Skip to content Skip to content

Site Report: MOA AWWU Maintenance and Operations Facility Diesel AST Overfill

Site Name: MOA AWWU Maintenance and Operations Facility Diesel AST Overfill
Address: 325 East 94th Court, Anchorage, AK 99519
File Number: 2100.38.574
Hazard ID: 26995
Status: Active
Staff: Mollie Dwyer, 9074651076 mollie.dwyer@alaska.gov
Latitude: 61.136926
Longitude: -149.876167
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

On June 15, 2016 approximately 200-250 gallons of diesel were released to the ground surface during a fuel transfer to a 10,000-gallon double-walled diesel aboveground storage tank located on a concrete pad north of the Anchorage Water and Wastewater Utility (AWWU) maintenance and operations facility. It was determined that the fill gauge and overfill alarm were not working. Initial remediation activities included excavation of ~200 tons of contaminated soil, along with free product recovery. The concrete tank support pad was left in place with contamination remaining underneath. Final excavation depths ranged from 12 to 84 inches below ground surface. Subsequent analytical sampling in 2018 confirmed diesel range organics (DRO) remain in soil and groundwater above DEC cleanup levels.

Action Information

Action Date Action Description DEC Staff
2/13/2019 Spill Transferred from Prevention Preparedness and Response Program Spill transferred by PPRP staff Gay Harpole. Spill no. 16239916701; spill date = 6/15/16; substance = diesel; quantity = ~200-250 gallons; source = overfill during a fuel transfer to a 10,000-gallon aboveground tank used to supply diesel to a fueling dispenser for the vehicle fleet. Mitzi Read
2/14/2019 Site Added to Database A new site has been added to the database Mitzi Read
5/6/2019 Potentially Responsible Party/State Interest Letter Potentially responsible party (PRP) letter emailed and mailed via USPS Certified Mail to RP, consultant, and ADEC SPAR Cost Recovery. Work plan requested by June 15, 2019. Amy Rodman
5/6/2019 Workplan Requested Work plan requested within Potentially responsible party (PRP) letter, work plan due June 15, 2019. Amy Rodman
6/7/2019 Site Characterization Workplan Approved ADEC Contaminated Sites Program has reviewed and approved the “Work Plan for Groundwater Sampling Activities, 325 East 94th Court, Anchorage, Alaska” (Work Plan) for the MOA – AWWU Maintenance and Operations Facility AST Overfill site in Anchorage, dated May 31, 2019. The work plan was submitted via email on June 3, 2019 by Shannon & Wilson, Inc. Proposed activities generally consist of sampling existing onsite groundwater monitoring wells for laboratory analysis for diesel range organics, volatile organic carbons, and polynuclear aromatic hydrocarbons (MW-1 only), along with managing investigation-derived waste. ADEC also requested GRO analysis for groundwater samples. Amy Rodman
10/16/2019 Site Characterization Report Approved ADEC has reviewed and approved the “Groundwater Sampling Activities, 325 East 94th Court, Anchorage” (Report) for the MOA AWWU Maintenance and Operations Facility Diesel AST Overfill site in Anchorage, AK dated October 7, 2019. The report was submitted to ADEC via email on October 8, 2019 by Shannon & Wilson, Inc. (Shannon & Wilson). Field activities were conducted on June 14 and September 21, 2019 and generally consisted of conducting monitoring well surveys and sampling groundwater for laboratory analysis. A work plan to address the groundwater ingestion exposure pathway is due November 29. Amy Rodman
11/25/2019 Update or Other Action Per consultant's email: fueling station relocation is planned for 2021. Work plan in progress and will include groundwater characterization. Amy Rodman
5/15/2020 Update or Other Action Nearby contamination discovered during a geotechnical exploration in support of a building design project. See email in file. Kara Kusche
8/14/2020 Meeting or Teleconference Held Teleconference to discuss site delineation and plans for future work. Also discussed a work plan for a new source area that was located during geotechnical investigation. The new source will be issued a separate hazard ID once information is submitted. Jamie Grant
10/9/2020 Site Characterization Workplan Approved The site characterization work plan received on October 6, 2020 has been approved. Jamie Grant
3/2/2021 Document, Report, or Work plan Review - other A Final Site Characterization Report was submitted on behalf of AWWU on March 2, 2021 for work conducted in October 2020. The field activities consisted of advancing four soil borings, installing three groundwater monitoring wells using a GeoProbe® direct-push drill rig to an approximate depth of approximately 10 feet below ground surface (bgs). Analytical soil and groundwater samples were collected in an effort to delineate the area of contamination. Borings B12, B13, and B14 were advanced northeast, south, and southwest of the ASTs, respectively. Boring B15 was advanced northwest of Well MW-2. Elevated field screening results or evidence of contamination (fuel odors, staining, etc.) were not observed. Therefore, step-out borings were not advanced. The soil was collected from each boring in 5 foot sections which was then divided into 2.5 foot intervals for screening and sampling. Four analytical soil samples were selected for laboratory analysis based on the highest field screening results. Borings B12, B13, and B15 were then advanced to approximately 14 to 15 feet bgs to facilitate the installation of groundwater monitoring wells (MW-4, MW-5, and MW-6). Analytical results for soil indicate detectable levels of DRO, trichlorofluoromethane, benzo[a]pyrene, benzo[g,h,i]perylene, fluoranthene,indeno[1,2,3-c,d]pyrene, phenanthrene, and/or pyrene in at lease one soil sample, however, all sample results were less than the most stringent ADEC Method Two cleanup levels. The remaining tested analytes were not detected in the soil samples. Analytical results for groundwater indicate Duplicate Samples MW1 and MW11 contained concentrations of DRO (maximum of 8,460 micrograms per liter [µg/L]) and naphthalene (maximum of 2.41 µg/L) that exceed the ADEC Table C cleanup levels of 1,500 µg/L and 1.7 µg/L, respectively. Sample MW2 contained 0.386 µg/L benzo[g,h,i]perylene and 0.216 µg/L indeno[1,2,3-c,d]pyrene, which exceed the ADEC Table C cleanup level of 0.26 µg/L and 0.19 µg/L, respectively. The remaining tested analytes were not detected at concentrations exceeding the ADEC Table C cleanup levels. MW-4, MW-5, and MW-6 did not contain contaminants above cleanup levels. Based on information in this report the extent of soil and groundwater contamination has been somewhat defined. Additional groundwater sampling will be needed to evaluate the concentration and the size of the dissolved plume over time. Jamie Grant
3/12/2021 Site Characterization Report Approved ADEC had reviewed and approved the Site Characterization Report received on March 2, 2021. Jamie Grant
5/26/2021 Long Term Monitoring Established ADEC has reviewed and approved a Quarterly Groundwater Monitoring Plan submitted on this day with the following condition: all samples must also be analyzed for VOCs. Samples will be collected and analyzed (DRO, VOCs, PAHs) from 6 monitoring wells each quarter beginning June 2021 and ending March 2022. Jamie Grant
3/25/2022 Offsite Soil or Groundwater Disposal Approved Approved transport for a 55-gallong drum of petroleum-contaminated purge water at the US Ecology Viking Facility. Janice Wiegers
8/10/2022 Document, Report, or Work plan Review - other ADEC approved the 2021/2022 quarterly groundwater monitoring report received on July 11, 2022. Monitoring Wells MW-1, MW-2, MW-4, MW-5, and MW-6 were sampled in June, September, and December 2021, and February 2022. Well MW-3 was not located during the sampling events and could not be sampled. DRO was detected in groundwater during three of the sampling events above cleanup levels. Naphthalene (maximum of 2.35 µg/L) benzo(a)pyrene, benzo[g,h,i]perylene, and indeno[1,2,3-c,d]pyrene were detected above cleanup levels in MW-1 during the June 2021 sampling event. Additional groundwater sampling at the site to further evaluate contaminant trends has been recommended. Brandi Tolsma
10/20/2022 Document, Report, or Work plan Review - other On this date, ADEC approved work plan to conduct annual groundwater monitoring in 2022 or 2023 depending on snow conditions. Groundwater samples will be collected from MW-1 through MW-6. One analytical sample will be collected from each well and analyzed for diesel range organics (DRO) by Alaska Method (AK) 102. The samples collected from Wells MW-1 and MW-2 will also be analyzed for volatile organic compounds (VOCs) by Environmental Protection Agency (EPA) Method 8260D and PAHs by EPA Method 8270D SIM. Based on the Mann-Kendall analysis of past sampling events, the DEC approves the request to reduce the sampling frequency from quarterly to annual. Brandi Tolsma
3/23/2023 Offsite Soil or Groundwater Disposal Approved Approved transport of 1 55-gallon drum of petroleum contaminated water to the Viking Drive Facility. Janice Wiegers
4/24/2023 Document, Report, or Work plan Review - other Groundwater sampling report was submitted by Shannon & Wilson. Monitoring wells MW-1, MW-2, MW-4, MW-5, and MW-6 were sampled in February. DRO remained in MW-1 and MW-2 above cleanup levels. Benzo(a)pyrene and benzo(g,h,i)perylene also exceeded cleanup levels in MW-2. Janice Wiegers
10/10/2023 Document, Report, or Work plan Review - other On this date, ADEC approved the soil and groundwater management plan submitted 09.19.2023 to support construction activities at the site. The project includes removing the two existing above ground tanks (ASTs), the fueling facility and supporting infrastructure, and constructing a new facility with three new ASTs to south of the existing ASTs. The project involves trenching and excavation to replace piping, utilities, storm drain and concreted pads, and associated pavements will also be removed and replaced. Monitoring wells (MWs) MW-1 through MW-6 are located within the project area and will be decommissioned. ADEC requests a workplan for ongoing groundwater monitoring at the site once the project reaches completion. Mollie Dwyer

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details
Hazard ID Site Name File Number
24744 MOA AWWU Operations Facility 1999 Used Oil Tank removal 2100.26.331
25575 MOA - AWWU - Maintenance Facility (1997 Tank Removal) 2100.26.569

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close