is also frequently parked at the site.
Action Information
| Action Date | Action | Description | DEC Staff |
|---|---|---|---|
| 10/10/2017 | Site Added to Database | A new site has been added to the database | Mitzi Read |
| 10/11/2017 | Potentially Responsible Party/State Interest Letter | Sent this date. | Danielle Duncan |
| 11/30/2017 | Update or Other Action | Sent a work plan request to delineate the petroleum contamination on site this date. Prior data received found all gasoline range organics (GRO) concentration at 1,000 mg/kg or less and diesel range organics (DRO) was 3,100 mg/kg or less. There is GRO contamination exceeding the cleanup level in between the 2 tanker trailers on the north end of the property. The DRO contamination exceeding ADEC cleanup levels is more widespread, but the majority is on the north side of the metal framed building. Additional DRO contamination above ADEC cleanup levels exists on the west side of the larger tanker trailer and between the 2 tanker trailers. | Danielle Duncan |
| 1/8/2018 | Update or Other Action | Rec'd a phone call from the responsible party and resent the undeliverable letter (work plan request) via email. | Danielle Duncan |
| 1/19/2018 | Meeting or Teleconference Held | Teleconference with A. Harder and E. Donat to discuss steps moving forward. E. Donat will prepare a conceptual site model and may propose alternative cleanup levels. | Danielle Duncan |
| 2/20/2018 | Update or Other Action | Spoke to the consultant - there is a drinking/agriculture well near the site that was recently installed. The conceptual site model that will be provided will reflect this. | Danielle Duncan |
| 4/4/2018 | Document, Report, or Work plan Review - other | Responded and concurred (this date) with a memo regarding site characterization and appropriate cleanup levels from Chilkat Environmental via electronic mail dated March 12, 2018. | Danielle Duncan |
| 6/29/2018 | Update or Other Action | Spoke to the consultant and a work plan is in the works. He noted that bedrock is present at about 4.5 ft. belowground and at that point there are large rocks which will prevent further drilling - will use an excavator. The vertical and lateral distribution will be delineated. The analyses will be PAHs, BTEX, VOCs, in addition to the petroleum ranges. RRO will not be analyzed due to low DRO values and biogenic wetland interference. His site visit indicated no sheen on the creek and that snow dumping occurs in the creek and the 2 culverts. I let him know that I would likely do a site visit. | Danielle Duncan |
| 7/3/2018 | Site Characterization Workplan Approved | Approved the Chilkat Environmental work plan to delineate the petroleum contamination lateraly and vertically. Chilkat Environmental will advance 6 to 12 test pits using a mini excavator or a hand auger and collect 50 samples. These will be analyzed for ambient odor and sheen. Half of these samples will be field screened using a photoionization detector (PID) and 10 samples (having the highest PID results) will be submitted to a laboratory for analysis of gasoline range organics (GRO) and diesel range organics (DRO). Two samples (having the highest PID results) will also be analyzed for lead, volatile organic compounds (VOCs), and semivolatile organic compounds (SVOCs) including polycyclic aromatic hydrocarbons (PAHs). The samples may be held in the laboratory for total organic carbon (TOC) analysis and these results may be used to calculate a site-specific alternative cleanup level. | Danielle Duncan |
| 8/15/2018 | Site Characterization Report Approved | Approved the Characterization for Hill Fuel Hoonah Airport this date. The results found petroleum contamination above ADEC cleanup levels in test pits A and B only which are located on the north end of the property. In this area, DRO was present up to 2,800 milligrams per kilogram (mg/kg). GRO was also present up to 360 mg/kg and the prior ESA found GRO up to 1,000 mg/kg. Other petroleum constituents above ADEC cleanup levels were naphthalene and 1,2,4-trimethylbenzene. The contamination appears to continue north of the site on to private property and potentially below the airport apron; these areas are inaccessible. The requested and approved remedy is site closure with the institutional control being an asphalt cap once an asphalt batch plant is available in Hoonah. The site will remain open on the CS database until the capping is complete. | Danielle Duncan |
Contaminant Information
| Name | Level Description | Media | Comments |
|---|
Control Type
| Type | Details |
|---|
Requirements
| Description | Details |
|---|
There are no documents for this site report.
No associated sites were found.