Action Date |
Action |
Description |
DEC Staff |
12/26/2002 |
Site Added to Database |
Non-Qualifying Status. |
Debra Caillouet |
10/16/2006 |
Update or Other Action |
File number issued 2237.38.002. |
Aggie Blandford |
6/21/2010 |
Site Visit |
ADEC staff acoompanied by USACE staff and their contractors drove to Lake Louise for a site inspection and meetings with the local ADOT project manager to solidify plans for this summer's field work. We visited the lake shore recreation site where some solid waste is to be removed from the shore line as well as in the sediment on the bottom of the lake. Little solid waste was visible from the shore and additional surveys will need to be conducted from a boat to determine the extent of solid waste tht is remaining. We also visited the airstrip that services the Lake Louise area. It has been undergoing some expansion and drums were discovered scattered along the southern side of the runway. We walked around in the area for some time inspecting the visible drums and estimating the number of drums that remain. There are approximately 150-200 drums scattered in the woods adjacent to the cleared area south of the airstrip. Techniques to remove the drums were discussed. A work plan is forthcoming. |
Jonathan Schick |
7/26/2010 |
Update or Other Action |
ADEC staff recieved a copy of the Draft Drum/Debris Removal Work Plan for theLake Louise Army Recreation Camp and the Army Airfield. The plan details the removal and disposal of solid waste along the lake shopre and beneath the surface of the water. There are approximately 150-200 drums that have been disposed of along the southern side of the airstrip that services the Lake Louise area. The plan details the removal of these drums and the sampling strategy to be performed after the drums have been removed. Additionally the plan details the sampling strategy if any of the drums still contain product. During the two site visits that the ADEC staf has participated in, none of the drums were found to contain any product. |
Jonathan Schick |
8/2/2010 |
Update or Other Action |
Contaminated Sites Staff issued a letter to the US Army Corps of Engineers regarding the Draft Work Plan for Drum and Debris Removal at the US Army Airfield and Recreation Camp at Lake Louise. The main concerns about the draft plan was to make sure that the characterization of the soils beneath the drum was performed consistently and thoroughly. Additonally the state expressed concern about disturbing potentially impacted sediments from the lake bottom during the debris removal action. |
Jonathan Schick |
9/13/2010 |
Update or Other Action |
ADEC Contaminated Sites Staff recieved a Final copy of the Drum and Debris Removal Work Plan for the US Army Airfield and the Army Recreational Camp on the shore of Lake Louise. The Final version was dated September 2010. According to the schedule presented in the document, teh field work is set to start today. The plan details the removal of approximately 200 abandoned drums in the brush adjacent to the airfield and characterizing the soil beneath the removed drums. Additioally the work plan addresses the removal of inert debris from the lake bottom at the Army Recreation Camp area. Some of the underwater debris has been identified as a navigational hazard for recreational users of the lake. |
Jonathan Schick |
11/4/2010 |
Site Characterization Workplan Approved |
ADEC Contaminated Sites Staff issued a letter to the US Army Corps of Engineers approving the Final Version of the Drum and Debris Removal Work Plan for the US Army Airfield and Recreation Camp at Lake Louise. |
Jonathan Schick |
3/22/2011 |
Update or Other Action |
COntaminated Sites Staff recieved the Draft Version of the Lake Louise Drum/Debris Removal Report for the US Army AIrfield and Recreational Camp. |
Jonathan Schick |
4/15/2011 |
Update or Other Action |
Contaminated Sites Staff submittted a comment letter to the US Army Corps of Engineers Project Manager detailing the State's concerns with the report. The State requested that the report be augmented with additional information regarding the soil and waste stream sampling that toook place at the airfield. More detail was requested on the types and condition of the solid waste that was removed from the lake bottom. |
Jonathan Schick |
5/13/2011 |
Update or Other Action |
Contaminated Sites Staff recieved responses to our comments on the Draft Lake Louise Drum/Debris Removal Report from the US Army Corps of Engineers. The responses were acceptable and the report will be approved to be finalized. |
Jonathan Schick |
7/6/2011 |
Update or Other Action |
Contaminated Sites Staff recieved the Final Version of the Drum/Debris Removal Report for Lake Louise Army Airfield and Recreational Camp dated June 2011. The comments were addressed in the final report and it will be approved. |
Jonathan Schick |
7/29/2011 |
Update or Other Action |
Contaminated Sites Staff recieved the Draft Work Plan for Drum and Debris Removal for contaminated soil removal dated July 2011. The plan details the program to return to the Army Airfield at Lake Louise and remove remaining impacted soil where drums were removed in 2010.
|
Jonathan Schick |
8/1/2011 |
Site Characterization Report Approved |
Contaminated Sites Staff submitted a letter to the US Army Corps of Engineers approving the Final version of the Drum and Debris Removal Report for the Lake side Recreational Camp and the Airfiled drum removal. Additional remoavl action associated with the airfield site is slated to be conducted in the 2011 field season. |
Jonathan Schick |
8/18/2011 |
Update or Other Action |
Contaminated SItes Staff submitted comments on the Draft Drum and Drbris Removal Work Plan. The State's main concerns were regarding differentiating the total chromium from the hexavalent chromium and the designation of the action level that will be used for the PID to guide the excavation activities. |
Jonathan Schick |
8/26/2011 |
Update or Other Action |
Contaminated Sites Staff recieved response to our comment submitted on the 18th of August. The responses addressed our main concerns and the plan should be approved to be finalized with the agreed upon changes. |
Jonathan Schick |
8/31/2011 |
Update or Other Action |
Contaminated Sites Staff submitted a letter to the USACE Project Manager approving the finalization of the work plan for drum and debris removal at the area adjacent to the airstrip at Lake Louise. With the agreed upon changes in the comment response form, the plan can be implemented in the field.
|
Jonathan Schick |
9/12/2011 |
Site Characterization Workplan Approved |
Contaminated Sites Staff recieved the Final version of the Drum and Debris Removal Work Plan Amendment 1: DRO-Contaminated Soil Removal dated September 2011. THe plan is an amendment to the 2010 plan where the scattered drums and debris were removed from the site and several areas beneath the drums were noted to be impacted. This year's work is to return to the sites where impacted soil was identified and remove the soil, and collect confirmation samples. There is also an attempt to collect data to support a background metals survey for the area to eliminate several metals as contaminants of concern. |
Jonathan Schick |
12/21/2011 |
Site Characterization Report Approved |
Contaminated Sites Staff recieved the Revised Final Version of the Lake Louise Drum/Debris Removal Report for the US Army Airfield and Recreation Camp. The report summarizes the drum and debris removal action from the summer of 2010. The revised report addressed the comments submitted prveiously on this document. The residual impacted soil has been removed from the areas identified in this report and that removal will be detailed in a separate report. |
Jonathan Schick |
1/30/2012 |
Document, Report, or Work plan Review - other |
Contaminated Sites Staff recieved a Draft Technical Memorandum for the 2011 DRO-Contamintes Soil Removal at the US Army Airfield at Lake Louise. The memo described the work performed at the site in 2011 including the removal of approximately 8 cubic yards of DRO impacted soil and shipped the material off-site for treatment and disposal. The memo also discusses the fact that more work remains to be completed at the site to remove mmore impacted soil. |
Jonathan Schick |
3/1/2012 |
Document, Report, or Work plan Review - other |
Contaminated Sites Staff submitted a letter to the Remedial Project Manager for the US Army Corps of Engineers regarding the Draft Technical Memorandum on DRO soil removal from the Laek Louise Army Airfield during the 2011 field season. Our comments were regarding other field screening options to detect the DRO impacted soil in the field and assist in the removal project. |
Jonathan Schick |
3/2/2012 |
Document, Report, or Work plan Review - other |
Contaminated Sites Staff recieved an email from the contractor for the US Army Corps of Engineers regarding our comments on the Draft Technical Memorandum for DRO contaminated soil removal at the US Army Airfield at Lake Louise. The email contained responses to comments agreeing to make the suggested changes into a final document. |
Jonathan Schick |
3/20/2012 |
Document, Report, or Work plan Review - other |
Contamintaed Sites Staff recieved a Final version of the Technical Memorandum for DRO contamianted Soil removal for the US Army Airfield at Lake Louise. The comments from the draft version were included in the final version and it is approved for the record. Additional excavation and confirmation sampling will be required at the site and is anticipated for the 2012 field season. |
Jonathan Schick |
5/23/2012 |
Document, Report, or Work plan Review - other |
Contaminated Sites Staff submitted a comment letter to the USACE project manager regarding the Draft Work Plan Addendum for soil sampling at the Lake Louise Airfield. The plan details the early summer sampling program to try to delineate the horizontal and vertical extent of the remaining DRO contamination at the site. The main concern with the plan was that the use of hand augers may not be able to delineate the vertical extent of impacted soil as the soil may be frozen and impenatrable to hand tools where the impacts may have advanced further into the frozen soils during times when the soil is warmer. |
Jonathan Schick |
6/11/2012 |
Document, Report, or Work plan Review - other |
Contaminated sites staff submitted a letter to the USACE project manager approving the finalization of the 2012 Work Plan Addendum for soil sampling at the airfield. THe plan addressed the State's concerns regarding the difficulty in confirming the vertical extent of the impacted soils with the tools to be used in the field. |
Jonathan Schick |
6/19/2012 |
Document, Report, or Work plan Review - other |
Contaminated Sites Staff recieved the Final version of the 2012 DRO-Contaminated Soil Sampling Work plan for the US Army Airfield Formerly Used Defense Site. The plan is dated June 2012 and will implemented at the end of this month or early in July.
|
Jonathan Schick |
9/28/2012 |
Site Characterization Report Approved |
2012 Lake Louise Remedial Investigation Summary, U.S. Army Airfield Formerly Used Defense Site, F10AK0997-01, Final, September 2012. The report provides additional characterization of diesel range organics (DRO) remaining in soil at five locations at the Lake Louise site. DRO remains at levels up to 39,000 mg/kg.
An alternative cleanup level for the migration to groundwater pathway is presented using 18 AAC 75.340, Method 3. The only parameter for the Method 3 calculation that was changed from the default levels is the total organic carbon (TOC) content. A value of 1.28 percent was calculated for the TOC and input to the on-line Method 3 Calculator provided by DEC. An alternative cleanup level of 3000 mg/kg DRO for the migration to groundwater is approved based on this data.
|
Debra Caillouet |
9/28/2012 |
Cleanup Level(s) Approved |
2012 Lake Louise Remedial Investigation Summary, U.S. Army Airfield Formerly Used Defense Site, F10AK0997-01, Final, September 2012
The report provides additional characterization of diesel range organics (DRO) remaining in soil at five locations at the Lake Louise site. DRO remains at levels up to 39,000 mg/kg.
An alternative cleanup level for the migration to groundwater pathway is presented using 18 AAC 75.340, Method 3. The only parameter for the Method 3 calculation that was changed from the default levels is the total organic carbon (TOC) content. A value of 1.28 percent was calculated for the TOC and input to the on-line Method 3 Calculator provided by DEC. An alternative cleanup level of 3000 mg/kg DRO for the migration to groundwater is approved based on this data.
|
Debra Caillouet |
10/5/2012 |
Document, Report, or Work plan Review - other |
Work Plan Addendum 2, 2012 DRO-Contaminated Soil Removal, U.S. Army Airfield, Lake Louise, Alaska (Draft) Formerly Used Defense Site F10AK0997-01, October 2012 |
Debra Caillouet |
12/12/2012 |
Cleanup Complete Determination Issued |
2012 DRO Contaminated Soil Removal, U.S. Army Airfield, Lake Louise, Alaska, Draft, 11 December 2012 and Cleanup Complete Determination
The report documents the removal of diesel range organics(DRO) impacted soil at four locations within the Formerly Used Defense Site at Lake Louise.
An alternative cleanup level of 3000 mg/kg DRO for the migration to groundwater was approved based the total organic carbon present in the soil. Confirmation sampling at the limits of each excavation showed all results to be below 3000 mg/kg DRO with results from 11 mg/kg to 1750 mg/kg.
|
Debra Caillouet |
12/12/2012 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed for source area id: 74161 name: auto-generated pm edit Lake Louise Army Training Camp |
Debra Caillouet |
12/12/2012 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 74161 auto-generated pm edit Lake Louise Army Training Camp. |
Debra Caillouet |
2/6/2013 |
Final Cleanup Report Reviewed |
Final report submitted 2012 DRO Contaminated Soil Removal |
Debra Caillouet |