Action Date |
Action |
Description |
DEC Staff |
12/18/1998 |
Site Ranked Using the AHRM |
Initial ranking. |
Greg Light |
9/8/1999 |
Update or Other Action |
FS seeking federal funding to perform an Engineering Evaluation/Cost Analysis to determine the most favorable method for removing the threat posed by copper and other contaminants, and to remove from the site all hazardous substances posing an imminent threat of release. |
Bill Janes |
11/4/1999 |
Site Added to Database |
Heavy metal contamination of surface water and marine organisms and sediments. Petroleum product contamination of soil. |
Bill Janes |
12/18/2001 |
Update or Other Action |
Project tickler review - email to Ken Maas regarding status of EECA. Statement of work for the EE/CA and are in the process of selecting using a GSA-contractor to do the work. Money obligated to do this job this summer. |
Bill Janes |
7/12/2002 |
Site Characterization Workplan Approved |
EE/CA workplan approved this date. Work should occur in late July 2002. |
Anne Marie Palmieri |
11/1/2002 |
Update or Other Action |
Preliminary data report; more contamination found; additional characterization will occur summer '03. |
Anne Marie Palmieri |
5/25/2005 |
Update or Other Action |
In a telephone call with the USFS, Ken Maas stated that the PRP search has been completed and the USFS will continue with EE/CA field activities in FY06. |
Anne Marie Palmieri |
9/25/2006 |
Site Characterization Workplan Approved |
Site characterization (EE/CA phase 2) workplan approved this date. Staff commented on draft and risk assessor (M. Brewer) comments submitted later. Fieldwork conducted in Sept. 2006. |
Anne Marie Palmieri |
3/31/2007 |
Update or Other Action |
Draft EE/CA submitted to DEC. Both DEC and Dept of Health staff review and comment on the document. Additional samples are needed and risk evaluation modifications need to be made. |
Anne Marie Palmieri |
4/30/2007 |
Exposure Tracking Model Ranking |
ETM ranking |
Anne Marie Palmieri |
8/9/2007 |
Meeting or Teleconference Held |
DEC meets with EPA to request EPA involvement with the site due to lack of forward progress by the USFS. |
Anne Marie Palmieri |
2/7/2008 |
Meeting or Teleconference Held |
Meeting held with EPA and USFS. |
Anne Marie Palmieri |
1/23/2009 |
Meeting or Teleconference Held |
Meeting with EPA to discuss outreach for proposed NPL listings. |
Anne Marie Palmieri |
1/29/2009 |
Meeting or Teleconference Held |
Meeting with USFS and EPA to discuss potential proposal on National Priorities List. |
Anne Marie Palmieri |
2/18/2009 |
Meeting or Teleconference Held |
Meeting with DNR to discuss potential proposal on the National Priorities List. |
Anne Marie Palmieri |
5/4/2009 |
Site Visit |
Site visit with USFS, DNR, DEC and Law. |
Anne Marie Palmieri |
5/5/2009 |
Meeting or Teleconference Held |
Public meeting with Organized Village of Kasaan at the POW Mining Symposium in Craig |
Anne Marie Palmieri |
7/17/2009 |
Update or Other Action |
Commissioner Hartig sends a letter to EPA stating that the State does not object to the Salt Chuck Mine being included on the National Priorities List. |
Anne Marie Palmieri |
8/13/2009 |
Meeting or Teleconference Held |
Meeting with EPA, USFS, and URS to discuss spending of USFS stimulus funds for this site. |
Anne Marie Palmieri |
9/22/2009 |
Update or Other Action |
Site proposed for National Priorities List; 60 day public comment period begins. |
Anne Marie Palmieri |
5/7/2010 |
Record of Decision |
Non-Time Critical Action Memo signed by the USFS. Selected alternative is excavation of contaminated soil and off-site disposal using a haul road. |
Anne Marie Palmieri |
5/7/2010 |
Update or Other Action |
EE/CA approved this date. The April 2010 EE/CA is focused on the USFS-uplands only. Information concerning the 2002 and 2006 sampling of the marine tidelands is included in the appendicies and the still draft 2007 EE/CA. |
Anne Marie Palmieri |
9/10/2010 |
Update or Other Action |
DEC was notified that the USFS has awarded the contract for the uplands removal to North Wind, Inc. |
Anne Marie Palmieri |
6/16/2011 |
Cleanup Plan Approved |
Staff approved this date the USFS' Non-Time Critical Removal Action sampling and analysis plan. |
Anne Marie Palmieri |
9/27/2011 |
Spill Transferred from Prevention Preparedness and Response Program |
Spill transferred by PERP staff Sarah Moore. Spill no. 1111992580; spill date = 9/15/11; substance = unknown; quantity = unknown; descripition: excavation caused sheen in marine waters. |
Mitzi Read |
7/11/2012 |
Document, Report, or Work plan Review - other |
Comments provided to EPA on SAP for 2012 RI. |
Anne Marie Palmieri |
7/26/2012 |
Public Notice |
EPA public meeting in Thorne Bay on 7/26. Meeting will be held in Kasaan on 7/30. |
Anne Marie Palmieri |
7/27/2012 |
Site Visit |
Site visit with EPA and USFS. EPA's contractor conducting a sampling event during this time. Results are anticipated in December 2012. Additional fieldwork will be conducted in 2013 to provide all needed information for the Remedial Investigation and risk assessment. |
Anne Marie Palmieri |
10/11/2012 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 73968 Mine. |
Anne Marie Palmieri |
12/13/2012 |
Meeting or Teleconference Held |
Meeting with DNR and DF&G staff to talk about CERCLA, site history, data gaps, and where the project is going. This meeting was held in preparation for the February RI scoping meeting. |
Anne Marie Palmieri |
2/12/2013 |
Meeting or Teleconference Held |
Palmieri and Wu participated in an EPA 2 day RI scoping meeting in Anchorage with staff from: DNR, ADF&G, USFS, DHSS, and US Fish and Wildlife. Topics included the site data gaps for the RI and risk assessment, treatability study, and possible removal action. |
Anne Marie Palmieri |
4/23/2013 |
Update or Other Action |
Palmieri gave a presentation at the Organized Village of Kasaan's 2013 Craig Mining Symposium about how people can get involved in the CERCLA process with an update on Salt Chuck. Palmieri also handed out subsistence use surveys. |
Anne Marie Palmieri |
5/7/2013 |
Site Visit |
Site visit with USFS, EPA, DF&G, and CH2M Hill (EPA contractor) |
Anne Marie Palmieri |
5/7/2013 |
Meeting or Teleconference Held |
EPA public meeting held in Thorne Bay |
Anne Marie Palmieri |
5/8/2013 |
Meeting or Teleconference Held |
EPA public meeting held in Kasaan |
Anne Marie Palmieri |
8/27/2013 |
Update or Other Action |
EPA begins the treatability study field work this date. DEC provided comments on the treatability study work plan. The purpose of the treatability study is to evaluate ways to prevent erosion of tailings in the inter-tidal area. |
Anne Marie Palmieri |
9/15/2014 |
Document, Report, or Work plan Review - other |
CS staff reviewed the draft Remedial Investigation and Risk Assessment reports and provided comments to EPA this date. |
Anne Marie Palmieri |
5/4/2015 |
Meeting or Teleconference Held |
DEC staff met with EPA regarding the human health risk assessment. EPA asked DEC to review some proposed changes to their calculations. DEC reviewed the proposed changes and provided comments back to EPA. |
Anne Marie Palmieri |
11/17/2017 |
Update or Other Action |
DEC provided additional comments to EPA on their responses to DEC comments on the draft RI. |
Anne Marie Palmieri |
3/9/2018 |
Update or Other Action |
EPA finalized the Remedial Investigation on this date. |
Anne Marie Palmieri |
4/23/2021 |
Meeting or Teleconference Held |
Staff met with EPA to discuss potential summer field activities. EPA plans to conduct sampling in-house. |
Anne Marie Palmieri |
7/14/2021 |
Document, Report, or Work plan Review - other |
Staff reviewed the EPA QAPP for their July 2021 field activities including sediment collection. |
Anne Marie Palmieri |
10/10/2022 |
Site Characterization Workplan Approved |
Issued approval letter for Quality Assurance Project Plan for assessing the aqueous partitioning of copper in sediments |
Nick Waldo |
10/26/2023 |
Site Visit |
DEC visited the site with EPA staff and contractors to prepare for the Feasibility Study. Activities included a site walk and observations, EPA Office of Research and Development staff installing biochar test plots, contractors collecting test volumes of tailings for a treatability study to inform development of a confined disposal facility, porewater sampling, and a meeting with representatives of the Organized Village of Kasaan. |
Nick Waldo |
3/8/2024 |
Document, Report, or Work plan Review - other |
DEC reviewed a treatability study workplan. The plan is to send site material which was collected during last October's field visit to a lab where aliquots will be mixed in varying ratios with cement. Samples will be tested before and after treatment for a variety of parameters including total metals, leachable metals by TCLP, pH, and pH-dependent leachability. No regulatory issues were identified, and DEC concurred the experimental design would provide useful information for development of the site remedy. |
Nick Waldo |
3/19/2024 |
Update or Other Action |
Added DNR-SAIL as "Other Affiliate" at request of DNR (tideland owner) |
Jennifer McGrath |