Skip to content Skip to content

Site Report: Courtney's Tudor Service

Site Name: Courtney's Tudor Service
Address: 2715 East Tudor Road, and Folker Street, Anchorage, AK 99507
File Number: 2100.38.019
Hazard ID: 2731
Status: Cleanup Complete - Institutional Controls
Staff: IC Unit, 9074655229 dec.icunit@alaska.gov
Latitude: 61.181200
Longitude: -149.830100
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

In May 1997 during the excavation of gasoline contaminated soil associated the a gasoline underground storage tank contamination in the soil and groundwater was found associated with an abandoned waste water log crib and an abandoned floor drain log crib both which were located north of the service station building. The floor drain log crib was found full of used oil that extended into the groundwater at 10 feet below ground surface at the site. The used oil product and most of the contaminated soil was removed and treated. An estimated 10 cubic yards of contaminated soil was left near the building foundation that had up to 1,270 mg/kg DRO and 0.107 mg/kg benzene, and 2.0 mg/l RRO contamination was identified in the groundwater near that area. Based on the soil and groundwater samples collected at that time, it appeared that contamination only remained in this area and did not extend off property. Later sampling conducted at the down gradient properties to west (2004) and north (2014) identified soil and groundwater contamination that appears to be extending on to their properties from this site. As part of an underground storage tank release investigation (see file 2100.26.122) for this property monitoring wells were installed and sampled between 1991 and 1997. The monitoring wells documented groundwater contamination and several inches of floating petroleum product on the groundwater at the site. Groundwater flow direction ranged from west by northwest to north by northwest, with the predominant flow direction begin to the northwest. Depth to groundwater on the service station property was generally 6 to 10 feet below ground surface. In 2001 DEC issued a "No Further Remedial Action Planned" (now called a Cleanup Complete with Institutional Controls) letter and a deed notice was placed on the property for the remaining soil and groundwater contamination. The deed notice state that when the remaining contaminated soil becomes accessible, for example if the service station building is removed, or if other information becomes available which indicates that the site may pose an unacceptable risk to human heath, safety, welfare or the environment, the DEC is to be notified by the land owner and/or operator and further site characterization and cleanup may be required. Also any groundwater pumping or dewatering or transport or disposal of potentially contaminated soil requires notification and approval by DEC. On November 6-15, 2006 Laurel One, LLC had the remaining 20,000 gallon underground storage tank, its associated piping, and five dispenser islands removed and assessed. Two cubic yards of visibly fuel stained soil was identified at the east fuel island. The soil samples collected from the excavated soil had up to 0.0483 mg/kg benzene. Those soils were subsequently treated on-site in a small lined cell. A confirmation soil sample collected at 5.5 to 6 feet below ground surface from the tank excavation had 0.0267 mg/kg benzene on the east sidewall which exceeds migration to groundwater cleanup level of 0.025 mg/kg. On September 11, 2007 DEC notified Mark Kulstad the representative for the current property owner (Laurel One, LLC) and their consultant (Thor Kallestad of Altas Consulting) that they should be aware under the terms of the Notice of Environmental Cleanup for this site that there is further characterization and cleanup required for the estimated 10 cubic yards of contaminated soil located to the north and northwest of the former gas station building that has been removed in preparation for the construction of a new building on the property. DEC noted that with the current construction activities on the property this is the time to conduct the required site work. DEC also noted that benzene groundwater contamination with a sheen and hydrocarbon odor has been identified in the up gradient former monitoring wells at the adjacent Tudor Car Wash site (which is down gradient of the Courtney's site). This is documented in the Tudor Car Wash file (2100.26.162) and noted in the ADEC electronic database for the Courtney's site in 2004. DEC noted that they are requesting a work plan to address the on property contamination and the identified off property contamination from this site including the installation of monitoring wells. The consultant noted that they were aware of the contamination at the site and that he would follow up on the soil and groundwater contamination investigation and cleanup when he returns to Alaska. In October 2014 contaminated soil and groundwater was encountered at 8 feet below ground surface just north of the northwest corner of the former Courtney’s gas station property at 2715 East Tudor Road during the excavation for a waterline. At 8 feet below ground surface they encountered petroleum contaminated soil with a petroleum stain and odor at the soil/water interface. The groundwater has a petroleum sheen and up to 47.1 ug/l benzene, 3.52 mg/l GRO, 4.87 mg/l DRO, and 5.45 mg/l RRO in the excavation water samples collected. These groundwater sample results are considered biased low due to them being collected from an open excavation, and bubbles and not sufficient volume in some of the VOA vials. The current property owner of the 2715 East Tudor Road property has been contacted regarding their liability for the contaminated soil and groundwater. The DEC letter requested that they submit by December 1, 2014 a work plan, including a schedule for conducting the work, for conducting soil and groundwater sampling to define the nature and extent of this and any other contamination for your site. Due to the contamination found the status for the Courtney’s Tudor Service site located at 2715 E Tudor Road in Anchorage (File No: 2100.38.019) is being changed from Cleanup Complete – Institutional Controls to Active. Between October 10, 2014 and October 31, 2014 six soil samples were collected from the waterline excavation sidewalls. Up to 66.9 mg/kg RRO, non-detect (<22.4 mg/kg) DRO, 3.86 mg/kg GRO, 0.00703 mg/kg benzene, non-detect PCBs and VOCs, naturally occurring concentrations for metals, and PAHs below method 2 cleanup levels. Higher soil concentrations may exist since the area where groundwater with visible sheens and petroleum odors (near Folker Road) did not have soil samples. On November 24, 2014 soil samples were collected from the potentially contaminated soil that was excavated as part of the waterline installation on the property to the north of the Subway (former Courtney's Service Station) property. Up to 3,170 mg/kg RRO, 568 mg/kg DRO, non-detect (<1.1 mg/kg) GRO, non-detect (<0.00552 mg/kg) benzene, non-detect for VOCs and PCBs, naturally occurring concentrations for metals, and below method 2 cleanup levels for PAHs in the stockpile samples collected. On June 16-17, 2016 three off-property soil borings (to the north, northwest, and west) were sampled and completed as monitoring wells. Benzene exceeded migration to groundwater soil cleanup levels in all three soil borings and for ethylbenzene in soil boring RSE-2. On June 23, 2016 groundwater samples were collected from the three off-property monitoring wells installed earlier in June 2016. The groundwater samples had up to 2.97 ug/l benzene, 0.296 mg/l GRO, 0.704 mg/l DRO, 1.21 mg/l RRO. RSE-2 (to the northwest) exceeded groundwater cleanup levels for RRO. On January 19, 2018 the three monitoring wells (RSE-1, RSE-2, and RSE-3) that were installed in 2016 were decommissioned in accordance with the approved work plan. On September 14, 2018 ADEC issued a letter changing the site status from Active Contaminated Site back to Cleanup Complete with Institutional Controls (IC) status.

Action Information

Action Date Action Description DEC Staff
3/6/1998 Document, Report, or Work plan Review - other In May 1997 during the excavation of gasoline contamianted soil associated the a gasoline underground storage tank contamination in the soil and groundwater was found associated with an abandoned waste water log crib and an abandoned floor drain log crib both which were located north of the service station building. The floor drain log crib was found full of used oil that extended into the groundwater at 10 feet below ground surface at the site. Eileen Olson
12/20/1999 Site Added to Database Soil and groundwater contamination. Eileen Olson
1/20/2000 Document, Report, or Work plan Review - other The used oil product and most of the contaminated soil was removed and treated. An estimated 10 cubic yards of contaminated soil was left near the building foundation that had up to 1,270 mg/kg DRO and 0.107 mg/kg benzene, and 2.0 mg/l RRO contamination was identified in the groundwater near that area. Eileen Olson
11/22/2000 Update or Other Action Public notice published requesting comment on proposed application of 10x rule for site groundwater and soils. Eileen Olson
2/12/2001 Site Number Identifier Changed Although metals were initially suspected to be present in the floor drain sludge and associated soil and groundwater contamination, they were not found to be present. Therefore, the Workplan is changed from 09 to 01. Eileen Olson
2/20/2001 Record of Decision No Further Remedial Action Planned/Institutional Controls (NFRAP/IC) determination granted in Record of Decision (ROD) issued this date. The determination requires that the attached notice is recorded on the property deed no later than March 15, 2001 with a copy of the recorded notice provided to ADEC by March 31, 2001. Eileen Olson
2/21/2001 Cleanup Level(s) Approved Record of Decison (ROD) granting NFRAP/IC status issued this date approves cleanup levels based on a determination in accordance with criteria set forth in 18 AAC 75.350 that the shallow groundwater at the site is not a current or potential future drinking water source and, therefore, an alternative cleanup level for the groundwater can be established under 18 AAC 75.345, Table C. The alternative groundwater cleanup level approved for the shallow groundwater aquifer at this site is ten times the Table C regulatory levels. This determination correspondingly allows alternative cleanup levels to be developed for the soil. Based on available information contamination in the soil and groundwater does not extend beyond the property boundaries. Eileen Olson
2/21/2001 Update or Other Action NFRAP/IC letter issued. An alternative groundwater cleanup level of ten times the Table C regulatory levels was approved for the shallow groundwater aquifer at the site. Robert Weimer
2/21/2001 Institutional Control Record Established NFRAP/IC established: Notice of Environmental Contamination to be recorded on property deed. The Department requires that a "Notice of Environmental Contamination" be recorded on the property. The purpose of the deed notice is intended to provide notice to future owners or operators of contamination that remains on site. Please ensure that the attached notice is recorded on the deed of this property no later than March 15, 2001. A copy of the recorded notice must be provided to this office by March 31, 2001. Eileen Olson
4/4/2001 Update or Other Action Received a copy of the recorded NEC (see 2/21/01 action) on 4/25/01. Date recorded is action date. Eileen Olson
10/1/2004 Update or Other Action Report for the Tudor Car Wash site (west of the Courtney's site) titled "Soil Boring and Groundwater Sampling Report 2621 East Tudor Road Anchorage, Alaska" received by the Department suggests that a benzene plume is migrating from Courtney's Tudor Service to Tudor Car Wash. Benzene was detected at concentrations around 10 ug/L in monitoring wells located upgradient of Tudor Car wash and downgradient of Courtney's Tudor Service. Todd Blessing
7/11/2007 Update or Other Action DEC notified Mark Kulstad the representative for the current property owner (Laurel One, LLC) and their consultant (Thor Kallestad of Altas Consulting) that they should be aware under the terms of the Notice of Environmental Cleanup for this site that there is further characterization and cleanup required for the estimated 10 cubic yards of contaminated soil located to the north and northwest of the former gas station building that has been removed in preparation for the construction of a new building on the property. DEC noted that with the current construction activities on the site this is the time to conduct the required site work. DEC also noted that benzene groundwater contamination with a sheen and hydrocarbon odor has been identified in the upgradient former monitoring wells at the adjacent Tudor Car Wash site (which is down gradient of the Courtney's site). This is documented in the Tudor Car Wash file (2100.26.162) and noted in the ADEC electronic database for the Courtney's site. DEC noted that they are requesting a work plan to address the on property contamination and the identified off property contamination from this site including the installation of monitoring wells. The consultant noted that they were aware of the contamination at the site and that he would follow up on the soil and groundwater contamination investigation and cleanup when he returns to Alaska. Robert Weimer
9/25/2008 Document, Report, or Work plan Review - other On November 6-15, 2006 Laurel One, LLC had the remaining 20,000 gallon underground storage tank, its associated piping, and five dispenser islands removed and assessed. Two cubic yards of visibly fuel stained soil was identified at the east fuel island. The soil samples collected from the excavated soil had up to 0.0483 mg/kg benzene, 0.654 mg/kg GRO, and 0.0109 mg/kg DRO. Those soils were subsequently treated on-site in a small lined cell. A confirmation soil sample collected at 5.5 to 6 feet below ground surface from the tank excavation had 0.0267 mg/kg benzene on the east sidewall which exceeds migration to groundwater cleanup level of 0.025 mg/kg. Robert Weimer
4/10/2012 Update or Other Action Found deed notice in the hard file at the Anchorage office and attached document in CS database. Kristin Thompson
9/14/2012 Update or Other Action Staff changed from Eileen Olson to IC Unit. Kristin Thompson
9/26/2012 Institutional Control Compliance Review IC review conducted. Evonne Reese
10/9/2014 Site Visit Site visit to observe current site conditions. Petroleum sheen observed on the excavation groundwater just to the northwest and down gradient from this property. Robert Weimer
10/9/2014 Site Reopened Cats Eye excavating called to report that soil and groundwater contamination encountered at 8 feet below ground surface just north of the northwest corner of the former Courtney’s gas station property at 2715 East Tudor Road. They were starting to excavate to install a new 6 inch water line from the main in Folker Road to the building at 2735 Tudor Road. They plan to dig to 11 feet below ground surface to install the water line. At 8 feet below ground surface they encountered petroleum contaminated soil with a petroleum stain and odor at the soil/water interface. The groundwater has a petroleum sheen. The excavation is currently open and secured. Robert Weimer
10/10/2014 Update or Other Action On October 10, 2014 excavation water samples were collected by White Environmental Consultants to establish concentrations for the AWWU permit for discharge of excavation water into a settling tank then into the nearby sanitary sewer. Up to 47.1 ug/l benzene, 3.52 mg/l GRO, 4.87 mg/l DRO, and 5.45 mg/l RRO in the excavation water samples collected. The sample results are considered biased low due to them being colected from an open excavation, and bubbles and not sufficent volume in some of the VOA vials. While the samples were over temperature at 16.1 degrees C they were delivered to the lab only 65 minutes after collection, so they did not have enough time to chill to 6 degrees C. Robert Weimer
10/21/2014 Update or Other Action On October 21, 2014 a permit for discharge of excavation water into a settling tank then into the nearby sanitary sewer was issued by AWWU. The permit allows up to 10 mg/l DRO, 5 mg/l GRO, and 5 mg/l total aromatic hydrocarbons in the water discharged into the sanitary sewer. Robert Weimer
10/24/2014 Potentially Responsible Party/State Interest Letter Notice of hazardous substance liability sent to the property owner Laurel One, LLC. The letter requested that they submit by December 1, 2014 a work plan, including a schedule for conducting the work, for conducting soil and groundwater sampling to define the nature and extent of this and any other contamination for your site. Due to the contamination found the status for the Courtney’s Tudor Service site located at 2715 E Tudor Road in Anchorage (File No: 2100.38.019) is being changed from Cleanup Complete – Institutional Controls to Active. Robert Weimer
10/24/2014 Exposure Tracking Model Ranking Initial ranking with ETM completed for source area id: 73707 name: auto-generated pm edit Courtney's Tudor Service Robert Weimer
10/28/2014 Document, Report, or Work plan Review - other ADEC provides comments on the proposed October 2014 soil and water sampling plan for the planned 170 foot long 6 inch diameter water line from the water main in Folker Road to the building at 2735 Tudor Road. They plan to dig to 11 feet below ground surface to install the water line. Near Folker Road 8 feet below ground surface they encountered petroleum contaminated soil with a petroleum stain and odor at the soil/water interface. The groundwater in that area has a petroleum sheen. Robert Weimer
10/29/2014 Document, Report, or Work plan Review - other ADEC provides comments on the revised October 2014 soil and water sampling plan for the planned 170 foot waterline installation. Robert Weimer
10/30/2014 Document, Report, or Work plan Review - other ADEC approves the new revised October 2014 soil and water sampling plan for the planned 170 foot waterline installation. Robert Weimer
10/30/2014 Site Visit Site visit to observe current site conditions. The open excavation extends about 100 feet toward the building and dewatering is ongoing. The west end in Folker Road was backfilled with clean fill prior to the consultant being on-site so a west sidewall sample was not collected. Overburden excavated soil with field reading above ambient is being placed on pavement on the north side of the excavation. Potentially contaminated soil is being placed on a bermed liner on the soil side of the excavation and is covered. All of the material excavated on October 9, 2014 is covered on the north side of the excavation. Robert Weimer
10/31/2014 Site Visit Site visit to observe current site conditions. The open excavation now extends to the building and dewatering is ongoing. Consultant stated that based on field readings the entire length of the 170 foot trench is contaminated, with most contaminated area observed on the west end of the trench near Folker Street. The consultant will be collecting at least 2 analytical samples from the north and south sidewalls. While DEC was present there was about a 1 gallon hydraulic soil spill from the excavator on the north side of the trench. Most of the hydraulic oil spilled on the pavement, but some was spilled on the edge of one of the overburden soil piles that was on the pavement. They will cleanup the hydraulic oil on the pavement an cover the impacted soil until it is removed from the overburden soil pile. The consultant is to return to the site tomorrow to oversee the removal of the contaminated soil to document the removal of the impacted soil and the stockpiling of the material separate from the other impacted soils. The consultant mentioned that earlier today the maintenance person for the Subway collected some soil from the contaminated soil pile and put it in zip lock baggies presumably to take to the lab for analysis. Robert Weimer
11/3/2014 Site Visit Site visit to observe current conditions for the waterline work. The excavation is still open and they continue to dewater the excavation to install the water line. It appears that the hydraulic oil impacted soil has been removed. Robert Weimer
11/19/2014 Offsite Soil or Groundwater Disposal Approved ADEC approves 140 cubic yards of contaminated soil (the warm and hot stockpiles) to be disposed of at the Anchorage Regional Landfill. Note: this soil was resampled on November 24, 2014 and some of the soil was reused as backfill in the waterline trench near the surface, and other soil is to be disposed of at the Anchorage Regional Landfill or thermally treated at ASR. Robert Weimer
11/19/2014 Offsite Soil or Groundwater Disposal Approved ADEC approves 1 cubic yard of hydraulic oil contaminated soil to be thermally treated at ASR. This contaminated soil was generated on October 31, 2014 due to a burst hydraulic hose on the excavator that spilled on to a portion of the clean over burden soil stockpile. Robert Weimer
11/21/2014 Document, Report, or Work plan Review - other The “November 21, 2014 Soil Sampling Work Plan – Addendum” for 2735 E. Tudor Road stockpile sampling and storage is approved. The work plan proposes to resample the "hot" and "warm" stockpiles and to place them and a liner and covered in four separate portions at the top of the waterline trench or stockpiled outside of the trench on the property on a liner and covered. Based on the results of this sampling the soil will either remain as backfill at the top of the trench or be removed and transported to the Anchorage Regional Landfill for disposal or ASR for thermal treatment. Robert Weimer
11/24/2014 Site Visit Site visit to observe the resampling of the "hot" and "warm" stockpiles. The "hot" stockpile was placed on a liner and covered on the top of the trench. The "warm" stockpile is going to be stored on property on a liner and covered over the winter. Robert Weimer
12/4/2014 Update or Other Action On December 1, 2014 ADEC received a letter on behalf of Laurel One LLC, the current property owner of this site, that the work plan requested by December 1, 2014 would be submitted "shortly". ADEC sent an email requesting that the requested work plan be submitted by no later than December 15, 2014. Robert Weimer
3/20/2015 Document, Report, or Work plan Review - other On November 24, 2014 soil samples were collected from the potentially contaminated soil that was excavated as part of the waterline installation on the property to the north of the Subway (former Courtney's Service Station) property. The soil was segregated into hot and warm stockpiles. The hot stockpile soil was used as backfill near the ground surface on a liner in the waterline excavation, and the warm stockpile soils are currently stored on the property. Soil samples collected from the hot stockpile contained up to 46.5 mg/kg RRO, non-detect (<21.3 mg/kg) DRO, non-detect (<1.12 mg/kg) GRO, non-detect (<0.00621 mg/kg) benzene, non-detect for VOCs and PCBs, and at naturally occurring concentrations for metals. The soil sample collected from the eastern portion of the warm stockpile contained up to 453 mg/kg RRO, non-detect (<21.6 mg/kg) DRO, non-detect (<1.23 mg/kg) GRO, non-detect (<0.00614 mg/kg) benzene, non-detect for VOCs and PCBs, naturally occurring concentrations for metals, and non-detect for PAHs. The soil sample collected from the western portion of the warm stockpile contained up to 3,170 mg/kg RRO, 568 mg/kg DRO, non-detect (<1.1 mg/kg) GRO, non-detect (<0.00552 mg/kg) benzene, non-detect for VOCs and PCBs, naturally occurring concentrations for metals, and below method 2 cleanup levels for PAHs. Robert Weimer
3/20/2015 Offsite Soil or Groundwater Disposal Approved ADEC approves request to transport the 30 cubic yard western portion of the warm stockpile to be transported to and thermally treated at ASR. Those soils contained up to 3,170 mg/kg RRO and 568 mg/kg DRO. Robert Weimer
3/20/2015 Offsite Soil or Groundwater Disposal Approved ADEC approves request to transport the 30 cubic yard eastern portion of the warm stockpile to be transported to and disposed of at the Anchorage Regional Landfill. Those soils contained up to 453 mg/kg RRO. Robert Weimer
3/20/2015 Update or Other Action Update from the consultant (White Environmental Consultants) for adjacent property owner to the north that did the environmental sampling for the waterline excavation that the sampling report is to be finalized and submitted to ADEC once the remaining stockpiled soil is transported to Anchorage Regional Landfill and ASR. To date just the laboratory data sheets, field notes, and a draft site diagram have been submitted. Robert Weimer
3/20/2015 Document, Report, or Work plan Review - other Between October 10, 2014 and October 31, 2014 six soil samples were collected from the waterline excavation sidewalls. Up to 66.9 mg/kg RRO, <22.4 mg/kg DRO, 3.86 mg/kg GRO, 0.00703 mg/kg benzene, non-detect PCBs and VOCs, naturally occurring concentrations for metals, and PAHs below method 2 cleanup levels. Higher soil concentrations may exist since the area where groundwater with visible sheens and petroleum odors (near Folker Road) did not have soil samples. Robert Weimer
5/7/2015 Update or Other Action Update from the consultant (White Environmental Consultants) for adjacent property owner to the north that did the environmental sampling for the waterline excavation that the sampling report has not yet been finalized. They plan to finalized it and submit it to ADEC once the remaining stockpiled soil is transported to Anchorage Regional Landfill and ASR. To date just the laboratory data sheets, field notes, and a draft site diagram have been submitted. ADEC requests that the report be submitted by May 22, 2015 even if the stockpiles have not been moved yet. The stockpile receipts can just be submitted later. Robert Weimer
7/14/2015 Meeting or Teleconference Held Meeting between DEC, DOL, Laurel One LLC, and their attorney to discuss past and future site work. Robert Weimer
8/13/2015 Update or Other Action Letter from Department of Law to the attorney for the property owner Laurel One LLC as follow up to the July 14, 2015 meeting. The letter requests 3 borings completed as monitoring wells to help delineate the extent of the off-property contamination for this site. Sampling requested is BTEX, GRO, DRO, RRO, and one for PAH. The letter also identified 3 additional sampling locations on-property needed to evaluate the site closure without Institutional Controls. Robert Weimer
8/26/2015 Document, Report, or Work plan Review - other ADEC receives documentation that 44.68 tons of contaminated soil was delivered to ASR for thermal treatment. Robert Weimer
8/26/2015 Document, Report, or Work plan Review - other ADEC receives documentation that 38.15 tons of contaminated soil was delivered to Anchorage Regional Landfill for disposal. Robert Weimer
1/25/2016 Offsite Soil or Groundwater Disposal Approved ADEC receives documentation that the 44.68 tons of contaminated soil was delivered to ASR for thermal treatment has been treated. Robert Weimer
2/25/2016 Update or Other Action ADEC review of RPs consultants request to install only one monitoring well. ADEC letter requests work plan be submitted by March 25, 2016 for conducting the site investigation work requested in the DOL letter of August 13, 2015 for three off-property monitoring wells. Robert Weimer
4/6/2016 Meeting or Teleconference Held The Alaska Department of Environmental Conservation (DEC) has reviewed the March 24, 2016 Subsurface Investigation Work Plan from Restoration Science & Engineering (RSE). Discussed with RSE the following: 1. Groundwater Sampling - As per the DOL letter dated August 13, 2015 the groundwater sampling is to include PAH analysis for each monitoring well. 2. Background Information - As noted in the DOL letter dated August 13, 2015 and the Atlas Consulting’s October 2007 UST removal report, contamination was left above DEC cleanup levels on the east sidewall of the 2006 tank excavation. 3. Schedule - DEC requests that the results of the soil sampling and the first groundwater monitoring event be submitted by July 15, 2016. Discussed with RSE that DEC would be sending out a conditional approval letter with the conditions/modifications discussed above. Robert Weimer
4/6/2016 Document, Report, or Work plan Review - other DEC letter. The Alaska Department of Environmental Conservation (DEC) has reviewed the March 24, 2016 Subsurface Investigation Work Plan from Restoration Science & Engineering (RSE). The work plan proposes to collect soil samples from three borings, complete them as monitoring wells, and collect groundwater samples. This work plan is approved under the following conditions/modifications: 1. Groundwater Sampling - As per the DOL letter dated August 13, 2015 the groundwater sampling is to include PAH analysis for each monitoring well. 2. Background Information - As noted in the DOL letter dated August 13, 2015 and the Atlas Consulting’s October 2007 UST removal report, contamination was left above DEC cleanup levels on the east sidewall of the 2006 tank excavation. 3. Schedule - DEC requests that the results of the soil sampling and the first groundwater monitoring event be submitted by July 15, 2016. Robert Weimer
6/16/2016 Site Visit Site visit to observe the installation of three monitoring wells. At each of the two monitoring wells on the west side of Folker Street a black liquid was encountered in the soils near the soil/water interface that had elevated field readings and a slight septic smell. The third monitoring well was still being installed. Robert Weimer
6/23/2016 Site Visit Site visit to observe groundwater sampling. Robert Weimer
7/28/2016 Update or Other Action DEC approves request for an extension from July 15, 2016 to August 15, 2106 for the submittal of the report of the results of the soil sampling and the first groundwater monitoring event that was conducted in June 2016. Robert Weimer
10/19/2016 Document, Report, or Work plan Review - other On June 16-17, 2016 three off-property soil borings (to the north, northwest, and west) were sampled and completed as monitoring wells. The soil samples collected had up to 0.129 mg/kg benzene, 0.134 mg/kg ethylbenzene, 30 mg/kg GRO, 18 mg/kg DRO, 71.1 mg/kg RRO, 22.3 ug/kg 1-Methylnaphthalene, 40.6 ug/kg 2-Methylnaphthalene, 3.01 ug/kg Benzo(a)pyrene, 2.94 ug/kg Benzo(b)Fluoranthene, 7.1 ug/kg Benzo(g,h,i)perylene, 3.09 ug/kg Chrysene, 17.1 ug/kg Napthalene, 2.85 ug/kg Phenathrene, and 3.04 ug/kg Pyrene. Benzene exceeded migration to groundwater soil cleanup levels in all three soil borings and for ethylbenzene in soil boring RSE-2. The soil cutting are currently stored on drums/containers on the northeast corner of the property awaiting a request for ADEC approval for treatment/disposal. Robert Weimer
10/19/2016 Document, Report, or Work plan Review - other On June 23, 2016 groundwater samples were collected from the three off-property monitoring wells installed earlier in June 2016. Monitoring well RSE-1 (to the north) has a screened interval from 4 to 14 feet below ground surface (bgs). Monitoring wells RSE-2 and RSE-3 have a screened interval from 5 to 15 feet bgs. The groundwater samples had up to 2.97 ug/l benzene, 0.296 mg/l GRO, 0.704 mg/l DRO, 1.21 mg/l RRO. RSE-2 (to the northwest) exceeded groundwater cleanup levels for RRO. PAH analysis was not conducted in the groundwater samples. Depth to water ranged from 6.83 to 7.22 feet bgs on June 20, 2016 and 6.90 to 7.25 feet bgs on July 18, 2016. The groundwater flow direction was to the west this monitoring event. The monitoring wells were purged prior to sampling with a bladder pump. The report states that the samples were collected near the soil/water interface. Groundwater samples were received in the lab over temperature (at 13.1 deg C) but arrived within 3 hours of sampling. Development and purge water is currently stored on drums/containers on the northeast corner of the property awaiting a request for ADEC approval for treatment/disposal. Robert Weimer
11/21/2017 Update or Other Action DEC has no objection to properly decommissioning all of the remaining monitoring wells to prepare the site for cleanup complete with ICs status. Also need request for the proper treatment and disposal of the purge water and drill cuttings stored on the property from the 2016 site characterization work. Robert Weimer
11/21/2017 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 73707 auto-generated pm edit Courtney's Tudor Service. Robert Weimer
1/19/2018 Document, Report, or Work plan Review - other ADEC approves work plan for the decommissioning of the remaining 3 site monitoring wells. The approval notes that ADEC still needs a request for the treatment/disposal of the purge water and drill cuttings generated during the 2016 site work. Robert Weimer
2/8/2018 Offsite Soil or Groundwater Disposal Approved ADEC approves request for thermal treatment at ASR of the 1 drum of contaminated drill cuttings that were generated during the 2016 release investigation work. Robert Weimer
9/13/2018 Document, Report, or Work plan Review - other On January 19, 2018 the three monitoring wells (RSE-1, RSE-2, and RSE-3) that were installed in 2016 were decommissioned in accordance with the approved work plan. Robert Weimer
9/14/2018 Cleanup Complete Determination Issued On September 14, 2018 ADEC issued a letter changing the site status from Active Contaminated Site back to Cleanup Complete with Institutional Controls (IC) status. ADEC has determined the cleanup is complete as long as the institutional controls are properly implemented and no new information becomes available that indicates residual contamination may pose an unacceptable risk. Any proposal to transport soil or groundwater off-site requires ADEC approval in accordance with 18 AAC 75.325(i). A “site” as defined by 18 AAC 75.990 (115) means an area that is contaminated, including areas contaminated by the migration of hazardous substances from a source area, regardless of property ownership. Movement or use of contaminated material in a manner that results in a violation of 18 AAC 70 water quality standards is prohibited. Groundwater throughout Alaska is protected for use as a water supply for drinking, culinary and food processing, agriculture including irrigation and stock watering, aquaculture, and industrial use. In the event that groundwater from this site is to be used for these purposes in the future, additional testing and treatment may be required to ensure the water is suitable for its intended use. Robert Weimer

Contaminant Information

Name Level Description Media Comments
Benzene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation GroundwaterSoil
DRO Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation GroundwaterSoil
RRO Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation GroundwaterSoil
Ethylbenzene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation GroundwaterSoil

Control Type

Type Details
CS Database Notation And Letter To Landowner/RP
Notice of Environmental Contamination

Requirements

Description Details
Excavation / Soil Movement Restrictions
Advance approval required to transport soil or groundwater off-site.
When Contaminated Soil is Accessible, Remediation Should Occur
Movement or use of contaminated material (including on site) in a manner that results in a violation of the water quality standards is prohibited (18 AAC 70)
Hazard ID Site Name File Number
23378 Courtney's Service Station 2100.26.122
23712 Tudor Car Wash 2100.26.162

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close