Action Date |
Action |
Description |
DEC Staff |
2/15/1995 |
Update or Other Action |
Final RFI/CMS Report submitted. Site is comprised of 7 distinct former AVGAS tanks areas located around the runways. Further investigation warranted at Areas 2, 3, and 6. |
Donald Seagren |
11/9/1995 |
Site Added to Database |
Suspected AVGAS contamination. |
Kent Patrick-Riley |
11/28/1995 |
Site Ranked Using the AHRM |
Initial ranking. Score = 26. |
Kent Patrick-Riley |
2/20/1997 |
Update or Other Action |
Site added by Shannon and Wilson, Inc. |
S&W-Miner |
2/20/1997 |
Preliminary Assessment Approved |
PA action added by Shannon and Wilson, Inc., on 2/20/97. Based on FUDS Site Summary dated 2/21/96, PA started 9/29/95. |
S&W-Miner |
2/8/1999 |
Meeting or Teleconference Held |
Interactive Planning Meeting, USCG Kodiak Sites, Drury Gulch, Site 2 - Navy Landfill, Site 16 - Airport Staging Area and Kodiak Fuds |
Rich Sundet |
2/8/1999 |
Update or Other Action |
Review of Work Summary submitted by Jacobs Engineering. |
Jeff Brownlee |
9/15/1999 |
Interim Removal Action Approved |
Site Investigation and Removal Action performed. |
Jeff Brownlee |
11/30/1999 |
Site Ranked Using the AHRM |
Site Ranked based on information from the 1999 Site Investigation and Removal Action. |
Jeff Brownlee |
3/13/2000 |
Update or Other Action |
Draft site investigation report review. RI included AUW Building, Building 520 and three suspected UST sites. Building 520 has unknown quantities of DRO impacted soil near Devils Creek- shallow bedrock. UST site 2 has a large concrete UST base filled with debris and soil. DRO impacted inside and outside - soil and groundwater. |
Jeff Brownlee |
7/17/2000 |
Update or Other Action |
Reviewed IRA work plan for further characterization at Building A-711, Building 520 and UST site 2. A-711 will get seven new wells to help characterize geology and contamination. Building 520 will have about 300 yards impacted soil removed and 4 wells placed to characterize groundwater. Devils Creek is about 200-feet from this site. UST site 2 is a former concrete storage tank approximately 50-feet in diameter and 10-feet high. Five wells will be installed here for groundwater characterization and hot spot soil removal. |
Jeff Brownlee |
5/3/2001 |
Update or Other Action |
Staff reviewed a Draft Remedial Investigation/Removal Action Report for the Airport Staging Area in Kodiak. Four Areas of Concern were investigated including the Advanced Underwater Research (AUW) Facility, Building 520, Tank Area Two and the Fire Training Pit. The COE calculated soil cleanup levels using Method 3, however the Total Organic Carbon input data did not appear statistically valid. We requested more data or a more conservative approach. Tank Area Two and Building 520 will require additional soil removal to meet proposed cleanup levels. The AUW building appears to have no contaminants of concern. The Fire Training Pit has increasing levels of DRO in groundwater and light detections of volatile and semi-volatile organics including TCE. Approximately 20,000 cubic yards of source impacted soil is scheduled to be excavated this summer. The site is adjacent to the Buskin River. One well approaching the river has 0.25 feet of free product. Sentry wells will need to be installed and potential ecological risk to the river and wetlands evaluated. |
Jeff Brownlee |
5/4/2001 |
Meeting or Teleconference Held |
Staff participated in a Kodiak Island Borough assembly meeting and public open house in Kodiak. The Corps of Engineers and their contractor, Jacobs engineering also attended. Three potential new sites were inspected based on community input. Overall interest seemed light, which has been normal in Kodiak. |
Jeff Brownlee |
5/8/2001 |
Meeting or Teleconference Held |
Staff participated in a comment resolution meeting for the Airport Staging Area 2000 Remedial Investigation Report. Additional contaminated DRO soil excavation will be necessary at Building 520 and UST Area Number 2. The Fire Training Pit Area will require extensive soil removal. The Advanced Underwater Research Facility (AUW) will have continued groundwater monitoring for metals. No other contaminants of concern were found at the AUW building. |
Jeff Brownlee |
7/17/2001 |
Update or Other Action |
Staff reviewed a site-specific operations plan for a thermal desorption unit. The facility will be used to treat soils on-site from one project, the Fire Training Pit. Approximately 20,000 cubic yards of primarily diesel-contaminated soil will be excavated. Gasoline and some low-level volatiles including TCE are present near the source area. |
Jeff Brownlee |
9/18/2001 |
Update or Other Action |
USCG notified EPA and ADEC of new SWMU's found during airport imporvements. USCG proposes to manage releases and any corrective action under SWMU 16. |
Donald Seagren |
5/10/2002 |
Meeting or Teleconference Held |
Staff participated in a comment resolution meeting for the Airport Staging Area 2000 Remedial Investigation Report. Additional contaminated DRO soil excavation will be necessary at Building 520 and UST Area Number 2. The Fire Training Pit Area will require extensive soil removal. The Advanced Underwater Research Facility (AUW) will have continued groundwater monitoring for metals. No other contaminants of concern were found at the AUW building. |
Jeff Brownlee |
5/28/2002 |
Update or Other Action |
Staff participated in an assembly meeting of the Kodiak Island Borough with the Corps of Engineers. One assembly member mentioned that there had been some public concern about a thermal treatment operation that may soon be operating in the Bells Flats area. Residents were concerned about air emissions from the facility. The COE briefed the community and assembly on the planned work for the 2002 season. Staff, the COE and their contractor also performed site inspections at several sites. |
Jeff Brownlee |
6/25/2002 |
Site Characterization Report Approved |
Staff reviewed an Interim Removal Action Report for the Airport Staging Area for work performed during 2001. Approximately 20,000 cubic yards of DRO and a small amount of PCE contaminated soil were removed from the Site 35 Fire Burn Pit. A down gradient test pit investigation shows contamination still present in the smear zone all the way to the bluff near the Buskin River.
Buskin Lake Site 12: Staff reviewed a workplan for monitoring will installation at this former drum storage area adjacent to the Buskin River influent to Buskin Lake. |
Jeff Brownlee |
6/3/2003 |
Update or Other Action |
Reviewed SPI post treatment sampling report for petroleum contaminated soils. Approved disposal in accordance with opertaions plan. |
Donald Seagren |
6/6/2003 |
Meeting or Teleconference Held |
CS staff participated in a public Open House and Kodiak Island Borough Assembly meeting in Kodiak. The COE Alaska District presented the work planned for the summer including additional soil removal at Cape Chiniak Tracking Station and Little Navy Annex, beginning remedial action at the Drury Gulch PCB site and the foamed asphalt paving project. There was little public interest at the Open House. |
Jeff Brownlee |
6/13/2003 |
Update or Other Action |
Approve 4000 tons of DRO contaminated soil and 3 tons of investigative derived wastes (soil cuttings) to be transported to SPI-Kodiak for thermal treatment. |
Donald Seagren |
9/5/2003 |
Meeting or Teleconference Held |
CS staff attended and participated in a Kodiak Island Borough assembly meeting and public open house for FUDS on Kodiak. The COE updated the assembly on the status of current and upcoming projects. There was minimal community interest at the open house |
Jeff Brownlee |
9/25/2003 |
Meeting or Teleconference Held |
CS staff reviewed a briefing document and participated in a scoping meeting for the Airport Staging Area (ASA) FUDS in Kodiak. The ASA is two sites, the former Fire Training Pit and Building 520. An interim removal action was performed at both sites in 2001. About 20,000 cubic yards of soil impacted with dominantly DRO was removed from the Fire Training Pit and thermally remediated. The scoping meeting was to discuss the remedial strategy to cleanup the remaining downgradient 2-foot thick smear zone that extends toward the Buskin River along with groundwater contamination. The Coast Guard, EPA, and DEC are recommending more site characterization before doing a feasibility study. According to the COE a new Inventory Project Report (INPR) will need to be produced before RI/FS work can be done on the project. The current INPR is for Remedial Action work, so there may be a delay in the process for the INPR to go through COE approval. Petroleum contamination from a former UST at Building 520 has been removed and thermally remediated. Groundwater sampling shows levels below Table C cleanup values at the Building 520 site |
Jeff Brownlee |
2/4/2004 |
Update or Other Action |
Reviewed Site 16, Airport Staging Area, Tank Area 2 Removal Action report for Spring 2003 removal. Additional excavation required. Tentatively scheduled for 2004, pending funding. |
Donald Seagren |
4/26/2004 |
Meeting or Teleconference Held |
Staff participated in a scoping meeting for the Airport Staging Area FUDS on Kodiak Island. The EPA, Coast Guard (landowner), consultants and DEC participated in the meeting. The site has a large smear zone of DRO and GRO impacted soil and groundwater adjacent to the Buskin River. The purpose of the meeting was to agree on the investigation approach to ensure adequate information to proceed to a feasibility study. We agreed to pursue a soil screening effort using Laser Induced Fluorescence (LIF) verified with a percentage of borings and samples. This information will then be used to plan monitoring well installation. We also discussed the level of effort needed to evaluate ecological risk from contaminant transport to the Buskin River. The point of compliance boundary, sediment sampling, background sampling and tidal influences on groundwater were also discussed |
Jeff Brownlee |
6/17/2004 |
Update or Other Action |
File number assigned and entered into the Fileroom DB and CS DB. |
Alyce Hughey |
7/28/2004 |
Site Characterization Workplan Approved |
CS staff reviewed a workplan for a remedial investigation at the Airport Staging Area Fire Training Pit FUDS in Kodiak. The remedial investigation has been ongoing this summer. A removal action in 2002 removed approximately 20,000 cubic yards of impacted soil from the source area. A plume of dominantly DRO contamination with a thick smear zone has moved downgradient of the Fire Training Pit and toward the Buskin River. The Corps of Engineers has been using a rapid optical screening tool using laser induced fluorescence (LIF) technology to help characterize the site. The LIF is sensitive to PAHs in the contamination and fluoresces in proportion to the concentration. The next phase of work which the subject workplan applies to is the placement of 22 soil borings, 11 monitoring wells and eight sediment samples along depositional areas of the Buskin River. Characterization data will be used to develop a Feasibility Study to decide on a preferred remedy to address the remaining contamination |
Jeff Brownlee |
8/12/2004 |
Meeting or Teleconference Held |
CS staff participated in a comment resolution meeting for a remedial investigation workplan for the Fire Training Pit FUDS in Kodiak. The EPA, Coast Guard, and Corps of Engineers also participated in the meeting. Agreement was reached on the placement of thirteen monitoring wells and ten soil borings. The investigation is designed to fill data gaps and provide adequate information to produce a Feasibility Study. A smear zone approximately four feet thick extends several hundred feet from the source area. Approximately 20,000 cubic yards of impacted soil was excavated from the source area in 2002 |
Jeff Brownlee |
8/19/2004 |
Update or Other Action |
Contaminated Sites staff performed site inspections at several formerly used defense sites on Kodiak Island. Building A-711 and the Fire Training Pit are currently being investigated and the preferred remedial remedy is being implemented at Drury Gulch. Non-aqueous phase liquid (NAPL) was found in a well at Building A-711 beyond the known plume boundary. NAPL was also noted in an open-hole boring downgradient of the Fire Training Pit toward the Buskin River. The work at Drury has been on hold temporarily while a data quality problem is worked out. The contract laboratory discovered that the lab method (Accelerated Solvent Extraction) for PCB analysis was biasing the results low so the majority of samples were rerun using a different method (sonification). The contractor is analyzing the data and planning a strategy to incorporate the new information |
Jeff Brownlee |
9/24/2004 |
Update or Other Action |
File number issued 2601.38.073 |
Aggie Blandford |
10/27/2004 |
Meeting or Teleconference Held |
staff participated in a Kodiak Island Borough Assembly meeting to discuss the status of Formerly Used Defense Sites on the island. The Corps of Engineers also participated at the meeting. The DEC and COE contractor also participated in a public open house to solicit comments on the cleanup work being done on Kodiak. Turnout was light as is typical in Kodiak |
Jeff Brownlee |
12/15/2004 |
Update or Other Action |
Reviewed the file and requested an update on any corrective actions tha toccurred during 2004. Have data on all soil thermally remdiated during 2004. |
Donald Seagren |
1/12/2005 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a meeting with the Coast Guard, EPA, Corps of Engineers and contractors to discuss remedial investigations at two Formerly Used Defense Sites on Kodiak. The Fire Training Pit and Building A-711 both have large contaminant masses at the smear zone and are near the Buskin River, a major salmon stream on the island. The 2004 remedial investigations at both sites filled in several data gaps. A list of remedial alternatives was discussed for inclusion in the upcoming Feasibility Studies. The cleanup team decided that a treatability study would be useful to gauge the biological response and area of influence to additives to supplement attenuation. The treatability study is planned for the summer of 2005 |
Jeff Brownlee |
2/17/2005 |
Site Characterization Report Approved |
Contaminated Sites staff reviewed a draft Remedial Investigation Report for the Fire Training Pit Formerly Used Defense Site on Kodiak. 18 monitoring wells were installed and 24 Laser Induced Fluorescence probes were advanced to delineate the plume. The investigation showed Diesel Range Organics and low level Volatile Organic Carbons in a smear zone originating at the Fire Training Pit and extending for about 700’ toward the Buskin River. The smear zone contamination is 2-4 feet in thickness due primarily tidal influence from nearby Womens Bay. The plume appears to be in equilibrium. Approximately 20,000 cubic yards of contaminated soils were removed from the Fire training Pit source area in 2001 |
Jeff Brownlee |
6/17/2005 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a public open house for Formerly Used Defense Sites on Kodiak Island. Staff also conducted several site inspections. Proposed Plans for the Little Navy Annex Site and the Cape Chiniak Site were introduced at the Kodiak Island Borough assembly meeting. The open house had a moderate amount of interest with several community members stopping by to discuss sites and pick up information. |
Jeff Brownlee |
7/21/2005 |
Update or Other Action |
Contaminated Sites staff reviewed a draft/final Remedial Investigation report for the Airport Staging Area Formerly Used Defense Site in Kodiak, Alaska. The Fire Training Pit was used as a fire training area in the 1950’s and 1960’s. Free product was sprayed on the ground and ignited. A 20,000 cubic yard source soil interim removal action was completed in 2001. The area is near the Buskin River and is tidally influenced. A thick smear zone of primarily Diesel Range Organic contamination extends from the former training pit almost to the river. Data seems to show that the plume is attenuating at the edges and there doesn’t seem to be current contaminant migration into the estuary. A treatability study is planned for later this summer with a feasibility study this fall to consider remedial options |
Jeff Brownlee |
8/30/2005 |
Update or Other Action |
Contaminated Sites staff participated in site inspections at several Formerly Used Defense Sites on Kodiak Island. The EPA and the Corps of Engineers contractor also participated in the inspections. Sites visited include Cape Chiniak, Long Island, Millers Field, Asphalt Disposal Area, Drury Gulch, Building A-711, and the Airport Staging Area |
Jeff Brownlee |
12/12/2005 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a scoping meeting for Feasibility Studies at two Formerly Used Defense Sites in Kodiak, Alaska. The meeting was attended by the Corps of Engineers and their contractor, the U.S. Coast Guard and their contractor, the EPA and their contractor and the ADEC. The purpose of the meeting was to review data, results and conclusions from treatability studies at the Airport Staging Area Fire Training Pit and Building A-711. Both sites are near the Buskin River and have similar technical challenges. Both sites have large smear zones of primarily Diesel Range Organics above and below the water table. The treatability studies helped eliminate several technologies including Thermally Enhanced Soil Vapor Extraction, Solidification, Slurry Phase Biological Treatment and Bucket Augering. For the Feasibility Study we have retained Bioventing, Air Sparging, Chemical Oxidation, Open excavation with Thermal Desorption and Enhanced Bioremediation |
Jeff Brownlee |
12/22/2005 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a scoping meeting for Feasibility Studies at two Formerly Used Defense Sites in Kodiak, Alaska. The meeting was attended by the Corps of Engineers and their contractor, the U.S. Coast Guard and their contractor, the EPA and their contractor and the ADEC. The purpose of the meeting was to review data, results and conclusions from treatability studies at the Airport Staging Area Fire Training Pit and Building A-711. Both sites are near the Buskin River and have similar technical challenges. Both sites have large smear zones of primarily Diesel Range Organics above and below the water table. The treatability studies helped eliminate several technologies including Thermally Enhanced Soil Vapor Extraction, Solidification, Slurry Phase Biological Treatment and Bucket Augering. For the Feasibility Study we have retained Bioventing, Air Sparging, Chemical Oxidation, Open excavation with Thermal Desorption and Enhanced Bioremediation |
Jeff Brownlee |
1/19/2006 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a Kodiak Island Borough Assembly meeting to discuss the recent documents available for the review and the field work the COE will be doing this summer in the island. The COE and DEC were interviewed on public radio to discuss the Kodiak projects and overall contaminated site cleanup process. There was also a public open house to give community members the opportunity to bring up concerns and ask questions in person. As typical for Kodiak turn out was light |
Jeff Brownlee |
4/19/2006 |
Update or Other Action |
CS staff reviewed a Treatability Study and Pilot Study Design work plan for the Former Fire Training Pit and Building A-711 Building Formerly Used Defense Sites in Kodiak. The remedial alternatives oxidation and biosparging will be tested for contaminant mass and concentration reduction. The oxidation test will be performed at Building A-711 using RegenOx as a reagent. The groundwater will be monitored to check for migration of contamination into the aquifer. The biosparging test at the Fire Training Pit is designed to be a full scale test using sixteen injection wells. If the test is successful the test array will be able to utilized for the long term remediation |
Jeff Brownlee |
4/20/2006 |
Update or Other Action |
CS staff reviewed a Treatability Study and Pilot Study Design work plan for the Former Fire Training Pit and Building A-711 Building Formerly Used Defense Sites in Kodiak. The remedial alternatives oxidation and biosparging will be tested for contaminant mass and concentration reduction. The oxidation test will be performed at Building A-711 using RegenOx as a reagent. The groundwater will be monitored to check for migration of contamination into the aquifer. The biosparging test at the Fire Training Pit is designed to be a full scale test using sixteen injection wells. If the test is successful the test array will be able to utilized for the long term remediation |
Jeff Brownlee |
5/24/2006 |
Update or Other Action |
Staff participated in site inspections with a Corps of Engineers Pacific Ocean Division representative on Kodiak Island. Several Formerly Used Defense sites were toured by helicopter including Burma Road, Long Island, Buskin Lake, Cape Chiniak Tracking Station and Little Navy Annex |
Jeff Brownlee |
6/1/2006 |
Meeting or Teleconference Held |
Staff participated with the Corps of Engineers (COE) and their contractor in a public open house for the Formerly Used Defense Sites on Kodiak Island. We also attended the Kodiak Island Borough Assembly meeting. The COE gave a briefing on the work planned for this summer. The open house showed light interest which is normal for Kodiak. Staff also met with Coast Guard environmental personnel and inspected several sites on the Coast Guard Base |
Jeff Brownlee |
6/19/2006 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in a comment resolution meeting for the Airport Staging Area Formerly Used Defense Site on Kodiak Island. A bioventing system with eight injection wells will be installed for an 18 month test. The strategy is to raise the soil gas oxygen concentration to facilitate aerobic bacterial degradation of the primarily Diesel Range Organic contaminant mass. Pre test and post test soil samples will be collected to try to quantify system performance and decide if the remedial alternative is feasible for the entire site |
Jeff Brownlee |
6/21/2006 |
Update or Other Action |
Contaminated Sites staff reviewed a pilot study work plan for the Fire Training Pit Formerly Used Defense Site (FUDS) on Kodiak Island. The feasibility study chosen remedial option is bioventing. The system will have eight injection wells using a pulsed rotation pushing air into one well at a time to keep soil gas oxygen levels elevated. The pulse method will allow the contractor to use a much smaller blower and hence keep operating costs reduced. The test is designed to run 18 months. Pre and post soil sampling will attempt to statistically evaluate contaminant reduction. The inherent heterogeneity of subsurface soil sampling will cause this evaluation to be a challenging part of the test process |
Jeff Brownlee |
7/17/2006 |
Institutional Control Record Established |
Site included in the USCG Land Use Control Assurance Plan. |
Jeff Brownlee |
9/14/2006 |
Update or Other Action |
Contaminated Sites staff reviewed a Land Use Assurance Plan for Environmental Activities for the U.S. Coast Guard Base in Kodiak. The document outlines a plan to track institutional controls (ICs) at the various contaminated sites on base. There are currently about fifteen sites on base with institutional controls. The plan objective is for the Coast Guard Environmental Section to screen contractor and other activity such as above or below ground construction, well drilling, etc. against the sites listed in the plan. Work can then be tailored to meet any existing ICs |
Jeff Brownlee |
9/18/2006 |
Update or Other Action |
Staff participated in site inspections at several Formerly Used Defense Sites and Coast Guard sites at Kodiak. The EPA and Coast Guard also participated in the inspections. Remedial actions were being conducted at Drury Gulch, Airport Staging Area Fire Training Pit and Building A-711. The team spent a fair amount of time going over historic data with the contractor for the PCB cleanup at Drury Gulch. We also observed a test run of direct push sampling using a Geoprobe rig at the gulch for sampling data gap areas that were erroneously backfilled due to an extraction method error at the lab |
Jeff Brownlee |
3/5/2007 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in an annual update meeting for the formerly used defense sites on Kodiak Island. The meeting was held in Seattle and attended by representatives for the Corps of Engineers (COE), Coast Guard, Environmental Protection Agency, and DEC. The agenda concentrated on three sites that are in active investigation or remediation, the Fire Training Pit, Building A-711 and the Drury Gulch Polychlorinated Biphenyl (PCB) cleanup. The Fire Training Pit is in the beginning of a 16 month pilot study test using sparging to enhance natural biodegradation of the smear zone contamination. Building A-711 has completed a pilot study using an oxygen enhancer to attempt chemical oxidation of a fairly large heavy end petroleum plume. The pilot study showed that the total oxygen demand of the system was too large to overcome without being cost prohibitive. The oxidant was also show to mobilize lighter fraction hydrocarbons into the aquifer. The alternative option discussed were limited removal of the most impacted area. We will also revisit monitored natural attenuation as the plume is almost immobile. The majority of the meeting centered on the PCB cleanup at Drury Gulch. The team discussed the past work summary, estimated quantities in place, path forward to completion, storm water controls, and the use of the 95% upper confidence limit |
Jeff Brownlee |
6/14/2007 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in public meetings and site inspections for the Kodiak Formerly Used Defenses Sites (FUDS) on Kodiak Island. Three FUDS are active this summer including a continuing PCB removal at Drury Gulch, a below water smear zone excavation at Building A-711 and a biosparge pilot test at the Fire Training Pit. The Corps of Engineers and their contractor participated in a public open house and Kodiak Island Borough assembly meeting. Turnout was light for the open house, which is typical for Kodiak |
Jeff Brownlee |
7/12/2007 |
Update or Other Action |
Contaminated Sites staff reviewed a revised feasibility study for the former Fire Training Pit at the Airport Staging Area Formerly Used Defense Site (FUDS). The site was initially screened for about 45 different remedial technologies. This study evaluated the five that were carried through the draft process and included monitored natural attenuation, excavation with off site disposal, excavation with on site treatment, chemical oxidation and biosparging. The final evaluation will be done after a biosparging pilot test that is currently operating has been completed. The preferred remedy will be presented in the proposed plan for the site |
Jeff Brownlee |
11/2/2007 |
Site Characterization Report Approved |
Contaminated Sites staff participated in a Kodiak Island Borough Assembly meeting and public open house for the semiannual community update on the Formerly Used Defense Sites on Kodiak Island. The Corps of Engineers and their contractor also participated in the meetings. PCB impacted soil is continuing to be removed from Drury Gulch. About 860-tons of TSCA material and 1,500-tons of non-TSCA material have been removed this season with an estimated 700-tons remaining over cleanup levels. The diesel and residual range organic impacted soil removal has been completed at Building A-711. Approximately 16,000-tons of impacted soil was removed and stockpiled for future on island thermal remediation. The Airport Staging Area Fire Training Pit biosparging pilot study continues to operate with periodic groundwater and soil gas monitoring to evaluated performance. Interest was moderate at the open house with several people stopping by to discuss projects |
Jeff Brownlee |
3/21/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Jeff Brownlee |
5/22/2008 |
Update or Other Action |
Contaminated Sites staff reviewed and commented on a performance report for a biosparging system at a FUDS in Kodiak. The Airport Staging Area Fire Training Pit has been undergoing a pilot study with eight air injection wells in an attempt to enhance biodegradation of a primarily Diesel Range Organic impacted smear zone over a large area below about 12-feet of overburden. Follow up soil and water sampling after 16-months of the system being on don’t show a statistically significant decrease in contamination, however visual indications and soil gas measurements show a healthy bacteria population and oxidation changes in the smear zone. The department recommended the system stay on until we get another round of water data to see if any trends develop and to make sure there is no contaminant transport to a nearby estuary |
Jeff Brownlee |
8/12/2008 |
Site Visit |
Contaminated Sites staff conducted site inspections with the EPA and Coast Guard at several Formerly Used Defense Sites (FUDS) and Coast Guard sites on Kodiak Island. Field work had been done this season at Building A-711, Building A-141, Drury Gulch, Airport Staging Area, and the Site 3 Laundry. PCB and TCE soil removals have been completed at Drury Gulch and the contractor is working on the cap over the entire gulch and the drainage channel realignment. The biosparging pilot study at the Fire Training Pit is being evaluated and the cleanup team has decided to go back to the feasibility study and consider other remedial alternatives for the site |
Jeff Brownlee |
8/12/2008 |
Site Visit |
At the request of the project manager the quality assurance officer was onsite on August 12, 2008 to take part in a site visit. Several sites were inspected including the former fire training pit, and Drury Gulch remeditation project. No workplan deviations were noted. |
Brenton Porter |
1/22/2009 |
Meeting or Teleconference Held |
Contaminated Sites staff participated with the Corps of Engineers in a Kodiak Island Borough Assembly meeting and a public open house to discuss Formerly Used Defense Sites on Kodiak Island. An update was provided on sites currently being worked on including Drury Gulch, Buskin Beach, Airport Staging Area, and Building A-711 |
Jeff Brownlee |
3/19/2009 |
Meeting or Teleconference Held |
Contaminated Sites staff participated in an annual scoping meeting with the Corps of Engineers, EPA and Coast Guard for the Kodiak FUDS projects. Agenda items included review of the 2008 field season, and planned investigations and remedial actions at Building A-711, Airport Staging Area and various Coast Guard Sites including the Lube Pits, Building A-141, Buskin Beach, and the Asphalt Disposal Area |
Jeff Brownlee |
5/21/2010 |
Site Visit |
Contaminated sites staff conducted site visits and meetings for several Kodiak FUDS including Building A-711, Drury Gulch, Airport Staging Area, and Buskin Beach. Staff conducted an extensive site walk of Drury Gulch which experienced significant erosion and sedimentation onto the cap as a result of a 100-year storm event during which 8 inches of rain fell on Kodiak Island within 24 hours. The USACE is conducting long term monitoring at both Drury Gulch and Building A-711. Groundwater sampling was conducted at A-711 during the week of this site visit. Sediment will be sampled from the cap surface, outside the fenced area, and in the lower drainage areas of Drury Gulch later this summer. Extensive erosion control, reseeding, and sediment removal is also planned later in 2010. The Airport Staging Area is also being scheduled for a round of groundwater monitoring for October 2010. The site visit was attended by USACE, ADEC, and contracted FES personnel. A meeting was conducted on May 21 with USCG environmental management staff at the Kodiak Base Support Unit to discuss the status of visited sites with emphasis on the storm water drainage issues resulting from Drury Gulch. |
Curtis Dunkin |
9/22/2010 |
Site Visit |
During an annual site prioritization meeting on Kodiak with representatives from the EPA, USCG, USACE, and ADEC, contaminated sites staff conducted site visits at the following Kodiak FUDS: Drury Gulch/Site 18, Building A711, Airport Staging Area, Former Navy Landfill/Red Lake Site 2, Buskin Beach, and the Site 9 AvGas Tank Farm. |
Curtis Dunkin |
11/3/2015 |
Update or Other Action |
CS staff reviewed the draft 2014 Airport Staging Area Groundwater Monitoring Report and submitted comments to the Army Corps of Engineers. The draft monitoring report summarizes the 2014 sampling and analysis activities and results which, along with previous investigation efforts and results will be used to evaluate and determine the path forward and remedy for the site. The 2014 field observations and analytical results indicate that the soil and groundwater petroleum contaminant plumes are steady state and that contaminants are not migrating to the Buskin River and associated estuary. |
Curtis Dunkin |
4/16/2018 |
CERCLA SI |
ADEC reviewed the draft 2017 Hydraulic Gradient and NAPL Characterization Report (dated February 2018) and submitted its review comments to the Army Corps of Engineers. The report documents the additional remedial investigation activities conducted by the Corps in 2017 to address data gaps including a tidal and hydraulic gradient study,characterization of the NAPL at the site, collection and laboratory analyses of groundwater samples from select monitoring wells that are within the previously existing network, as well as collection and laboratory analyses of soil samples from newly installed soil boring locations within the estuary of the Buskin River. |
Curtis Dunkin |
9/25/2018 |
Site Visit |
ADEC's project manager for the Kodiak Army Navy FUDS traveled to Kodiak, AK and participated in two days of annual planning meetings and site inspections with project delivery team representatives from the Army Corps of Engineers, USCG, and Environmental Protection Agency. |
Curtis Dunkin |
2/26/2019 |
Document, Report, or Work plan Review - other |
ADEC reviewed the draft 2019 Groundwater Monitoring Well PFAS Sampling and Analysis Plan and submitted comments to the USCG. |
Curtis Dunkin |
3/13/2019 |
Meeting or Teleconference Held |
ADEC participated in a project prioritization and technical planning meeting with stakeholder representatives from the USCG, USACE, EPA, and their respective contracted technical support teams for the ongoing development and implementation of the 2019 Kodiak FUDS projects. |
Curtis Dunkin |
4/4/2019 |
Document, Report, or Work plan Review - other |
ADEC received and reviewed responses to comments from the USCG and participated in a technical planning and resolution meeting with the project delivery team for the draft final 2019 Groundwater Monitoring Well PFAS Sampling and Analysis Plan. ADEC submitted approval of the RTCs and for the USCG to finalize the SAP document and implement the plan in the field. |
Curtis Dunkin |
5/15/2019 |
Update or Other Action |
ADEC received and reviewed a letter from the Army Corps of Engineers (USACE) which summarized and outlined USACE-FUDS' internal evaluation and determinations that FUDS will discontinue including POL contaminants in its site characterization and risk evaluation in the estuary as a result of a March 2019 private-party fuel release that resulted in diesel fuel being released to the Buskin River and was subsequently transported and released to the estuary at the Airport Staging Area site. |
Curtis Dunkin |
6/26/2019 |
Update or Other Action |
ADEC received notification from the Army Corps of Engineers (USACE) that the USACE Center for Expertise had made a determination that the characterization and risk assessment data completed to date by the FUDS program was complete and adequate for what USACE-CX determined to be the limits of the FUDS-CERCLA related contamination and that the FUDS program would be terminating the prospective draft 2019-20 Addendum Remedial Investigation Work Plan. ADEC informed USACE that it did not entirely concur with that decision however USACE-FUDS expressed that it would coordinate with ADEC and other stakeholders to address the remaining ongoing concerns. |
Curtis Dunkin |
8/20/2019 |
Site Visit |
ADEC traveled to Kodiak, AK to participate in two days of annual project delivery team meetings and conduct site inspections with representatives from EPA, USACE, USCG, and their respective technical contract support. |
Curtis Dunkin |
4/15/2020 |
Meeting or Teleconference Held |
ADEC participated in a technical planning and project prioritization meeting via web/teleconference with project delivery team representatives from the US Army Corps of Engineers, US Environmental Protection Agency RCRA, and the US Coast Guard. |
Curtis Dunkin |
5/26/2020 |
Document, Report, or Work plan Review - other |
ADEC reviewed the USCG and AKDOT's draft preliminary technical design documents and provided input and comments through participation in a technical planning meeting for the prospective 2020-21 Kodiak Airport Perimeter Fence Construction Project. |
Curtis Dunkin |
8/12/2020 |
Meeting or Teleconference Held |
ADEC participated in an annual planning meeting with representatives from the Army Corps of Engineers, the US Coast Guard, and the Environmental Protection Agency for the purpose of providing respective status updates on the site action prioritization and project implementation schedules for all six Kodiak Army Navy Formerly Used Defense Sites. |
Curtis Dunkin |
9/8/2020 |
Document, Report, or Work plan Review - other |
ADEC reviewed the USCG and ADOT's final 2020 Environmental Management Plan for the Kodiak Airport Perimeter Fencing Upgrades Project and submitted final approval to ADOT and the USCG. |
Curtis Dunkin |
4/14/2021 |
Document, Report, or Work plan Review - other |
ADEC completed review of the final Site 35 Fire Training Pit Per- and Polyfluoroalkyl Substances (PFAS) 2019 Groundwater Sampling Report (final report dated January 2021), and submitted final approval of the report to the USCG. The report summarizes the USCG's preliminary groundwater investigation efforts that were conducted in 2019; of which the analysis results confirmed that multiple PFAS contaminants are present in groundwater at multiple monitoring well locations across the site. Additional follow on investigations are planned in the future by the USCG who is also conducting a Kodiak USCG Base-wide Preliminary Assessment (PA) effort for known and/or potential areas of concern that are associated with the use and/or discharge of aqueous film forming foam (AFFF). The USCG anticipates distribution of the draft PA report in 2021. |
Curtis Dunkin |
6/24/2021 |
Document, Report, or Work plan Review - other |
ADEC reviewed the scoping letter and preliminary project drawings for the Kodiak Airport Rehabilitation Project and submitted general review comments to the Alaska Department of Transportation and Public Facilities. |
Curtis Dunkin |
7/29/2021 |
Document, Report, or Work plan Review - other |
ADEC reviewed the revised draft 2021 Kodiak Airport Perimeter Fence Project Environmental Management Plan and submitted review comments to the ADOT&PF and USCG. |
Curtis Dunkin |
8/5/2021 |
Site Visit |
ADEC participated in annual project delivery team meetings for the Kodiak Army/Navy Formerly Used Defense Sites (FUDS) at the USCG Base Kodiak with representatives from the Army Corps of Engineers, USCG, EPA, and their respective contracted technical support representatives, and conducted site visits and inspections of the active FUDS on Base Kodiak. |
Curtis Dunkin |
9/28/2021 |
Document, Report, or Work plan Review - other |
ADEC received and reviewed responses to comments (RTCs) for the revised final redline Contaminated Materials Management Plan (CMMP) from ADOT&PF for its 2021 Kodiak Airport Perimeter Fence Construction Plan; including final 2021 Environmental Management Plan and Sampling Analysis Plan documents. ADEC submitted review determinations and approvals of the RTCs for the CMMP. ADEC also separately submitted final conditional approvals to ADOT&PF for the CMMP, EMP, and SAP, conditional of the USCG's acceptance and approvals. |
Curtis Dunkin |
9/29/2021 |
Document, Report, or Work plan Review - other |
ADEC reviewed the draft 2021 Human Health Risk Calculations Report and submitted review comments to the Army Corps of Engineers. |
Curtis Dunkin |
8/10/2022 |
Document, Report, or Work plan Review - other |
ADEC reviewed the final 2022 Kodiak Airport Perimeter Fencing Upgrades 2021 Pre-construction Sampling Summary Report and submitted a final approval letter to ADOT&PF. |
Curtis Dunkin |
10/24/2022 |
Document, Report, or Work plan Review - other |
DEC evaluated and returned commments to the USCG on the “Environmental Management Plan (EMP), Kodiak Airport Perimeter Fencing Upgrades Project, State Project No. SFAPT00144, Kodiak, Alaska” (Undated) and the “Contaminated Materials Management Plan, ADEC File No’s. 2601.38.112, 2601.26.003, 2601.38.006, 2601.38.073, KDK Airport Perimeter Fencing Upgrades, State Project No. SFAPT00144, October 17, 2022.” The revised draft EMP and contaminated materials management plan (CMMP) describe the excavation, stockpiling and sampling of PFAS-contaminated and potentially PFAS-contaminated media at the Kodiak Airport during fencing construction. |
Melinda Brunner |
10/25/2022 |
Site Visit |
DEC participated in the project delivery team meetings and site visits on Kodiak with USACE, USCG and EPA on October 25 & 26, 2022. The USCG Navy Landfill/Red Lk. Site 2, USCG Airport Staging Area, USCG Kodiak Drury Gulch Site 18, USCG Site 09 Avgas Tank Farm, and USCG MA6 DOT Building A-711 were visited to assess current conditions, land use controls in place, and feasibility of additional characterization (when needed) given terrain. |
Melinda Brunner |
2/10/2023 |
Document, Report, or Work plan Review - other |
ADEC reviewed the revised redline final 2022/23 ADOT&PF Kodiak Airport Perimeter Fence Environmental Management Plan and the Contaminated Materials Management Plan and submitted an approval letter to DOT&PF to finalize the document and implement the plan in the field. |
Curtis Dunkin |