Site Report: Eaglecrest Maintenance Shop

Site Name: Eaglecrest Maintenance Shop
Address: South End Fish Creek Road, Middle of Douglas Island, Juneau, AK 99801
File Number: 1538.38.005
Hazard ID: 3121
Status: Active
Staff: Stacee Henderson, 9072628202 stacee.henderson@alaska.gov
Latitude: 58.276100
Longitude: -134.514800
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Batteries were found while clearing an area behind Eaglecrest maintenance shop; 1,400 pounds of batteries and 15 cubic yards of soil and metal were removed. Historical (1999) sample data on confirmation samples at the limits of the soil removal action confirmed that levels of total metals arsenic, selenium, chromium and lead in remaining soil are above DEC Method Two Migration to Groundwater Cleanup Levels. Groundwater characterization is needed to determine if metals contamination is migrating off-site to Fish Creek.

Action Information

Action Date Action Description DEC Staff
1/10/2000 Site Ranked Using the AHRM Initial ranking. Meilani Clark
1/13/2000 Site Added to Database Metals contamination. Meilani Clark
1/13/2000 Site Ranked Using the AHRM Reranked. Changed SW Exposure Index Value from 0.4 to 0 because SW not used as a DW source. Former Staff
3/27/2001 Update or Other Action Updated Landowner from USDA Forest Service to CBJ and Responsible Party from Channel Construction to CBJ. Changed ranking parameter surface water environments from 0 to 2 to include Fish Creek, which is located 80 feet from the battery dump. Located in Tongass NF, score for sensitive area raised from 0 to 2. On-site groundwater well not tested. Bruce Wanstall
7/29/2005 GIS Position Updated Lat Long data recorded. Metadata include NAD 83 Topozone Pro web utility projection on USGS 1:24000 scale topographic map. Accuracy is high; within 15 meters. File saved at jn-svrfile G:\SPAR\Spar-Contaminated Sites\26 Case Files (LUST Sites)\1538 Douglas\1538.26.002 CBJ - Eaglecrest Ski Area. Bruce Wanstall
2/1/2006 Update or Other Action Letter sent to the RP requesting data related to Eaglecrest Ski Area, Maintenance Shop groundwater contamination, per DEC letter 10-26-98 about Sept 1998 Soil and Groundwater Sampling Results, sampled by Smith Bayliss & LeResche. Bruce Wanstall
3/30/2006 Update or Other Action Email sent to the RP to follow up on letter requesting SBL 1998 Monitoring Well & Test Pit Sampling Data. Bruce Wanstall
6/12/2006 Update or Other Action Received and reviewed letter dated 10-22-98 titled Test Wells, Soils/Water Sampling at Eaglecrest Maintenance Shop by Smith Bayliss LeResche Inc. Laboratory data, well and test pit locations are not included with the letter. Bruce Wanstall
7/17/2006 Update or Other Action Letter sent to CBJ Engineering requesting groundwater assessment of the Lodge and Maintenance Shop areas. Review the Battery Dump Cleanup Report (SBL 1999) and requested update from facility manager on the contaminated soil stockpile left behind the Shop after the cleanup. Bruce Wanstall
7/2/2007 Exposure Tracking Model Ranking ETM ranking the battery dump site at the maintenance shop; controlling pathways include the water exposure routes that represent unlikely risk but that assumption is not supported by data from the site. Request ledger code for the site. Bruce Wanstall
4/2/2013 Update or Other Action By electronic mail DEC requested that CBJ add metals to a DEC approved groundwater sampling plan for the Eaglecrest Maintenance Shop to address the non-petroleum source area managed under this contaminated site record. Historical (1999) sample data on confirmation samples at the limits of the soil removal action confirmed that levels of total metals arsenic, selenium, chromium and lead in remaining soil are above DEC Method Two Migration to Groundwater Soil Cleanup Levels. Bruce Wanstall
12/10/2014 Document, Report, or Work plan Review - other DEC has reviewed: Eaglecrest Maintenance Shop Site Groundwater Monitoring (Report) letter/report dated November 20, 2014. Carson Dorn Inc. (CDI) completed the report documenting the results of sample collection at the referenced site and laboratory analysis for the total metal chemicals of concern (COCs). DEC concurs with the conclusions and recommendations and approves the Report with a comment on the use of dissolved metals vs. total (recoverable) metals as groundwater cleanup levels and how the data may be used to achieve site closure. Another round of sampling in July 2015 is requested. Bruce Wanstall
7/21/2016 Update or Other Action ADEC contacted the environmental consultant to determine status of the sampling; the CBJ project manager is not available. Sent a copy of the report approval letter that agreed with the consultant recommendation for another round of samples be collected from the monitoring wells before closing out the site. Bruce Wanstall
3/13/2019 Site Characterization Report Approved ADEC Contaminated Sites Program staff reviewed and approved “Eaglecrest Ski Area Maintenance Shop Site – Groundwater Monitoring” (Report) dated February 11, 2019 from Cox Environmental Services (CES) for the Eaglecrest Maintenance Shop site in Juneau, Alaska. This Report was submitted to ADEC’s Contaminated Sites Program via email on February 12, 2019. Field work generally consisted of sampling two groundwater monitoring wells and collecting samples for laboratory analysis. Annual groundwater monitoring will occur until stable or decreasing trend is established. On October 25, 2018, two groundwater monitoring wells (MW-1 and MW-2 were sampled for total and dissolved metals concentrations Three metals were confirmed above ADEC’s Table C groundwater cleanup levels (CL) in MW-1: arsenic (0.31 mg/L, CL = 0.00052 mg/L), cadmium 0.03 mg/L, CL = 0.0092 mg/L), and lead (0.79 mg/L, CL = 0.015 mg/L). Barium, selenium, and silver were detected, but at concentrations below Table C groundwater cleanup levels. Mercury was confirmed at non-detect concentrations. Total chromium concentration in MW-1 was 2.3 mg/L. Arsenic was the only metal confirmed above Table C groundwater cleanup levels at 0.0061 mg/L (CL = 0.00052 mg/L) in MW-2. Barium and lead were detected in MW-2, but at concentrations below Table C groundwater cleanup levels. Cadmium, selenium, silver, and mercury were confirmed at non-detect concentrations in MW-2. Total chromium concentration in MW-2 was 0.043 mg/L. Amy Rodman
9/25/2019 Site Characterization Report Approved ADEC has reviewed and approved the “Eaglecrest Maintenance Shop– Groundwater Sampling” (Report) for the Eaglecrest Maintenance Shop site in Sitka, AK dated September 12, 2019. The report was submitted to ADEC via email on September 20, 2019 by Cox Environmental Services. Field activities were conducted on August 21, 2019 and generally consisted of sampling groundwater monitoring wells MW-1 and MW-2 for laboratory analysis of total and dissolved metals. Arsenic was detected above Table C groundwater cleanup level of 0.00052 mg/L in MW-1 and MW-2 at 0.017 mg/L and 0.006 mg/L, respectively. Lead was detected in MW-1 at 0.044 mg/L, above the Table C groundwater cleanup level of 0.015 mg/L. ADEC concurs with the recommendation for another round of groundwater sampling to continue to establish a trend in groundwater concentrations towards closure with institutional controls. Amy Rodman
7/21/2020 Document, Report, or Work plan Review - other On June 16, 2020 ADEC received the Draft Groundwater Monitoring Report CBJ-Eaglecrest Maintenance Shop” via email. ADEC has reviewed the draft groundwater monitoring report and provided comments. The report summarizes groundwater sampling activities and analysis for total and dissolved metals, total and dissolved mercury, and total chromium (VI). Rachael Petraeus
8/25/2020 Document, Report, or Work plan Review - other On August 25, 2020 ADEC received "Eaglecrest Maintenance Shop Draft 2020 GW Monitoring Report" via electronic submittal. The draft report summarizes groundwater monitoring activities over the 2020 field season. Rachael Petraeus
10/15/2020 Site Characterization Report Approved On October 15, 2020 ADEC approved site characterization report with additional overall comments. Rachael Petraeus

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.