Action Date |
Action |
Description |
DEC Staff |
8/28/1997 |
Interim Removal Action Approved |
RP placed boom and sorbant pads in drainage areas and in nearby Keku Straits where sheen was noted. Due to simultaneous activities contributing to sheening, source areas were multiple and difficult to determine. Drainage areas were continuously monitored. Some contribution from the power plant appears likely. |
Sally Schlichting |
9/2/1997 |
Update or Other Action |
Site visit conducted with USCG. |
Sally Schlichting |
9/11/1997 |
Update or Other Action |
(Old R:Base Action Code = RPL1 - Initiate Dialog with RP). Letter sent to RP requesting cleanup plan. |
Sally Schlichting |
11/5/1997 |
Site Added to Database |
Residual range petroleum contamination. |
Sally Schlichting |
1/5/1998 |
Update or Other Action |
Interception trench rerouting drainage on north side of the power plant building was installed in the contaminated area. |
Sally Schlichting |
3/26/1998 |
Cleanup Plan Approved |
Approval letter this date for asphalt sub-base encapsulation of 90 of the total volume of 165 cubic yards of petroleum contaminated soil excavated from the power plant property during the site cleanup. |
Sally Schlichting |
12/7/2000 |
Site Ranked Using the AHRM |
Initial ranking based on data available in database. |
Former Staff |
1/11/2006 |
Update or Other Action |
Review file for site cleanup oversight --> Site Assessment/ Cleanup Report states petroleum contamination remained near the road, access gate and along the power plant building foundation on the northwest side. Contamination was consistently found at a hardpan gravel layer at 4 to 5 feet below ground surface; a french drain on the west side of the building foundation diverts surface drainage toward the south side and away from the north side of the power plant where residual soil contamination is not accessible but is stabilized. |
Bruce Wanstall |
7/31/2007 |
Update or Other Action |
ETM ranking found that surface soil and subsurface soil are the controlling exposure pathways at the site. The site cleanup remedy to move the contaminated material from the site to a biocell at a controlled site is effective. Controlling subsurface excavation and accessing ground water on the property is an integral part of the cleanup remedy. |
Bruce Wanstall |
7/31/2007 |
Exposure Tracking Model Ranking |
Intitial Ranking Complete for Source Area: 73687 (Autogenerated Action) |
|
8/1/2007 |
Update or Other Action |
Contacted the former Tlingit-Haida Regional Electrical Authority office in Auke Bay; is now the Inside Passage Electrical Authority; to obtain information on the power plant landowner and operator in Kake. The biocell has been maintained since 1997, awaiting remedial disposal options for incorporation into road construction; 2001 soil sample data indicated minor concentrations of diesel remained. |
Bruce Wanstall |
6/1/2009 |
Update or Other Action |
Contact message left with T-HREA and CIty of Kake to try and resolve what remains to be done and where. |
Bruce Wanstall |
9/11/2013 |
Update or Other Action |
Staff changed from Erik Norberg to Denise Elston. |
Kristin Thompson |
3/25/2014 |
Update or Other Action |
Spoke to B. Shaw @ Inside Passage Electric Co-op and he is going to contact an environmental consultant and submit a workplan to sample the biocell. The last data we have is from 2001. Depending on results, we may continue bioremediation or close the site out. Another possibility is entrenching the contaminated soil into concrete for a new powerhouse building in 2-3 years. |
Danielle Duncan |
3/27/2014 |
Potentially Responsible Party/State Interest Letter |
Sent a PRP letter to Inside Passage Electric Co-op. |
Danielle Duncan |
4/28/2014 |
Update or Other Action |
Spoke with IPEC; they said CDI would be doing work there in August. I reminded him that a workplan would need to be submitted and approved before any work was done. |
Danielle Duncan |
5/6/2014 |
Update or Other Action |
Spoke to CDI and they plan to go out and sample biocell in August. RP took soil samples of the biocell (8) on their own and had analyzed. Only 1 sample (~600) was > migration to groundwater cleanup. Although DEC cannot use this data, will likely close site out once a workplan and new data are approved. |
Danielle Duncan |
7/23/2014 |
Update or Other Action |
Spoke to CDI and they have been contacted by the RP to sample the biocell. CDI will submit a work plan via email soon. |
Danielle Duncan |
11/7/2014 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73687 Oil Transfer Spill Event. |
Danielle Duncan |
11/10/2014 |
Update or Other Action |
Per CDI, the RP is planning to till and fertilize the biocell and then be in touch with them. |
Danielle Duncan |
1/7/2015 |
Update or Other Action |
Spoke to RP and the biocell has been tilled prior to the ground freezing for winter and they plan on contacting their consultant this spring to sample it. |
Danielle Duncan |
2/9/2015 |
Update or Other Action |
No work plan in the works yet per RP - waiting for ground to thaw. |
Danielle Duncan |
3/16/2015 |
Update or Other Action |
The RP is planning on tilling the biocell and should have the consultant draft a work plan soon. |
Danielle Duncan |
3/27/2015 |
Site Characterization Workplan Approved |
Approved the work plan submitted via email communication by CDI to sample the biocell next Monday while they are in town on other business. They will collect five soil samples (plus one duplicate) to be analyzed for DRO and RRO by Alaska Methods 102/103. The samples will be collected from the mid-to-bottom of the biocell as it was tilled this last week. Samples to be submitted for laboratory analysis will be determined by field screening with a PID (highest PID readings). |
Danielle Duncan |
6/24/2015 |
Update or Other Action |
Should be receiving a report from CDI on sampling activities by the end of August. |
Danielle Duncan |
7/16/2015 |
Document, Report, or Work plan Review - other |
Rec'd CDI's report "Re: Kake Power Company Soil Biocell Sampling" this date. |
Danielle Duncan |
8/4/2015 |
Site Characterization Report Approved |
Approved CDI's report on the sampling of the biocell. The analytical results indicate that the biocell has not yet remediated to levels below ADEC cleanup criteria. Remaining DRO concentrations range from 240-2,000 mg/kg. It was recommended that the biocell continue to be fertilized and tilled before sampling in the fall of 2016. |
Danielle Duncan |
3/31/2016 |
Update or Other Action |
AEA is planning on building a new tank farm to replace the failing one in Kake. The location for the new tank farm is adjacent to the IPEC power plant and the biocell that is currently in that location will be capped with an impermeable cap. I am working with Owen Means at HDL on this. |
Danielle Duncan |
5/20/2016 |
Document, Report, or Work plan Review - other |
Rec'd the work plan: Contaminated Materials Work Plan Kake Bulk Fuel Upgrades dated May 2016 submitted by HDL Engineering Consultants on behalf of Alaska Energy Authority. |
Danielle Duncan |
6/2/2016 |
Document, Report, or Work plan Review - other |
Approved the work plan titled: Contaminated Materials Work Plan Kake Bulk Fuel Upgrades dated May 2016 submitted by HDL Engineering Consultants on behalf of Alaska Energy Authority. The biocell will capped and any new contaminated soil to be left in place according to the ADEC Technical Memorandum: Managing Petroleum-Contaminated Soil, Water, or Free Product during Public Utility and Right of-Way Construction and Maintenance Projects dated March 2014. However, if contaminated soil or water is encountered the ADEC will be notified immediately as stated in the work plan. The letter does not serve as an approval for the tank farm design itself as that is beyond the scope of the Contaminated Sites Program. The biocell will be placed beneath the new tank farm soil liner and an impermeable liner will be placed over top. There will also be a secondary containment dike containment liner and these liners will overlap one another. The liners will be a nominal thickness of no less than 36 mil and a minimum of 18 inches of structural fill will be placed over top to ensure that the liner is not damaged from trucks driving on top of it. No soils will be moved off site. Once the new tank farm is built, the Kake Power Plant Contaminated Site will be closed on the ADEC database.
|
Danielle Duncan |
6/21/2016 |
Update or Other Action |
Sent a letter requesting that the biocell be relocated and placed on a liner this date. |
Danielle Duncan |
7/5/2016 |
Update or Other Action |
Spoke to the RP and they are looking into a place to put the c-soil and need a liner. They will get back with me. |
Danielle Duncan |
7/7/2016 |
Update or Other Action |
RP provided me with pictures from 1998 showing the original location of the biocell which is currently on City property and has cars parked on top. I sent a letter to all interested parties indicating that the biocell does not need to be moved and the original HDL plan for the tank farm is still valid. |
Danielle Duncan |
4/6/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73687 Oil Transfer Spill Event. |
Danielle Duncan |
12/4/2017 |
Update or Other Action |
IPEC has worked with HDL and AEA to move forward with the “Contaminated Materials Work Plan Kake
Bulk Fuel Upgrades” as indicated in the June 2nd, 2016 letter from DEC. As indicated in the work plan, a new Bulk Fuel Tank Farm and Power Generation Facility have been constructed in Kake. The 1997 biocell was capped with an impermeable 36 mil liner as indicated in the work plan. Structural fill was placed atop the liner to a depth of 18 inches. The tank farm was then constructed atop the capped biocell. No soils were moved off site. |
Danielle Duncan |
12/4/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73687 Oil Transfer Spill Event. |
Danielle Duncan |
12/13/2017 |
Cleanup Complete Determination Issued |
During the summer of 2016, the Alaska Energy Authority (AEA) began planning to build a new tank farm at the City of Kake storage yard where the biocell was located. The ADEC coordinated with AEA and HDL Engineering Consultants to use the biocell soil as fill below the new tank farm. AEA submitted a work plan to ADEC outlining this proposed action and the work plan was approved on June 2, 2016. The fill material was then capped with an impermeable liner and the tank farm construction has been completed as documented in the November 15, 2017 letter to ADEC from the Inside Passage Electric Cooperative. |
Danielle Duncan |