Site Report: Everts Air Fuel Mail Trail Facility
Site Name: | Everts Air Fuel Mail Trail Facility |
---|---|
Address: | 5449 Mail Trail Road, Fairbanks, AK 99709 |
File Number: | 100.38.284 |
Hazard ID: | 26953 |
Status: | Active |
Staff: | Shawn Tisdell, 9074512752 shawn.tisdell@alaska.gov |
Latitude: | 64.814230 |
Longitude: | -147.883724 |
Horizontal Datum: | WGS84 |
![]() | ![]() |
![]() | ![]() |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
In September, 2018 contaminated soil was encountered during installation of public water utility line. (The water line was being installed to provide an alternate water source due to prior detection of Perfluorooctanesulfonic Acid (PFOS) and Perfluorooctanoic Acid (PFOA) in the potable on-site well during an area-wide investigation and attributed to fire fighting foam used at the Fairbanks International Airport.) Soil from the initial excavation was stockpiled on site. Sample analyses confirmed diesel range organics (DRO); gasoline range organics (GRO); benzene, toluene, ethylbenzene, and xylenes (BTEX); and several other volatile organic compounds (VOCs)and polyaromatic hydrocarbon (PAHs) in soil and groundwater above DEC cleanup levels. Additional excavation of the top two feet of soil (~100 cubic yards) was conducted in October and the excavated soil was stockpiled off site at 3374 Van Horn Road. The source of the contamination is unknown. This site is on the same property as Hazard ID 24339, file no. 100.26.058, Crowley Mail Trail Facility.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
9/19/2018 | Potentially Responsible Party/State Interest Letter | Potentially Responsible Party / State Interest Letter sent to Everts Air Fuel by PPRP staff Jill Stockbridge. | Mitzi Read |
12/12/2018 | Spill Transferred from Prevention Preparedness and Response Program | Spill transferred by PPRP staff Jill Stockbridge. Spill no. 18309925502; spill date = 9/12/18; substance = unknown; quantity = unknown; PPRP file no. 100.02.155; description: contaminated soil (suspected petroleum) was encountered during installation of a water line, source is unknown. | Mitzi Read |
12/18/2018 | Site Added to Database | A new site has been added to the database | Mitzi Read |
7/24/2019 | Workplan Requested | Site characterization work plan requested to delineate contamination at the site. Work plan submittal deadline is August 26, 2019. | Shawn Tisdell |
9/3/2019 | Document, Report, or Work plan Review - other | DEC received "Everts Air-Water Line Excavation Contaminated Soil and Groundwater Delineation Corrective Action Work Plan" dated August 29, 2019. A strategy is outlined in this work plan to collect soil samples and install and/or use existing monitoring wells to delineate the degree and extent of soil and groundwater contamination at the site. | Shawn Tisdell |
7/13/2020 | Update or Other Action | Site characterization work plan was review, a letter was sent out requesting modifications to the work plan before it could be approved. | Shawn Tisdell |
5/25/2021 | Meeting or Teleconference Held | ADEC staff met with Everts Air representative and discussed management of stock piles and prioritizing response action for contaminated sites that Everts Air is managing. Both parties will meet again in a couple weeks to discuss more specific site cleanup action. | Shawn Tisdell |
8/25/2022 | Document, Report, or Work plan Review - other | Approved 8/11/2022 Work Plan for Stockpile Sampling. This plan provided a soil sampling strategy for two stockpiles to determine a treatment or disposal strategy. A 280 cubic yard (CY) stockpile was created following excavation of contaminated soil discovered during installation of a water line in 2019. A 50 CY stockpile was created following excavation of soil contaminated following the release of Jet A from an above ground tank discharge, PPR Spill#18309925502. Screening samples and analytical samples will be collected according to Table 2A of the ADEC 2022 Field Sampling Guidance. | Shawn Tisdell |
6/21/2023 | Meeting or Teleconference Held | DEC project manager met with Everts Air Ground Operations manager to discuss four active contaminated sites including this one, which Everts is the responsible party. The general site cleanup process and site closure decision milestones were discussed. Contaminated soil stockpile management was discussed. A request was made by the DEC to determine current conditions of monitoring wells at each site and to develop a work plan for each site that leads towards site closure milestones. | Shawn Tisdell |
Contaminant Information
Name | Level Description | Media | Comments |
---|
Control Type
Type | Details |
---|
Requirements
Description | Details |
---|
There are no documents for this site report.
Hazard ID | Site Name | File Number |
---|---|---|
24339 | Crowley Mail Trail Facility | 100.26.058 |