Action Date |
Action |
Description |
DEC Staff |
8/25/1999 |
Interim Removal Action Approved |
DEC received the final 1998 SI/IRA/RA Report on Amaknak and Unakaska Islands, by Jacobs Engineering, dated Aug. 1999. The report documents that ~380 WWII era drums mostly empty, but some containing sludge, water and/or soil, were removed from this site during 1998. Approximately 60 cubic yards of petroleum contaminated soil were removed and thermally treated.
- The fieldwork included a survey for unexploded ordnance (UXO), which identified ordnance related material including empty casings (.30 cal and 20mm, rifle clips, practice rifle-grenade parts, a live .30 rifle grenade cartridge, shipping containers for 155mm projectiles and other ordnance related debris).
- The report recommended no further action; note - DEC did not concur with this recommendation, but requested further investigation. |
John Halverson |
2/24/2000 |
Site Added to Database |
Drums, solid waste and diesel range organics. |
John Halverson |
6/5/2000 |
Site Characterization Report Approved |
DEC received the Comprehensive Remedial Investigation Report on Amaknak/Unalaska Islands, by Jacobs Engineering, dated May 2000. The report documents removal and characterization work at the four drum areas near Port Levashef. Approximately 380 drums and 60 cubic yards of petroleum contaminated soil were removed. No further action is recommended for drum groups 1 and 4. Further characterization is recommended for groups 2 and 3. The report documents two large craters off the side of the road, which are reportedly craters left behind from open burning/detonation of ordnance following WWII. |
John Halverson |
9/5/2001 |
Update or Other Action |
DEC received the final 2000 Island-wide Report on Amaknak/Unalaska Islands, by Jacobs, dated August 2001. The report documents a downgradient monitoring well was installed at drum area 2 and drum area 3. Soil screening and sampling was done on a grid across both sites. Elevated metals were noted in soil at drum area 3. Further groundwater monitoring is planned. |
John Halverson |
11/26/2001 |
Update or Other Action |
DEC received the final 2001 Island-wide Workplan, Amaknak/Unalaska Islands, by Jacobs. It calls for resampling an existing monitoring well at drum area 2 and conducting further characterization using a grid pattern across drum area 3. |
John Halverson |
7/3/2002 |
Site Characterization Workplan Approved |
DEC received the final 2002 Island-wide workplan from Jacobs Engineering. It calls for additional soil sampling at drum area 3 (it states that 2001 sampling showed inorganics at levels near background and regulatory levels) and resampling the monitoring well on-site. |
John Halverson |
6/13/2003 |
Update or Other Action |
DEC received the final 2001/2002 Island-wide SI/RI/IRA report from Jacobs Eng. Confirmation sampling at Drum Group 2 showed soil and groundwater meet applicable cleanup levels and that site is recommended for no further action. Groundwater samples from Drum Group 3 met cleanup levels, but a localized area of soil containing elevated lead (1,590 mg/kg) was identified. A limited soil removal and confirmation sampling are recommeded for Drum Group 3. |
John Halverson |
3/2/2005 |
Update or Other Action |
DEC reviewed and commented on a draft soil removal plan for Drum Group 3. Additional details on field screening, excavation and confirmation sampling were requested. Fieldwork is planned for early summer 2005. |
John Halverson |
6/10/2005 |
Update or Other Action |
File number issued 2542.38.015. |
Aggie Blandford |
6/10/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Jill Taylor |
9/14/2010 |
CERCLA Proposed Plan |
The draft final Proposed Plan #8 was received to ADEC addressing Port Levashef Management Area 12. Port Levashef Drum Group 3 and Lone Drum 1 was recommended for Alternative 2 (Corrective Action Complete/Cleanup Complete with ICs) becuase remaining As contamination is most likley naturally occuring. Port Levashef Drum Groups 1, 2, 4 and Lone Drum 2 were recommended for Alternative 1 (Corrective Action Complete/Cleanup Complete with NDAI) becuase the contaminant sources had been removed to the extent practicable, remaining DRO contamination is minimal and below method THree ACLs. Contamination does not appear to be migrating to groundwater, and the Cd at Drum Group 3 that was detected in 2000 did not exceed cleanup levels in 2001, nor does it any longer appear to be a contaminant of concern for the site. |
Meghan Dooley |
1/31/2024 |
Document, Report, or Work plan Review - other |
Per the review of the Draft Restoration Summary Report, Containerized Hazardous, Toxic, and Radioactive Waste. Amaknak Formerly Used Defense Sites F10AK0841-13, -14, -15, -16, -18, -20, Unalaska Valley, Pyramid Valley-Port Levashef, Summer Bay-Humpy Cove, Margaret Bay-Airport, Mount Ballyhoo, and Little South America (2023), this site AKA Port Levashef Drum Group 3 (PLD 3); is anticipated for FY24 Contract. |
Cascade Galasso-Irish |