Action Date |
Action |
Description |
DEC Staff |
12/6/1999 |
Update or Other Action |
On this date ADEC Sent a No Further Action Letter to ADOT&PF for three of the four USTS on site. The three USTS include: a regulated 300 gal diesel UST; a regulated 500 gal. gas UST; and a 1,000 gallon HOT. The site will remain active due to soil contamination surrounding a 2,000 gal. HOT. |
Grant Lidren |
4/23/2003 |
Site Added to Database |
Site is part of the former Nike Missile site. |
Elizabeth Stergiou |
4/23/2003 |
Site Ranked Using the AHRM |
Site Access value of 1 due to presence of a soil stockpile on site. Population Proximity value of 1 due to assumed use of the on site buildings. Groundwater Usage value of 0.4 assumed. |
Elizabeth Stergiou |
4/23/2003 |
GIS Position Updated |
Site location derived from TopoZone interactive web site. |
Elizabeth Stergiou |
3/9/2004 |
Update or Other Action |
File number assigned: 2265.38.010. |
Sarah Cunningham |
5/10/2005 |
Update or Other Action |
DNR received funding to remove the hazmat and structures from this facility. They are still developing an RFP to conduct the work hopefully during the 2005 field season. Following the removal of structures and utilidors - ADEC will evaluate the need to conduct additional site assessment under the State MOA. |
Jim Frechione |
4/25/2006 |
Site Characterization Workplan Approved |
DEC issued a work plan approval letter for the work outlined in the work plan titled “Soil Excavation and Characterization Work Plan, DMLW Goose Bay Correctional Facility, Alaska, dated February 13, 2006 prepared by Shannon & Wilson Inc. Activities related to four drums found shot-up at the site. |
David Pikul |
10/6/2006 |
Update or Other Action |
DEC issued approval for the transport and treatment of approximately 50 cubic yards of soil containing GRO (446 mg/kg), DRO (315 mg/kg), benzene, (0.731 mg/kg), toluene (41.2 mg/kg), Ethylbenzene (14.9 mg/kg), xylenes (91.9 mg/kg), tetrachloroethene (21.2 mg/kg) & arsenic (5.36 mg/kg). TCLP analysis of tetrachloroethene was below RCRA levels. Post treatment analysis required AK 101&102, EPA 8260. Soil originated from the location of four former leaking drums. The soil was transported to OIT, Inc. in Fairbanks, via B.C. Excavating. |
David Pikul |
7/11/2007 |
Update or Other Action |
Site transferred from Pikul to Oelkers. |
Shannon Oelkers |
7/27/2007 |
Update or Other Action |
Site transferred from Oelkers to Frechione. |
Shannon Oelkers |
10/10/2007 |
Update or Other Action |
Site transferred to Horwath. |
Paul Horwath |
2/29/2008 |
Update or Other Action |
File number changed from 2265.38.010 to 2226.38.003 to reflect the correct location. |
Alyce Hughey |
9/10/2008 |
Exposure Tracking Model On Hold |
Unable to rank this site because the file does not contain a copy of the Shannon & Wilson report covering the assessment and cleanup work performed under the ADEC approved February 13, 2006, Shannon & Wilson Inc., "Soil Excavation and Characterization Work Plan, DMLW Goose Bay Correctional Facility, Alaska". Paul Horwath sent an e-mail to Shannon & Wilson requesting that they provide ADEC with a copy of their report(s) covering work performed at this site. |
Paul Horwath |
5/29/2009 |
Update or Other Action |
File transferred from Soldotna to Anchorage 6-1-09. Project Manager changed from Paul Horwath to Linda Nuechterlein. |
Alyce Hughey |
8/3/2009 |
Document, Report, or Work plan Review - other |
On this date, ADEC received Soil Excavation and Characterization DMLW Goose Bay Correctional Facility, dated October 2006 and submitted by Shannon & Wilson. Soil was excavated from two areas: the drum stained soil area and at the former Tank 4 area. At former tank 4, the sloughed soil from the previous foundation removal, the 75 cubic yard stockpile, as well as 200 cy. additional soil (excavated 40 ft. long by 10 ft. wide by 22 ft. deep on the east end to 14 ft. bgs on the west end), was land spread, graded, and hydro seeded. The excavation itself was backfilled with crushed concrete from the previous foundation and stockpiled soil. Before the land spreading/ backfilling activities commenced, eight soil samples collected 1.5 ft. into the pile contained DRO up to 3,030 mg/kg and six confirmation samples collected from the depths of the excavation and sidewalls were non-detect. GW was not encountered. At the drum stained area, which measures 15 ft. by 20 ft., the three drums and 50 cubic yards of contaminated soil excavated to 12 ft. bgs., was moved to a liner and was later thermally remediated. Two soil samples collected 1.5 ft. into the pile contained GRO up to 446 mg/kg, DRO up to 315 mg/kg, benzene up to 0.101 mg/kg, toluene up to 41.2 mg/kg, ethylbenzene up to 14.9 mg/kg, total xylenes up to 91.8 mg/kg PCE up to 21.2 mg/kg. Soil samples collected from the base of the excavation and sidewall at 11 and 12 ft. bgs, contained benzene up to 0.13 mg/kg & PCE up to 0.308 mg/kg . |
Grant Lidren |
8/4/2009 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 78790 name: 2,000 Gal Diesel UST |
Grant Lidren |
11/4/2009 |
Site Visit |
On this date a site visit of the former Battery Control Area was conducted to collect a few photographs of the site without buildings. The site hasn’t been heavily used as a dumping ground since the cleanup work took place in 2006. There were a few small pieces of debris and evidence of a bonfire, but otherwise the site "looks" clean. |
Grant Lidren |
11/18/2009 |
Cleanup Complete Determination Issued |
The Alaska Department of Environmental Conservation (ADEC), Contaminated Sites Program, has completed review of the environmental records associated with the ADNR Goose Bay Nike Admin & Prison Site. Based on the information provided to date, the ADEC has determined that the contaminant concentrations remaining on site do not pose an unacceptable risk to human health or the environment, and this site is closed. This decision is based on the administrative record for the ADNR Goose Bay Nike Admin & Prison Site, which is located in the offices of the ADEC in Anchorage, Alaska.
|
Grant Lidren |
6/7/2012 |
Update or Other Action |
During site visit by USACE in 2012 for Goose Bay Nike Site Launch Facility file #2226.38.004, the former prison's abandoned DWW was discovered. USACE plans on pouring bentonite and temporarily capping the DWW to prevent use/misuse of DWW on 6/18/2012. |
Grant Lidren |
1/3/2013 |
Update or Other Action |
USACE poured bentonite and temporarily capped the DWW to prevent use/misuse of the DWW. |
Grant Lidren |