Action Date |
Action |
Description |
DEC Staff |
9/2/1995 |
Update or Other Action |
(Old R:Base Action Code = RI - Remedial Investigation). Action date used is the date of the Air Force Relative Risk Evaluation Worksheet, which indicates the site is in the RI phase. |
Former Staff |
3/3/1997 |
Site Added to Database |
Site added by Shannon and Wilson. |
S&W |
2/6/2003 |
Site Number Identifier Changed |
Changed the Region from 36 to 31 and Sequence Number from 10 to 06. |
Former Staff |
9/5/2003 |
Site Number Identifier Changed |
Changed the Workplan from X9 to X1. |
Former Staff |
9/17/2003 |
Update or Other Action |
Staff completed a site visit of Bullen Point and Point Lonely Distant Early Warning Sites in order to determine the condition of their dump sites and the erosion impacts. The dump sites at both places are on the lagoon-side of the facilities so are not experiencing the dramatic effects of erosion that have been seen at Oliktok or Barter Island. However, the face of the dumps are becoming exposed and there is debris in the adjacent surface water bodies. These sites will need to addressed during the Air Force’s Clean Sweep Operations. Another issue was identified at Point Lonely, though, that requires immediate attention. The ocean-side of the facility has lost over 150 feet of shoreline this summer. This has caused a pump house (deactivated) to collapse on to the beach. It appears there was a small fuel release when the building and pipes collapsed. PERP was on site and had the Air Force take samples to determine the extent. Additional actions will be taken upon receipt of the results. |
Ann Farris |
6/1/2005 |
Site Ranked Using the AHRM |
Initial site ranking. |
Emily Youcha |
6/1/2005 |
Site Characterization Workplan Approved |
Staff approved a remedial investigation/feasibility study workplan for the site. Work will be conducted in July/August 2005. Samples will be collected for DRO/RRO, GRO, BTEX,VOCs, PCBs, metals, and PAHs. |
Emily Youcha |
7/25/2005 |
Update or Other Action |
Staff attended a site visit to Pt Lonely AFS on July 18 with BLM representatives. Debris from the landfill can be seen at the edge of the lagoon. |
Emily Youcha |
7/29/2005 |
Meeting or Teleconference Held |
Contaminated Sites staff is working with the Air Force on creating a template for ecological and human health risk assessments covering six sites across the North Slope, including this site. The Air Force determined it needs to conduct base-line risk assessments at these sites prior to making cleanup decisions on them. Developing a template is an effort to make the process more efficient. |
Emily Youcha |
12/8/2005 |
Meeting or Teleconference Held |
Staff attended the Restoration Advisory Board meeting in Barrow and provided a summary of the current activites at the site. |
Emily Youcha |
3/21/2006 |
Update or Other Action |
Staff received a copy of the 2005 draft RI/FS. Staff participated in a meeting with the BLM and the Air Force on February 17 to discuss the status of Pt. Lonely and a potential transfer of the Air Force Buildings to the North Slope Borough. |
Emily Youcha |
5/15/2006 |
Update or Other Action |
Staff reviewed the RI/FS for this site. PCBs were detected in 1 of 2 sediment samples. Selenium was detected in surface water at a concentration of 358 ug/L, above the screening criteria. It is unknown if the selenium is naturally occuring or anthropogenic. DRO was detected in landfill soils above Method One cleanup levels in 6 of 12 samples. RRO was detected above Method One cleanup levels in 4 of 12 samples. Stained gravels were seen in several test pits. The estimated size of the landfill is 27,000 square feet. The density and thickness of debris is variable. The average thickness is probably 3.5 ft. The estimated volume of the landfill is 3500 cu. yds, not including the cap. Erosion of the site is estimated to be lower than the average rates for Pt. Lonely due to the protective lagoon. |
Emily Youcha |
5/26/2006 |
Update or Other Action |
Contaminated Sites staff recently obtained term contractor review of a draft Air Force North Slope Risk Assessment Work Plan (RAWP). Comments were received from the term contractor, and a comment review teleconference was held with the term contractor risk assessor on 5/10/06. The RAWP seeks to develop risk based cleanup levels based on exposure pathways for categories of sites (e.g., garage sites) at Air Force radar stations in the north slope region. The work plan is generally well written, but some of the key items that need clarification are how data gaps will be handled at individual sites; determination of background levels for organics and inorganics; how it will be determined whether a large water body is potentially affected by a site; and how toxicity will be determined for trichloroethylene. |
Emily Youcha |
6/1/2006 |
Meeting or Teleconference Held |
Staff met with the Air Force to resolve comments on the 2005 RI/FS. It is thought that the cleanup of the landfill will result in decreased selenium concentrations in the adjacent lagoon. The thought is that the selenium may be natually occuring in the soil (although there is no background data), but the conditions in the landfill are anoxic resulting the the selenium going into solution. If the landfill is cleaned up, this will no longer occur. Long-term monitoring of the selenium after the landfill removal may be needed. |
Emily Youcha |
7/11/2006 |
Meeting or Teleconference Held |
Staff performed a site visit to Pt. Lonely with the North Slope Risk Assessment team. Sites SS03 and SS02 are included as template sites, but nearly all sites at Pt Lonely were visited. The former location of the pumphouse was identified and has not yet eroded into the ocean. The coast continues to erode, particularly in the vicinity of the former Sewage Outfall site and little beach remains for vehicle or foot travel on the beach in that area. |
Emily Youcha |
7/13/2006 |
Update or Other Action |
Contaminated Sites staff was informed by an Air Force contractor that Pacific Air Forces issued a policy regarding the cleanup of landfills. Apparently, only compliance funding (rather than the Defense Environmental Restoration Account) can be used for the cleanup of the landfills, even if hazardous substances are present in the landfill. Due to the lack of compliance funding, many landfills are not programmed for clean up until 2013 at the earliest, including the Point Lonely DEW Line landfill. However, the Air Force project manager for Oliktok believes compliance funds for removal of the Oliktok eroding landfill are secured and available for the 2007 performance-based contract cleanup. |
Emily Youcha |
8/18/2006 |
Meeting or Teleconference Held |
Contaminated Sites staff met with the Air Force and the Bureau of Land Management (BLM) to discuss the upcoming cleanup at Point Lonely Air Force Station. This site is located in a right-of-way on BLM property and the Air Force has to meet several environmental requirements before relinquishing the property. The Air Force requested to re-open a permitted landfill at Point Lonely for one time use to deposit demolition debris and low-level petroleum-contaminated soil. BLM is hesitant to approve it because landfills built on BLM property are not consistent with their policy. |
Emily Youcha |
7/11/2007 |
Exposure Tracking Model Ranking |
Intitial Ranking Complete for Source Area: 73902 (Autogenerated Action) |
|
10/25/2007 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
12/11/2007 |
Risk Assessment Report Approved |
ADEC received the Final Risk Evaluation Report – Alaska North Slope Radar Installation Sites on November 6, 2007. This report meets the requirements of the ADEC Contaminated Sites Program Risk Assessment Procedures Manual, adopted by reference in 18 AAC 75.340. An approval letter was sent to Dave Cook, Program Manager HQ PACAF/A7NR, on December 10, 2007
This project identified categories of sites that are common on remote Air Force installations in the North Slope region of Alaska and developed conceptual site models and human health and ecological risk based screening levels for four of these categories: garage sites, fuel storage sites, non-fuel storage sites, and transformer sites. The project developed templates for conducting human health and ecological risk evaluations for these categories and performed a risk evaluation as a test case for one example of each type of site. The final report contains guidance on applying the process to other North Slope region sites. It may be used on a site-specific basis as a tool to assist in assessing potential risks posed by North Slope Air Force installation sites.
|
Tamar Stephens |
12/13/2007 |
Public Notice |
Public meeting was held in Barrow to present Proposed Plan. Public comment period: 12/13/2007 - 1/11/2008. DEC contaminated sites staff attended. |
Tamar Stephens |
7/10/2008 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
7/30/2008 |
Document, Report, or Work plan Review - other |
Staff reviewed and approved the Draft Quality Assurance Program Plan for 2008 Clean Sweep Activities (Cleanup Plan) for USAF Point Lonely SRRS. This work plan describes the cleanup activities that will be conducted at the Point Lonely SRRS during 2008. Activities specific to Landfill LF007 are excavation of buried material and contaminated soil from the site, with off-site disposal of soil that exceeds 18 AAC 75.341 Method 2 cleanup levels. Soil with petroleum contamination below Method 2 may be landspread at SS005. Inert debris is planned for disposal through an expansion of onsite landfill LF011. |
Tamar Stephens |
8/5/2008 |
CERCLA ROD Approved |
Decision document signed. Decision document was signed by Colonel Brent Johnson, USAF, on 8/4/2008 and by DEC Environmental Program Manager John Halverson on 8/5/2008. Key elements of the selected remedy are excavation of buried material and contaminated soil; off-site disposal at treatment, storage, or dispoal facilities of soil that exceeds 18 AAC 75.341 Tables 2A and 2B Method 2 cleanup levels for the arctic zone; landspreading of petroleum contaminated soil below Method 2 cleanup levels; landfilling of inert debris in an expansion of Point Lonely landfill LF011. |
Tamar Stephens |
8/5/2008 |
Cleanup Level(s) Approved |
Cleanup levels were approved with signing of the Decision Document on 8/29/2008. Cleanup levels are the Method One Arctic Zone cleanup levels from 18 AAC 75.341 Table A2 for DRO and RRO, and Method Two Arctic Zone Table B1 cleanup levels for PCBs or other compounds. |
Tamar Stephens |
8/29/2008 |
Document, Report, or Work plan Review - other |
Staff reviewed and sent comments on the Draft Quality Assurance Program Plan (cleanup work plan) for 2009 Clean Sweep Activities at the U.S. Air Force Point Lonely Short Range Radar Station, Alaska. |
Tamar Stephens |
10/13/2008 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
3/12/2009 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
7/17/2009 |
Cleanup Plan Approved |
Staff approved the Final Quality Assurance Program Plan (Cleanup Plan) for 2009 Clean Sweep Activities to continue cleanup started in 2008. |
Tamar Stephens |
12/13/2009 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
3/17/2010 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
3/18/2010 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
4/21/2010 |
Document, Report, or Work plan Review - other |
Staff reviewed and sent comments on the Draft Cleanup Report for 2008-2009 Clean Sweep Activities, Point Lonely Short Range Radar Station, Alaska. This report describes cleanup actions that were performed during 2008 and 2009 at the Point Lonely Short Range Radar Station. |
Tamar Stephens |
6/17/2010 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
7/29/2010 |
Document, Report, or Work plan Review - other |
Staff reviewed and sent comment on the draft Point Lonely Work Plan for 2010 Site Activities. The work plan describes activities to be conducted at Point Lonely during summer 2010. |
Tamar Stephens |
8/23/2010 |
Document, Report, or Work plan Review - other |
Contaminated sites staff sent an approval letter for the final Work Plan for 2010 Site Activities (August 2010) for Point Lonely Short Range Radar Station on August 9, 2010. The work plan describes activities to be conducted at Point Lonely during August 2010: Soil sampling to delineate the remaining petroleum contaminated soil at the Drum Storage Area (SS002); Surface water sampling at the Old Landfill (LF007); Inspection of LF007 for surface erosion or exposed solid waste; Surface and active zone water sampling at the South Landfill (LF011/partial relocation of LF007); Surface water sampling at the Landspread Area (SS006) to verify water quality standards are not exceeded; Visual inspection of LF011 for subsidence, erosion, and revegetation; Identification and mapping of above-ground and below-ground fuel pipelines for removal and disposal under future clean sweep activities; Performing a topographic survey of approximately 23 acres on the south side of the runway, toward the eastern end, as a potential future landfill site; Perform a top-of-bluff survey as part of an ongoing effort to track coastal erosion at the facility; Inspecting contents of the hangar.
|
Tamar Stephens |
10/14/2010 |
Meeting or Teleconference Held |
DEC staff attended Barrow Restoration Advisory Board meeting. |
Tamar Stephens |
3/17/2011 |
Meeting or Teleconference Held |
DEC project manager Tamar Stephens attended Barrow Restoration Advisory Board Meeting. |
Tamar Stephens |
9/1/2011 |
Document, Report, or Work plan Review - other |
Staff reviewed and sent comments on the draft 2010 Supplemental Remedial Investigation and Pipeline Survey report for U.S. Air Force Point Lonely Short Range Radar Station (SRRS). |
Tamar Stephens |
10/13/2011 |
Meeting or Teleconference Held |
DEC project manager Tamar Stephens attended Barrow Restoration Advisory Board Meeting. |
Tamar Stephens |
11/14/2011 |
Update or Other Action |
) Landfill contents were excavated during 2008 and 2009.
2) Soil was disposed as follows:
• POL soil > Method 2 was disposed off site (30 yd)
• PCB soil >5 mg/kg disposed off site (160 yd);
• PCB soil between 1-5 mg/kg: 160 yd disposed off site and 1,605 yd currently stored in hangar
• No POL soil landspread: 5,110 yd with debris disposed in LF011; 1,125 yd with debris currently stored in hangar.
• Lead-contaminated soil currently stored in hangar (20 yd)
3) Inert wastes: 250 yd disposed in LF011; 50 yd currently stored in hangar.
Soil stockpile area: approx. 200 yds scraped from surface, then sampled. Confirmation samples show it meets method 1 cleanup levels for POLs; <1 mg/kg PCBs. Still has small solid waste items in soil.
|
Debra Caillouet |
6/11/2014 |
Document, Report, or Work plan Review - other |
Draft Remedial Cleanup/Building Demolition and Debris Removal Work Plan, Point Lonely Short Range Radar Station, AK, June 2014 |
Debra Caillouet |
3/2/2015 |
Document, Report, or Work plan Review - other |
Draft Construction Completion Report #2, 2014 Building Demolition, Point Lonely Short Range Radar Station, AK, February 2015 |
Debra Caillouet |
3/10/2015 |
Document, Report, or Work plan Review - other |
Comment was sent on the Draft Construction Completion Report #1, LF007 (Old Dump Site No. 1), Point Lonely Short Range Radar Station, AK, February 2015. |
Debra Caillouet |
4/14/2015 |
Document, Report, or Work plan Review - other |
Draft Final LF007 Point Lonely CCR #1
ADEC does not accept the characterization that was completed for LF007 for use in determining what portions exceed the Method 1 cleanup levels.
There are two main concerns.
The response to the comment on the interpretation of the silica gel cleanup does not include any narrative explaining why the chromatograms show the presence of naturally occurring organics. The guidance requires this to support any contention that biogenic interference has elevated the sample results and that based on this they are not above cleanup levels. The InterpretationofChromatograms.pdf” is just a set of the chromatograms. The SGS case narratives say either “unknown hydrocarbon” or “middle distillate”. There is no evidence that a person with experience reviewing biogenic material in chromatograms looked at these and made a determination.
There has been no documentation that the MI samples were managed or prepared in accordance with the ADEC guidance. The 30 g aliquots were not collected by weight and there is no demonstration that any attempt to achieve uniformly sized aliquots. There is no demonstration that the samples were dried and sieved. One sample was reported at 27% solids which demonstrates that the samples were not dried.
This rejection of the characterization data requires a revision to the work plan submitted for the 2015 season.
|
Debra Caillouet |
5/12/2015 |
Document, Report, or Work plan Review - other |
In response to an emailed comment response a letter was sent that concluded: ADEC does not accept the characterization of LF007 as sufficient to determine locations where the cleanup levels have been met.
The DUs that were confirmed to be above the cleanup levels can be managed as contaminated soil for the 2015 field work. All other DUs are either to be resampled appropriately or managed as contaminated soil.
|
Debra Caillouet |
7/24/2015 |
CERCLA Remedial Design/Remedial Action Plan Approved |
Final UFP-QAPP for Remedial Activities at Point Lonely Short Range Radar Station, AK, Revision 1 July 2015 |
Debra Caillouet |
7/31/2015 |
Update or Other Action |
Transfer to Fairbanks |
Susan Carberry |
8/4/2015 |
Update or Other Action |
Project management changed from Caillouet to Carnahan. |
John Carnahan |
8/7/2015 |
Meeting or Teleconference Held |
Teleconference with BEM contracting and AF representatives to discuss site status and closure determination for LF007. Approval of closure sampling requirements summarized in email to AF RPM. |
John Carnahan |
8/27/2015 |
Document, Report, or Work plan Review - other |
The revised approach submitted on August 27, 2015 consisting of re-sampling the Pt. Lonely Modular Train using an ISM approach is approved.
|
John Carnahan |
10/7/2015 |
Meeting or Teleconference Held |
Review CA14-16 and CA16-18 JEPs. Complete State Performance Reporting. |
John Carnahan |
4/8/2016 |
Document, Report, or Work plan Review - other |
Provide comments on Draft LF007 Remedial Action Completion and Site Closure Report for Old Dump Site No. 1. |
John Carnahan |
9/14/2016 |
Cleanup Complete Determination Issued |
Cleanup Complete Determination with no IC requirement issued. |
John Carnahan |
1/17/2017 |
Update or Other Action |
Stephen Krause replaces Lori Roy as the AF RPM for Barter, Bullen, Wainwright, Lisburne, Point Lonely, Oliktok, Lake Louise, Big Mtn and Duncan Canal. |
John Carnahan |