Action Date |
Action |
Description |
DEC Staff |
10/17/2000 |
Update or Other Action |
Site Reconnaissance, Abandonded Bulk Fuel Storage Facilities, Villiage of Anvik Alaska Report submitted by Shannon & Wilson and recieved by the ADEC on this date. |
Grant Lidren |
4/21/2003 |
Site Added to Database |
DRO contamination. |
Deborah Williams |
4/21/2003 |
Site Ranked Using the AHRM |
Preliminary ranking. |
Deborah Williams |
7/15/2004 |
Update or Other Action |
File number changed from 2405.42.002 to 2405.38.001 |
Sarah Cunningham |
11/29/2006 |
Update or Other Action |
Staff transferred from Pikul to Jaynes. |
Aggie Blandford |
4/8/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Bill O'Connell |
6/6/2008 |
GIS Position Updated |
Coordinates updated with Google Earth Pro |
Grant Lidren |
3/5/2009 |
Meeting or Teleconference Held |
Teleconference today with Anvik, EPA Brownfields, and DEC Brownfields to discuss potential methods of addressing contamination at former tank farms in Anvik. Additional conversations were held with IGAP following the meeting. |
Bill O'Connell |
1/12/2015 |
Potentially Responsible Party/State Interest Letter |
Sent to Deloy Ges as landowner. |
Keather McLoone |
3/8/2016 |
Update or Other Action |
Letter sent to PRP requesting status update and site characterization work plan for site due by May 9, 2016. |
Lisa Griswold |
8/8/2016 |
Document, Report, or Work plan Review - other |
2013 Phase I ESA reviewed on this date. Report details status and location of four ASTs on property as well as cement foundation, dispenser shed, and possible mixed contaminants. Tribal entity contacted ADEC and informed that the consultant is currently writing a work plan and QAPP for a co-mingled phase 2 ESA. |
Lisa Griswold |
8/29/2016 |
Document, Report, or Work plan Review - other |
Environmental Management Plan (Phase II ESA work plan) reviewed on this date. Work plan includes advancing test pits and hand auger in areas of stained soil to evaluate for petroleum contamination while also testing the paint outside the tanks for lead. Work plan references and revises an E3 Environmental LLC QAPP for Anvik. The work plan was conditionally approved upon if groundwater is encountered, a sample will be taken at the soil water interface. |
Lisa Griswold |
5/11/2017 |
Update or Other Action |
Letter sent to RP to request an updated on the work plan that was approved in August 2016 and to inform that project management was being transferred to Rodman. |
Lisa Griswold |
5/11/2017 |
Update or Other Action |
Site transferred to Rodman |
Lisa Griswold |
4/23/2018 |
Workplan Requested |
Letter with site summary for four Anvik tank farm sites mailed to RP requesting work plan. Work plan due on June 15, 2018. |
Amy Rodman |
8/23/2018 |
Meeting or Teleconference Held |
Teleconference between ADEC CSP staff, Deloy Ges Inc. staff, and local brownfields tribal response program coordinator. Discussed seven contaminated sites in ADEC's contaminated sites database, where Deloy Ges Inc. was listed as one of the responsible parties. Discussed liability, site history, and other potential responsible parties. ADEC will provide site file, liability proof, and site intake reason to Deloy Ges Inc. staff. |
Amy Rodman |
10/8/2018 |
Update or Other Action |
Letter emailed to Deloy Ges, Inc. and GASH (Grayling, Anvik, Shageluk, Holy Cross) Consortium brownfields TRP. Letter contained legal address, site & assessment history, ADEC communication details, and relevant BLM land conveyance dates. Follow-up teleconference planned for October 2018. |
Amy Rodman |
8/30/2019 |
Update or Other Action |
Site location was verified on this date. Coordinates for this site are used to determine the presence and position of the site on the BLM’s ANCSA Conveyed Land web map.
|
Rebekah Reams |
10/2/2019 |
Update or Other Action |
Letter mailed to Deloy Ges, Inc. and Episcopal Diocese of Alaska with summaries on Anvik Chase Enterprise tank farm site and Anvik Commercial Co tank farm sites. Land was originally owned by Episcopal Diocese of Alaska and conveyed to Deloy Ges, Inc in 2005. Requested historical information on tank farm operators on both sites. (A. Rodman) |
Julie Fix |
10/2/2019 |
Update or Other Action |
Letter sent to current and past landowners, requesting information on past entities/individual operators of tank farm on this site and the Anvik Chase Enterprise Store TF site. |
Amy Rodman |
12/30/2020 |
Update or Other Action |
J. Fix assigned as new project manager. |
Julie Fix |
8/30/2023 |
Update or Other Action |
Sent a Project Manager Update letter to RP providing current project manager contacts and requesting updated RP contact information. |
Julie Fix |