Site Report: Polaris Hotel

Site Name: Polaris Hotel
Address: 123 Lacey Street, Fairbanks, AK 99701
File Number: 102.38.206
Hazard ID: 27217
Status: Informational
Staff: Marc Thomas, 9074655206 marc.thomas@alaska.gov
Latitude: 64.844022
Longitude: -147.717082
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

The City of Fairbanks received a Targeted Brownfield Assessment for the main portion of the Polaris Hotel in 2017. The work included only a Hazardous Building Assessment which found Asbestos Containing Material in high amounts. The building is in poor condition, not earthquake sound and requires demolition as soon as feasible. The City of Fairbanks intends to redevelop the entire City Block 12 into a mix of Residential and Commercial buildings potentially including a convention center, a center for performing arts and affordable housing. The City of Fairbanks applied for a DEC Brownfield Assessment and Cleanup in 2020 in order to continue their work towards redeveloping the property. The only contaminants known at this time are the Hazardous Building Materials identified in the 2017 Targeted Brownfield Assessment.

Action Information

Action Date Action Description DEC Staff
5/1/2017 Brownfields Award Main portion of the Polaris hotel approved for a Targeted Brownfield Assessment to be conducted by the EPA. Lisa Griswold
4/28/2020 Meeting or Teleconference Held DEC Brownfields Assessment and Cleanup (DBAC) kick off meeting held on this date. Meeting topics included services desired and potential timeline. Lisa Griswold
5/22/2020 Site Added to Database A new site has been added to the database Mitzi Read
5/27/2020 Document, Report, or Work plan Review - other Targeted Brownfield Assessment report reviewed on this date. The report consists of a Hazardous Building Materials Survey of the main portion of the hotel. 542 samples were taken for suspect Asbestos Containing Materials (ACM), and 365 samples were taken for evaluation of lead based paint. Results of the report found both friable and non-friable ACM, lead based paint, and fluorescent light magnetic ballasts that are assumed to contain PCBs. Mercury-containing fluorescent light tubes were not located in the main portion of the hotel. Lisa Griswold
10/19/2020 Brownfields Award SFY 21 DEC Brownfields Assessment and Cleanup awarded to City of Fairbanks for the purposes of conducting a health and safety analysis, possible site characterization and cleanup planning. EPA State and Tribal Response Program (STRP) funds $71,705.00 awarded. Lisa Griswold
11/9/2020 Meeting or Teleconference Held Meeting with Polaris Work Group conducted on this date. Lisa Griswold
5/5/2021 Meeting or Teleconference Held Teleconference was held between ADEC, City of Fairbanks, Explore Fairbanks, and NORTECH. Items discussed were the Health and Safety report and the Data Gap analysis report. As some items could be considered both health and safety or a data gap, after review and collaboration, the goal is to complete a health and safety action that could accomplish City of Fairbank's main concerns, and address other data gaps with remaining Brownfields funding. Lisa Griswold
5/12/2021 Document, Report, or Work plan Review - other ADEC reviewed the Polaris Buiding Data Gap Analysis Report received on March 8, 2021. The report identified potential issues that could inhibit the redevelopment of Block 12. These issues include: Exterior paint needs further evaluation of lead and PCBs Transformer oil present requires evaluation of PCB content Potential threats to groundwater located in the basement need further evaluation Groundwater within the building footprint has not been evaluated Potential impacts on Lots 5, 6 and 8 are unknown Historical releases on or near Lot 9 are unknown Potential upgradient source areas have not been evaluated The report recommended the following: Analyze the exterior paint for lead and PCBs Ground surface around the building should be evaluated for flaking paint and extend evaluation as necessary Conduct an inspection of each type of drain to evaluate connection to wastewater system Pack and dispose of all waste chemicals and cylinders Inspect the floor beneath the waste chemicals and cylinders, and conduct potentially conduct a subsurface investigation Test and remove the remaining transformer oil Test the water found in the sub-slab pits in the basement Test the groundwater beneath the Polaris Building, with potential for soil gas sampling Evaluate potential releases on Lot 5, 6, 8 and 9 Test the groundwater around the perimeter of Block 12 ADEC had no comments on the report. Lisa Griswold
5/12/2021 Document, Report, or Work plan Review - other ADEC reviewed the finalized Health and Safety Evaluation and Recommendations report received on March 19, 2021.This Report documented the current health and safety issues that exist at the Polaris Hotel with recommendations on how to proceed. Recommendations include: Developing a detailed Site Safety and Health Plan (SSHP) Secure the building to address the current physical hazards, biological hazards, and hazardous materials Conduct a pre-abatement release prevention action Address other materials that would be considered hazardous during demolition Abate the Hazardous Building Materials and interior biological hazards Demolish the building ADEC had no further comments on this report. Lisa Griswold
6/18/2021 Meeting or Teleconference Held Meeting held between ADEC, Nortech and City of Fairbanks. Topics included moving forward on the project and funding. Lisa Griswold
8/31/2021 Meeting or Teleconference Held Meeting with the Polaris Working Group held on this date. Lisa Griswold
10/12/2021 Document, Report, or Work plan Review - other ADEC received draft of a Health and Safety work plan for the Polaris Hotel and has no comments. Lisa Griswold
10/13/2021 Meeting or Teleconference Held Update meeting with Nortech held. Lisa Griswold
11/4/2021 Update or Other Action Nortech submitted results from PCB paint testing. PCB containing paint is present on site. See site file for more information. Lisa Griswold
12/15/2021 Update or Other Action Staff assigned changed to Marc Thomas. Lisa Griswold
2/10/2022 Document, Report, or Work plan Review - other ADEC received report entitled, "PCBs in Paint - Results Summary and Additional Recommendations Polaris Building & Annex." This report summarized the results of four sampling events addressing PCB sampling of exterior and interior painted surfaces and outlined considerations/recommendations for addressing (including options for disposal) identified PCBs. Marc Thomas
5/18/2022 Meeting or Teleconference Held DEC and the City of Fairbanks discussed project findings and next steps for the project. Marc Thomas
6/14/2022 Document, Report, or Work plan Review - other ADEC received the report entitled, "April 2022 Interior Paints and Concrete Sampling - PCB Results Summary Polaris Building & Annex." This report summarized additional PCB sampling that occurred in April 2022. Marc Thomas
7/27/2022 Document, Report, or Work plan Review - other DEC received report entitled, "Polaris Building: Pre-Demolition Assessment." This report summarizes previous investigations of the site, documents steps taken to address immediate concerns at the property that were identified as current risks, and provide recommendations for the City of Fairbanks to consider as next steps are identified related to site remediation/building demolition and disposal options. Marc Thomas
8/24/2022 Document, Report, or Work plan Review - other ADEC received the report entitled, "Universal Waste Collection and Disposal Polaris Building & Annex," which summarized the universal waste collected and disposed in May 2022. Marc Thomas
11/3/2022 Update or Other Action Received for review documents associated with City of Fairbanks RFP for building demolition. Marc Thomas
5/31/2023 Update or Other Action Demolition of annex building commenced. Marc Thomas
6/29/2023 Update or Other Action DEC received a summary of DBAC-supported work provided by the contractor to assist the City of Fairbanks utilize federal appropriations to demolish the Polaris Hotel and Annex. Marc Thomas

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

No associated sites were found.