Action Date |
Action |
Description |
DEC Staff |
8/3/1998 |
Update or Other Action |
ADEC received the Workplan Addendum UST/Pipeline Removals, Thermal Treatment Operations Plan, Other RI, IRA, and SI Tasks, dated July 1998 (Jacobs Engineering) for FUDS work planned in 1998. It called for removal of remaining USTs, contaminated soil from the sites tanks were removed in 1997, and removal of the paint drums, among work on other sites. Note - workplan received before the report documenting what was done the previous year. |
John Halverson |
3/9/1999 |
Interim Removal Action Approved |
ADEC received the final 1997 Report - Interim Removal Actions, Site Investigations, Remedial Investigations Amaknak and Unalaska Islands, dated March 1999 (Jacobs Engineering). The report described site inspections at 88 WWII buildings in Unalaska Valley (UV); 25 USTs were identified at these buildings and 24 were removed (7 were from the Ski Bowl Area); one UST at Building UV-3760 could not be removed due to access problems and will be addressed later; samples from five of the UST excavations met matrix cleanup levels; further investigation/evaluation is needed at the others; a "paint drum" area was identified on private property in lower Unalaska Valley, it contains ~24 abandoned drums of military paint. Recommended removal of additional UST, contaminated soil removal from UST sites, removal of paint drums. |
John Halverson |
8/25/1999 |
Update or Other Action |
ADEC received the 1998 SI/IRA/RI Report Amaknak and Unalaska Islands. It documents the following:
Upper Unalaska Valley/Ski Bowl Area - field work postponed due to concern over possible adverse impacts to wetlands and snow falling before they had a chance to install well points;
Upper UV - 165th Road and Ugadaga Road - confirmed the presence of two more USTs;
Lower UV - removed 3 more USTs and 36 drums from the paint drum area. Evaluation of need for further work to be included in comprehensive RI report. |
John Halverson |
11/24/1999 |
Site Added to Database |
Diesel fuel contamination. |
John Halverson |
2/11/2000 |
Update or Other Action |
ADEC reviewed and commented on the December 1999 draft Comprehensive Remedial Investigation Report for Amaknak and Unalaska Islands. The report summarizes work done under the FUDS program over the past several years. It documents removal of 14 USTs in lower Unalaska Valley and recommends no further action at eight of them. Further removal, institutional controls and/or monitoring are recommended at the others. In Upper Unalaska Valley 18 USTs were removed and no further action is recommended at 11 of them. Further cleanup, institutional controls and/or monitoring are recommended at the others. Further information was requested on some sites and additional monitoring was requested at some. |
John Halverson |
6/5/2000 |
Site Characterization Report Approved |
ADEC received the final Comprehensive Remedial Investigation Report - Amaknak and Unalaska Islands, May 2000, by Jacobs Engineering for the Corps. Report recommends no further action at four of the seven former UST locations in the lower Unalaska Valley (UV), no further action at four of eight former UST locations the Ski Bowl area in lower UV, no further action at four of eight former UST locations in upper UV and no further action at three of five former UST locations in the upper Broadway area within upper UV. Further soil removal and/or characterization are recommended at the remaining 11 former UST sites. |
John Halverson |
6/5/2000 |
CERCLA RI Report Approved |
The Comprehensive Remedial Investigation Report was received. This document discusses the field activities and results from 1996, 1997, 1998, and 1999. Activities included site investigations (SI), Interim Removal actions (IRA) and Remedial Investigations (RI). These various activities were performed at 56 sites throughout the entire Amaknak/Unalaska FUDS. Sampling was conducted to determine both site-specific as well as background levels of contaminants of concern. 93 USTs, 1 AST, associated piping, and 230 drums, contaminated liquid, sludge, and soil were removed during the IRA. Soil borings were drilled, monitoring wells installed and samples were taken to determine type and extent of contamination. Where appropriate a Method Three ACL was calculated. 31 sites are recommended for no further action (NFA) and 25 sites were recommended for further remedial action. NFA is recommended for this site as the source has been removed and exposure to remaining contamination is limited. |
Meghan Dooley |
9/5/2001 |
Update or Other Action |
DEC received the final 2000 Island-wide SI/IRA Report Amaknak/Unalaska Islands, August 2001, by Jacobs Engineering. It documents the following:
UST 2674 - recommended no further action (NFA);
UST 2664 and 2667 - NFA and institutional controls (ICs);
UST 3260 - additional monitoring and development of alternative cleanup levels;
UST 3465 - NFA;
UST 3475 - NFA;
USTs 2762A and 2762B - NFA and ICs;
USTs 2766A and 2766B - NFA;
UST 3665 - NFA;
Upper Unalaska Valley UST 3760 and 3860 - NFA;
UST 3065 - further action and ICs. |
John Halverson |
1/23/2003 |
Site Number Identifier Changed |
Changed the Sequence Number to 04 from 01 to accommodate multiple Pyramid Valley sites. |
John Halverson |
12/1/2003 |
GIS Position Updated |
Using Montana |
Debra Caillouet |
6/10/2005 |
Update or Other Action |
File number issued 2542.38.012. |
Aggie Blandford |
6/11/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Jill Taylor |
9/14/2010 |
CERCLA Proposed Plan |
ADEC received Proposed Plan #7 which addressed the Unalaska Valley Management Area 11. The plan recommends Alternative 1 (Corrective Action Complete/Cleanup Complete with NDAI) for the General Hills USTs becuase contaminants remain at levels less than Method 3 ACLs and although risk had not been calculated the plan suggests there is no indication that the site poses unacceptable risk to human health or the environment. |
Meghan Dooley |
10/7/2015 |
Update or Other Action |
Updated site coordinates based on 1996 Removal Action Report and Google Maps imagery. |
John Halverson |
10/31/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73846 USTs. |
Linda (Qi) Liu |
11/30/2017 |
Update or Other Action |
ADEC updated statements in Problem/Comment. |
Linda (Qi) Liu |
12/5/2017 |
Cleanup Complete Determination Issued |
ADEC issued a site closure letter after a review of environmental records. |
Linda (Qi) Liu |