Site Report: Residence - 8393 W Snow Goose Drive HHOT

Site Name: Residence - 8393 W Snow Goose Drive HHOT
Address: 8393 Snow Goose Drive, Wasilla, AK 99654
File Number: 2265.38.045
Hazard ID: 27641
Status: Active
Staff: Shawn Tisdell, 9074512752 shawn.tisdell@alaska.gov
Latitude: 61.530877
Longitude: -149.662362
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

At the site, located at 8393 W Snow Goose Road, Wasilla, Alaska at an unknown time for unknown reasons a 300-gallon aboveground home heating oil tank containing fuel (diesel) (approximately 100 gallons) fell from its metal storage platform and spilled an unknown volume to the ground surface. Soils were excavated to the depth of 13 feet adjacent to the cabin; however, contamination remained in the bottom of the excavation pit and below the cabin. Fertilizer was applied to enhance natural remediation, and soils were replaced in the excavation pit with layers of clean fill, and fertilizer.

Action Information

Action Date Action Description DEC Staff
10/13/2021 Site Added to Database A new site has been added to the database Courtney Pegus
10/13/2021 Spill Transferred from Prevention Preparedness and Response Program Spill transferred by PPRP staff Worman, Kristin K (DEC), Spill (20239918302) Collection date 7/1/2020 request for 3893 W Snow Goose Drive HHOT, Permission granted Lisa Krebs-Barsis given to Julie Fix site. A 300-gallon aboveground home heating oil tank containing approximately 100 gallons of fuel fell from stand and an unknown amount of fuel was released into the soil adjacent to the cabin. Some soil was removed but there remained evidence that contamination was still present during the time when the site was back-filled with new soil Courtney Pegus
11/3/2021 Potentially Responsible Party/State Interest Letter PRP letter sent via email on this date. Hardcopy PRP letter sent via certified mail on 11/4/2021. Julie Fix
11/12/2021 Workplan Requested Work plan request letter sent via email and a hardcopy via certified mail. Julie Fix
11/17/2021 Meeting or Teleconference Held Meeting with consultant, Corvid Environmental. Discussed site history, previous field work, and a work plan for 2022 field work. Action items include a CSP review of the 9/2020 report and an additional meeting with Corvid to discuss data gaps and the 2022 work plan/field work. Follow up email summarizing meeting sent to the RP. Julie Fix
2/10/2022 Document, Report, or Work plan Review - other The draft “Revet HHOT Site Characterization Groundwater Monitoring Work Plan” was received on this date. Comments were sent to the RP and consultant on 4/1/2022. A revised work plan was submitted on 7/7/2022. Additional communications and teleconferences with the consultant were held in August 2022 and on 9/29/2022. Julie Fix
10/17/2022 Site Characterization Workplan Approved The revised “Revet HHOT Site Characterization Groundwater Monitoring Work Plan” was approved on this date. A soil boring will be installed using a direct push GeoProbe in the source area. The boring will be completed as a groundwater monitoring well. Two (2) soil samples will be collected and analyzed for GRO, DRO, RRO, VOCs, and PAHs. Groundwater samples will be analyzed for GRO, DRO, VOCs, and PAHs. Julie Fix
2/3/2023 Document, Report, or Work plan Review - other The "Revet HHOT Site Characterization Report" received on this date and is currently under review. Julie Fix
8/17/2023 Site Characterization Report Approved The "Revet HHOT Site Characterization Report" was approved on this date. The report describes the collection of two samples at 30 and 50 feet bgs. The samples were analyzed for GRO, DRO, VOCs, and PAHs. All sample results were either non-detect or well below the DEC cleanup levels. Julie Fix
3/21/2025 Update or Other Action Email sent to RP requesting updates to contact information, questions about current status of site, and providing notice that a new CS project manager is overseeing the site. Shawn Tisdell
4/21/2025 Meeting or Teleconference Held Project manager talked with consultant from Corvid LLC about current site status. All contamination remaining on site lies at depths greater than 2 feet below ground surface. Consultant recommends site closure with institutional controls. Shawn Tisdell

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements