Action Date |
Action |
Description |
DEC Staff |
11/26/1999 |
Site Added to Database |
Petroleum, gasoline and diesel. |
Sally Schlichting |
11/29/1999 |
Site Ranked Using the AHRM |
Initial ranking. |
Sally Schlichting |
12/1/1999 |
Update or Other Action |
Site characterization work requested to be performed after area was identified during Skagway upper tank farm assessment. |
Sally Schlichting |
5/7/2001 |
Cleanup Level(s) Approved |
Method 2 soil cleanup levels are approved. |
Anne Marie Palmieri |
5/7/2001 |
Site Characterization Report Approved |
Report approved this date. |
Anne Marie Palmieri |
5/7/2001 |
Cleanup Plan Approved |
Air sparging system will be installed. Additional characterization samples at the face of the bluff requested. |
Anne Marie Palmieri |
11/21/2002 |
Update or Other Action |
Michael Katzie of the Skagway Traditional Council wants to be kept up to date with this cleanup. |
Anne Marie Palmieri |
3/21/2003 |
Site Characterization Report Approved |
Supplemental Investigation report reviewed and approved. |
Anne Marie Palmieri |
5/27/2003 |
Meeting or Teleconference Held |
Meeting held with White Pass and Golder in Skagway. |
Anne Marie Palmieri |
5/27/2003 |
Update or Other Action |
A point of compliance for meeting AWQS was placed on the beach and the remedial action objective (RAO) for benzene during the air sparging was put off until Golder does additional monitoring. |
Anne Marie Palmieri |
2/5/2004 |
Update or Other Action |
Air sparging system was not installed last summer. Golder hopes for spring start-up. |
Anne Marie Palmieri |
2/10/2004 |
Update or Other Action |
City wants to replace timber seawall and add an additional 50 feet to the roadbed on the harbor side. Sampling of proposed dredging area to occur in 2/04. |
Anne Marie Palmieri |
6/4/2004 |
GIS Position Updated |
GPS reading obtained |
Bill Janes |
6/4/2004 |
Update or Other Action |
Project manager transition site visit. |
Bill Janes |
7/20/2004 |
Update or Other Action |
CR check received - $258.12. Check previously received for $1,490.79 |
Bill Janes |
10/27/2004 |
Update or Other Action |
CR check received - $75 |
Bill Janes |
9/5/2006 |
Update or Other Action |
Site visit. City upgrades to seawall and road nearly completed.
Inspected SVE/Air Sparge system. System switched automatically depending on tidal level. Sparging occurs during high tide and vapor extraction during lower tidal levels. System is turned off during the winter months as there is no one to maintain it. About 700 gallons recovered to date. |
Bill Janes |
2/26/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Bill Janes |
9/10/2008 |
Meeting or Teleconference Held |
Meeting via teleconference with Ed Hanousek (White Pass) and Gary Hamilton (Golder Associates) regarding the status of this site. The air sparging/soil vapor extraction unit has been running all summer and will continue to until the end of the season. One well is showing product and is being bailed. No other wells are showing non-aqueous phase liquids. Approximately 1,000 gallons has been recovered to date from this site. Groundwater modeling has been done. Not seeing much mass fluxing into the harbor. |
Evonne Reese |
9/26/2008 |
Site Visit |
Site visit conducted along with other White Pass sites. The air sparging/vapor extraction system will continue to run until mid October when it will be shut down for the winter. |
Evonne Reese |
7/20/2010 |
Update or Other Action |
Project management transfered to Bruce Wanstall; dissolved hydrocarbon concentrations in groundwater were generally lower in 2005 than the two previous sampling summary reports. Air sparging and soil vapor extraction system operation are geared to reduce the petroleum contaminant mass. LNAPL recovery is done by hand during summer months. |
Bruce Wanstall |
9/8/2011 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73670 Former Bulk Fuel ASTs. |
Bruce Wanstall |
5/3/2012 |
Site Characterization Report Approved |
DEC has reviewed and approved the Golder 2011 EMP Report. The DEC approval letter was sent today by regular mail to White Pass & Yukon Route representative Ed Hanousek. The DEC has requested action by White Pass at this Site in 2012. Most are recommended by Golder in the Report but a few of the requests go beyond that. DEC requests access wells be installed for continuous recovery of free product on groundwater and the addition of water wells up-gradient and down-gradient of the contaminant plume. |
Bruce Wanstall |
9/6/2012 |
Site Visit |
DEC traveled from Juneau to Skagway and attended a meeting with representatives of White Pass and Yukon Route and consultant Golder & Associates. A site visit was performed by the attendees and plans were made for DEC and Golder to return to the site for scheduled sampling site activity in fall 2012. |
Bruce Wanstall |
11/16/2012 |
Site Visit |
DEC traveled to Skagway to observe free product recovery from groundwater wells during the lowest slack tide in November, 2012, by consultant Golder Associates for RP White Pass and Yukon Route. Approximately 1/2 gallon of free phase oil was recovered in the first bailing on the evening of the 15th from well MW00-37; a second bailing on the evening of the 16th will be conducted to derive an estimated recharge rate. The oil appeared to be weathered #2 diesel which is consistent with groundwater sampling chemical analysis. |
Bruce Wanstall |
4/15/2013 |
Meeting or Teleconference Held |
DEC held a teleconference meeting with Golder to discuss the approval letter requests for future site activity at the Skagway Wharf Tank site. Golder agreed to replace MW00-044 with a free product recovery well and DEC agreed to not require water well installation behind the sheet pile bulkhead on the foreshore of the Small Boat Harbor. Golder anticipated that site activity in 2013 will begin in late May and will carry over into June. |
Bruce Wanstall |
8/12/2013 |
Meeting or Teleconference Held |
DEC traveled to Skagway to attend meetings with representatives of White Pass and Yukon Route to assist with the planning and coordination of site activity by consultant Golder Associates at the site. DEC requested White Pass submit a report for the well sampling performed at the site in 2013. |
Bruce Wanstall |
10/24/2013 |
Update or Other Action |
DEC requested by electronic mail that Golder submit a reporting schedule for 2013 site activity at the Wharf Tanks Site. In a meeting in fall 2012 DEC discussed with Golder and White Pass the problems inherent with long periods of no updates or reports from environmental consultants performing work on active contaminated sites. DEC and Golder discussed the specific work plan expectations for the Wharf Tanks site in April 2013. The same work plan expectations were discussed with the new supervising manager for White Pass (John Finlayson) in August 2013. Shortly after today's email was circulated Mr. Finlayson contacted DEC to state that going forward he and Ed (Hanousek) would improve the flow of information to the department regarding site activity. |
Bruce Wanstall |
10/28/2013 |
Document, Report, or Work plan Review - other |
In fall 2013, Golder submitted a letter Work Plan summarizing collaboration with DEC to plan a schedule for future site activity appropriate to the status of the cleanup process at the Site. DEC approved the proposal for Golder to perform annual groundwater monitoring in fall, 2013, then after collecting a sample from well MW-0044 in 2014, replace the well with a 6-8-inch product recovery well that will span depths of high and low tide groundwater levels. Golder planned to complete the new well with a flush mount road-box to accommodate seasonal high road traffic near the Small Boat Harbor and the eastern-shore cruise ship dock. |
Bruce Wanstall |
4/2/2014 |
Document, Report, or Work plan Review - other |
In spring 2014 DEC verbally agreed to modifications to the approved 2013 Golder Work Plan and inquired on progress compiling monitoring data into an environmental monitoring report. Golder stated that a report is in progress and efforts continue to schedule well drilling at Skagway sites in 2014 to replace monitoring well MW00-44 with a recovery well. |
Bruce Wanstall |
6/11/2014 |
Site Visit |
DEC met with White Pass President John Finlayson, Superintendent of Rail Operations Mark L. Taylor, Director of Safety & Labor Relations Tyler Rose, and Golder Associates Senior Hydrologist Tamra Reynolds and Golder Principal Gary J. Hamilton at White Pass offices in Skagway. DEC agreed that correspondence, site work and reporting by Golder for this Site is acceptable. New well installation is planned in May, 2015. |
Bruce Wanstall |
8/29/2014 |
Update or Other Action |
Golder installed the product recovery well in May, 2014, and plans to sample all wells in September 2014. Although Golder has compiled an environmental sampling report summarizing groundwater monitoring data since the report titled: 2006 to 2009 Environmental Monitoring Program Former Wharf Tank Site (Golder 2011), DEC agreed to postpone completion to allow addition of the 2014 data into a Summary Report in 2015. |
Bruce Wanstall |
9/24/2015 |
Document, Report, or Work plan Review - other |
DEC letter to White Pass & Yukon Route Railway provides approval for: 2011 to 2014, Environmental Monitoring Program, ADEC File# 1526.38.009 Report (Report), dated April 24, 2015. Golder and Associates Inc. completed the Report documenting results of environmental sampling and product recovery at the Skagway Wharf Tanks Area Site between October 2011 and September 2014. DEC agreed with conclusions in the Report and recommendations to employ a passive product skimmer in the new product recovery wells with monitoring and measurements by White Pass staff and continuing with annual groundwater sample monitoring. DEC requested Golder submit a scheduled plan for the continuous monitoring of the recovery wells by White Pass staff. The next groundwater sample monitoring is scheduled for fall 2015. |
Bruce Wanstall |
8/15/2016 |
Document, Report, or Work plan Review - other |
DEC reviewed and approved the 2015 Wharf Tanks Environmental Monitoring Report completed by Golder and Associates for the White Pass and Yukon Route Railway. Golder conducted annual groundwater sampling at the Wharf Tanks Site on October 8, 2015 at monitor wells MW00-37, MW00-38, MW00-39, MW00-40, WW0041, MW00-42, MW00-44, MW00-45, and MW14-02. Groundwater samples were not collected from well MW00-46 as this well was blocked at approximately four feet below grade and from MW00-43 as this well was not accessible due to a locking road box that could not be opened. In regard to wells MW00-40 and MW00-44, which have historically had measureable LNAPL, Golder collected samples immediately after the removal of a product skimmer. |
Bruce Wanstall |
10/10/2017 |
Update or Other Action |
Staff assigned changed from Bruce Wanstall to Kara Kusche. |
Kathryne Roldan |
5/10/2019 |
Document, Report, or Work plan Review - other |
ADEC reviews and provides comment of the report titled "Results of the 2016 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route, Former Wharf Tanks Site, Skagway, Alaska" dated September 22, 2017. Benzene, GRO, DRO, and RRO remain above ADEC cleanup levels in at least one well each. Contaminant concentrations are a mix of decreasing and stable. |
Kara Kusche |
5/28/2019 |
Document, Report, or Work plan Review - other |
ADEC has reviewed the report titled "Results of the 2017 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route Former Wharf Tanks Site, Skagway, Alaska" dated December 11, 2018. Benzene, ethylbenzene, xylene, GRO, DRO, and RRO remain above ADEC cleanup levels in at least one well each. Contaminant concentrations are a mix of decreasing and stable. |
Kara Kusche |
7/9/2019 |
Site Characterization Report Approved |
ADEC approves the report titled "Results of the 2016 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route, Former Wharf Tanks Site, Skagway, Alaska" dated July 5, 2019. |
Kara Kusche |
7/10/2019 |
Site Characterization Report Approved |
ADEC approves the report titled "Results of the 2017 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route, Former Wharf Tanks Site, Skagway, Alaska" dated July 9, 2019. |
Kara Kusche |
7/23/2019 |
Document, Report, or Work plan Review - other |
ADEC provides comment on the report titled "Results of the 2018 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route Former Wharf Tanks Site, Skagway, Alaska" dated July 11, 2019. Overall, groundwater concentrations are decreasing since monitoring began, but DRO and RRO in some wells appear to be more recently increasing. Benzene, ethylbenzene, xylene, GRO, DRO, and RRO remain above cleanup levels in one or more wells each. |
Kara Kusche |
7/17/2020 |
Site Characterization Report Approved |
ADEC approves the 2018 groundwater monitoring report. |
Jessica Hall |
7/22/2020 |
Document, Report, or Work plan Review - other |
ADEC provides comment on the 2019 groundwater monitoring report. |
Jessica Hall |
9/9/2020 |
Site Characterization Report Approved |
ADEC approves the report titled "Results of the 2019 Groundwater Monitoring Program" dated July 06, 2020. ADEC concurs with the recommendations presented and the next groundwater monitoring event to be performed in fall 2020. |
Jessica Hall |
6/15/2022 |
Site Characterization Report Approved |
DEC has reviewed the report titled "Results of the 2021 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route Former Wharf Tanks Site, Skagway, Alaska" dated May 2022. Five of the nine wells proposed were sampled in June 2021. Groundwater was approximately 17.45-24.25 feet bgs with flow direction toward Taiya Bay. Samples were analyzed for BTEX, GRO, and RRO. Two wells MW00-41 and MW14-01 had exceedances of GRO, benzene, and ethylbenzene. Five of the wells had exceedances of DRO and four for RRO. Trends for contaminants are mostly decreasing or stable, however RRO is increasing. |
Lisa Krebs-Barsis |
9/1/2023 |
Site Characterization Report Approved |
DEC has reviewed the report titled "Results of the 2022 Groundwater Monitoring Program, ADEC File Number 1526.38.009, White Pass & Yukon Route Former Wharf Tanks Site, Skagway, Alaska" dated July 2023. Five of the nine wells proposed were sampled in November 2022. Groundwater was approximately 15.9-19.8 feet bgs with flow direction toward Taiya Bay. Samples were analyzed for BTEX, GRO, and RRO. Two wells MW00-45 had an exceedance of benzene for the first time since 2015. Both of those wells also exceeded for ethylbenzene
and GRO. MW00-45 had an exceedance of xylene. MW14-01 also had and exceedance of benzene. Five of the wells had exceedances of DRO and three for RRO. Trends for contaminants are mostly decreasing or stable, however RRO is increasing. |
Lisa Krebs-Barsis |
7/22/2024 |
Site Characterization Report Approved |
Reviewed/approved the "2023 Groundwater Monitoring and Sampling Program" report, dated June 18, 2024. Seven of the nine wells proposed were sampled in July 2023. Groundwater was approximately 17.52-21.96 feet bgs with flow direction toward Taiya Bay. Samples were analyzed for GRO, DRO, RRO, and BTEX. Four of the seven wells sampled exceeded cleanup levels: MW00-37 (DRO); MW00-38 (DRO and RRO); MW00-45 (GRO, DRO, benzene, ethylbenzene, and xylene); MW14-01 (GRO, DRO, RRO, benzene, and ethylbenzene). Product was recovered from MW00-40 at 6.1 ounces, which is an increase from 2022. Product recovery well MW00-44 was not monitored due to inaccessibility. Trends for contaminants are mostly decreasing or stable, however RRO is increasing. |
Stacee Henderson |