Site Report: Halliburton Services MP15.5 Spur HW
Site Name: | Halliburton Services MP15.5 Spur HW |
---|---|
Address: | 42320 Kenai Spur Highway, Mi. 15.5 N. Kenai Spur HW, Kenai, AK 99611 |
File Number: | 2320.38.020 |
Hazard ID: | 3334 |
Status: | Cleanup Complete |
Staff: | No Longer Assigned, 9074655229 dec.icunit@alaska.gov |
Latitude: | 60.593889 |
Longitude: | -151.331111 |
Horizontal Datum: | NAD83 |
![]() | ![]() |
![]() | ![]() |
We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.
Problems/Comments
Environmental Screening report indicates that concentrations of GRO, DRO and RRO in soil exceed applicable ADEC cleanup criteria. SE corner of Spur Highway and Samuel Avenue.
Action Information
Action Date | Action | Description | DEC Staff |
---|---|---|---|
5/16/2000 | Site Ranked Using the AHRM | Initial ranking. | Donald Seagren |
5/16/2000 | Update or Other Action | Cost Recovery Letter Issued this date. | Donald Seagren |
6/1/2000 | Meeting or Teleconference Held | Site inspection with Mark Spencer and Bill Lustikoff. Walked site, discussed potential problems areas; discussed plans for further site investigation and short comings of prior report. Dames and Moore will prepare work plan for further site investigation. Halliburton is taking step to remove old catch basin in area of former outside equipment storage. | Donald Seagren |
6/2/2000 | Site Added to Database | GRO, DRO and RRO. | Former Staff |
6/8/2000 | Update or Other Action | Interim actions taken to remove old basin and liner. Water sampled and barreled. Surface soil samples taken. Old liner removed and incinerated. Shallow basin backfilled. | Donald Seagren |
6/9/2000 | Update or Other Action | Site inspection - liner removal, surface soil sampling and temporary backfilling. Soil at end and middle of pit appeared contaminated with petroleum. Contamination may have been from releases that seeped under liner rather than leaking through holes/tears in the liner. Liner will be incinerated by Raven Construction at their Sterling facility. | Donald Seagren |
5/29/2001 | Site Characterization Workplan Approved | Discussed comments with Liz Shen of GeoEngineers. | Donald Seagren |
10/2/2001 | Interim Removal Action Approved | Review and approve request to ship 4 drums of soil cuttings from MW installation to ASR in Anchorage for thermal remediation. | Donald Seagren |
12/26/2001 | Site Characterization Report Approved | Reviewed Subsurface Site Investigation Report, dated 5 December 01. Awaiting site closure workplan in order to proceed with final cleanup and closure of this site. LTM may be appropriate depending on what is done under floor drain area inside building. | Donald Seagren |
7/2/2002 | Cleanup Plan Approved | Reviewed and approved Work Plan - Site Closure Support, dated 27 June 02. | Donald Seagren |
7/25/2002 | Update or Other Action | Met with Jamie Oakley, GeoEngineers, during excavation of floor drain area. Discussed how best to approach determining and removing DRO contaminated soil. | Donald Seagren |
7/30/2002 | Update or Other Action | Site inspection. Additional excavation being done. Additionally floor drain system, oil/water separator and hydro tank sump will be assessed and either removed totally or closed in place with cement. Outside contamination excavated and stockpiled. Soil will be transported to ASR for treatment and disposal. | Donald Seagren |
8/2/2002 | Update or Other Action | Approved transport of 125 cubic yards of PCS to ASR for treatment and disposal. | Donald Seagren |
12/17/2002 | Update or Other Action | Reviewed Report of Environmental Services Remedial Excavations and Groundwater Monitoring Activities, dated 11 December 02. | Donald Seagren |
12/17/2002 | Site Closure Approved | All soil and GW levels are below ADEC Method 2, <40" Zone, migration to GW cleanup levels. Closure and abandonment of MWs approved. | Donald Seagren |
3/10/2003 | Update or Other Action | Reviewed MW abandonment report. All MWs abandoned following ADEC approved procedures. | Donald Seagren |
3/2/2004 | Update or Other Action | File number assigned and entered into the Fileroom DB and CS DB. | Alyce Hughey |
8/24/2005 | GIS Position Updated | Using Figure 1 and 2 from a Subsurface Site Investigation Former Halliburton Energy Services, Mile Point 15.5, from GeoEngineers, dated December 5, 2001, in conjunction with TopoZone Pro and the KPB Parcel Lookup, entered the coordinates for this site. Metadata includes No Topo Basemap, TopoZone Pro Street Map, Black and White Aerial Photo, on a Medium Size Map, View Scale 1:10,000, Coordinate Datum NAD83. High degree of confidence in accuracy of location. | Alyce Hughey |
Contaminant Information
Name | Level Description | Media | Comments |
---|---|---|---|
For more information about this site, contact DEC at (907) 465-5390. |
Control Type
Type | Details |
---|---|
No ICs Required |
Requirements
Description | Details |
---|---|
Advance approval required to transport soil or groundwater off-site. |
There are no documents for this site report.
No associated sites were found.