Action Date |
Action |
Description |
DEC Staff |
11/18/1998 |
Update or Other Action |
Site visit. |
Sally Schlichting |
11/24/1998 |
Update or Other Action |
Sole source contract initiated to finger print and date hydrocarbon contamination. |
Sally Schlichting |
5/29/1999 |
Site Characterization Report Approved |
Contamination at the site was deemed responsibility of property owner. |
Sally Schlichting |
7/8/1999 |
Cleanup Plan Approved |
Cleanup plan for contamination on property approved. |
Sally Schlichting |
8/27/1999 |
Update or Other Action |
RSA- DOT $16K. |
Sally Schlichting |
11/18/1999 |
Update or Other Action |
Request for site characterization. |
Sally Schlichting |
11/26/1999 |
Site Added to Database |
Free product (diesel) was encountered in 11/98 at the vacant lot owned by Mary Lou Moe at 20th and State Streets. |
Sally Schlichting |
11/29/1999 |
Site Ranked Using the AHRM |
Initial ranking. |
Sally Schlichting |
11/29/1999 |
Update or Other Action |
Cost Recovery Letter Issued this date. |
Sally Schlichting |
8/21/2001 |
Update or Other Action |
Site visit conducted. |
Anne Marie Palmieri |
12/5/2001 |
Update or Other Action |
RFP for installation of monitoring wells and sampling issued to Hart Crowser. |
Anne Marie Palmieri |
7/16/2002 |
Update or Other Action |
The State is paying for the cleanup. The contamination is on RP's land but it seems to be coming from upgradient. Several organizations (City/State/White Pass) are potential RPs and trying to figure out who is responsible. |
Anne Marie Palmieri |
1/15/2003 |
Update or Other Action |
RFP for site characterization issued to CH2M Hill. |
Anne Marie Palmieri |
5/13/2003 |
Site Ranked Using the AHRM |
Site reranked with new information from CH2M Hill. |
Anne Marie Palmieri |
9/24/2003 |
Site Characterization Report Approved |
CH2M Hill Final Report approved. Report was sent to RP via her attorney and John Mielke for the church. |
Anne Marie Palmieri |
3/4/2004 |
Update or Other Action |
Request for access letters sent to adjacent landowners Kurt Kosters and Les Fairbanks for the 4/04 sampling event. |
Anne Marie Palmieri |
6/4/2004 |
Update or Other Action |
Project manager transition site visit - obtained GPS reading |
Bill Janes |
7/7/2004 |
Site Characterization Report Approved |
Site Characterization Report was approved. Additional data was obtained in May 2004 to determine if contamination on-site was a result of upgradient sources. Contamination source appears to be on-site. |
Anne Marie Palmieri |
7/12/2004 |
Update or Other Action |
Letter was sent to RP via her attorney stating that DEC has determined source is on-site. |
Anne Marie Palmieri |
10/21/2004 |
Update or Other Action |
Telecon with Thurbon and Sullivan. Next step is to talk to RP's consultant to get a briefing on his findings. |
Bill Janes |
2/8/2005 |
Update or Other Action |
Telecon with RP's attorney. He is looking for the report on the upgradient Coach Cleaning Shop because RP's consultant believes it has information on age of diesel. RP's attorney indicated they may be ready to go forward with remediation if it appears stable and is not migrating. |
Bill Janes |
2/16/2005 |
Update or Other Action |
Reviewed Coach Cleaning Shop file. Nothing in the report regarding diesel aging. |
Bill Janes |
9/28/2006 |
Update or Other Action |
RP's attorney called. Would like to get things moving again. Will be checking with a consultant to put together a plan to resample the property. |
Bill Janes |
2/26/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Bill Janes |
5/6/2011 |
Document, Report, or Work plan Review - other |
Email approval sent this date to RP's attorney for the groundwater sampling and analysis plan submitted by Carson Dorn. Four wells to be sampled for GRO, DRO and BTEX. |
Bill Janes |
11/8/2011 |
Update or Other Action |
Environmental Site Assessment Workplan for the property received. |
Erik Norberg |
1/22/2013 |
Document, Report, or Work plan Review - other |
Environmental Site Assessment Workplan for the property reviewed. The report includes an investigation of three groundwater wells, MW-1, MW-2, and MW-3 at this site. A free product thickness of 0.18 inches was measured in MW-1 and a sheen was observed during sampling. DRO was found in MW-1 at a concentration of 2.3 mg/l, ethylbenzene at 0.01550 mg/l and xylenes at 0.03915 mg/l. No free product was observed in wells MW-2 & MW-3. DRO was detected at a concentration of 0.020 mg/l and RRO at a concentration of 0.18 mg/l in MW-3. |
Erik Norberg |
9/11/2013 |
Update or Other Action |
Staff changed from Erik Norberg to Denise Elston. |
Kristin Thompson |
5/16/2014 |
Update or Other Action |
Working with CDI on possible monitoring well sampling. |
Danielle Duncan |
5/20/2014 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73958 Unknown Source. |
Danielle Duncan |
5/21/2014 |
Update or Other Action |
Discussed options moving forward with attorney for RP and decided to move forward with an NEC given that obtaining more groundwater monitoring data is not possible at this time. |
Danielle Duncan |
6/6/2014 |
Institutional Control Record Established |
Notice of Environmental Contamination
As required by the Alaska Department of Environmental Conservation (ADEC), Grantor, pursuant to 18 AAC 75.375 b (3), Mary Lou Moe, Grantee, as the owner of the subject property, hereby provide public notice that the property located at: Parcels 11 and 12 of Lot 119 in Skagway, AK
has been subject to a discharge or release, regulated under 18 AAC 75, Article 3, as revised April 8, 2012.
In November of 1998, during excavation for a new foundation, free-phase hydrocarbons were discovered at the water table (7 ft. below ground surface) on the property. Approximately 100 gallons of free-phase hydrocarbon was recovered at that time. Since then, multiple environmental studies have been conducted on the property and both free-phase hydrocarbon and contaminated soil have been discovered. Due to groundwater contamination, monitoring wells were installed and sampled on various occasions both on the Moe property and neighboring lots. Some of these wells had concentrations of hydrocarbons exceeding groundwater cleanup levels established in 18 AAC 75.345, Table C. The most recent monitoring well data (2011) indicates that groundwater contamination is still present at values exceeding groundwater cleanup levels. During the 2011 monitoring well sampling event, free-phase hydrocarbon was present at a thickness of 0.18 inches and diesel range organics (DRO) was present exceeding cleanup levels. |
Danielle Duncan |
10/5/2015 |
Update or Other Action |
Requested a work plan this date - certified letter # 7014 0150 0000 1161 6845 |
Danielle Duncan |
3/2/2016 |
Update or Other Action |
2nd formal request for a work plan this date. Certified # 7014 2021 0001 4209 6144. |
Danielle Duncan |
3/31/2016 |
Update or Other Action |
Rec'd a call from the RP's attorney - may be able to get this site moving again. |
Danielle Duncan |
5/9/2016 |
Update or Other Action |
3rd request for a work plan. Certified # 7014 2120 0001 4209 8308 |
Danielle Duncan |
6/1/2016 |
Update or Other Action |
Discussed the site with the RP's attorney. We hope to find traction on this site soon. |
Danielle Duncan |
8/24/2016 |
Update or Other Action |
Spoke with the DOT today and they have some work planned in the ROW on the storm water drains, curbs, and gutters on State St. from 1st to the bridge. The City of Skagway will be doing work first in the ROW to a depth of about 8 feet replacing water lines. |
Danielle Duncan |
10/17/2016 |
Update or Other Action |
A consultant has been notified and I should see a work plan to review soon. |
Danielle Duncan |
8/22/2017 |
Update or Other Action |
Per the responsible party's attorney a work plan should be received soon. |
Danielle Duncan |
10/16/2017 |
Document, Report, or Work plan Review - other |
Approved the work plan to excavate 3 test pits (TP) until encountering groundwater (approximately 7-8 feet below ground surface) on the Moe property. TP1 will be excavated in the location of monitoring well 1 where free product was observed in 2011. TP2 will be located at a location where historic field screening data indicated petroleum contamination at 5-7 feet below ground surface at 560 parts-per-million. TP3 will be located where historic field screening data indicated a petroleum concentration of 600 parts-per-million at 4-6 feet below ground surface. If groundwater monitoring well 1 where free phase petroleum product was found in 2011 can be located, then it will be sampled and analyzed for the same analytes as the soil. |
Danielle Duncan |
5/29/2018 |
Update or Other Action |
Skagway finally thawed enough to dig and sample. The samples are out Gold Streak this morning. As authorized, the soils excavated from the test pits are now stored on and under impermeable tarps. I gave permission to repack the trenches with those materials for now. |
Danielle Duncan |
8/6/2018 |
Site Characterization Report Approved |
Approved the Gubala Consulting report dated July 19, 2018. Three test pits were advanced on site using an excavator where historic data indicated the presence of petroleum soil contamination. Oily sheens but no free product were observed on the groundwater surface. The contaminated horizon appeared at the approximate same depth (5.5 to 6 ft. belowground) for each test pit. The results found no chlorinated compounds, but petroleum contamination above ADEC cleanup levels set forth in 18 AAC 75.340 Tables B1 and B2. Contamination was highest at TP2 and TP3 consistent with the former location of a cabin. DRO values ranged from 800 to 9,800 milligrams per kilogram (mg/kg) and GRO ranged from 30 to 410 mg/kg. The VOC and PAH results were also above cleanup levels in some cases. |
Danielle Duncan |
9/5/2019 |
Update or Other Action |
Per the responsible party's attorney a response letter for last years site work is in the works. |
Danielle Duncan |
12/15/2020 |
Document, Report, or Work plan Review - other |
On December 15, 2020 ADEC received the "SGY: State Street Pavement Rehabilitation Project No. 0972018/Z680850000 Contamianted Media Plan Guidance" dated October 29, 2020. The work plan summarizes procedures and construction practices to manage contaminated material if encountered, manage dewatering activities in accordance with an ADEC Dewatering permit, if necessary, field screen disturbed soil for potential contamination and manage potentially contaminated soil for reuse or disposal. |
Rachael Petraeus |
3/1/2023 |
Meeting or Teleconference Held |
Spoke with a relative of the owner of the property to arrange a site visit and talk about status of the site. |
Flannery Ballard |
3/7/2023 |
Site Visit |
The DEC undertook a site visit at the property this date. The DEC took photos, saved to the site file, and discussed the site history and its current status with a prospective buyer. |
Flannery Ballard |
5/22/2023 |
Potentially Responsible Party/State Interest Letter |
The DEC sent a PRP letter to Mr. Jay Burnham, who purchased the property on May 18, 2023. |
Flannery Ballard |