| Action Date |
Action |
Description |
DEC Staff |
| 4/15/2000 |
Site Added to Database |
Petroleum. |
Elim Yoon |
| 4/15/2000 |
Institutional Control Record Established |
Institutional controls established for this site in the OU A ROD. Residential land use and domestic use of groundwater prohibited. |
Elim Yoon |
| 4/15/2000 |
Record of Decision |
The Record of Decision for this site was signed this date. |
Elim Yoon |
| 10/10/2003 |
Record of Decision |
Site was removed from OU A ROD by OU A ROD Amendment; will be regulated under 18 AAC 75. |
Sami Goldman |
| 9/1/2004 |
Conditional Closure Approved |
RAC; site is in IC monitoring program |
Jason Weigle |
| 10/19/2004 |
GIS Position Updated |
Latitude and Longitude was derived using ArcGIS with either High Resolution Aerial Photography from the Navy with an up to 3 meters error, or line maps used in investigations combined with road layers, +/-25 feet accuracy. Metadata is as follows: Updated NAD 1983 State Plane Alaska 10 FIPS 5010 Feet; Projection: Lambert Conformal Conic; False Easting: 3280833.333333; False Northing: 0.000000; Central Meridian: -176.000000; Standard Parallel 1: 51.833333; Standard Parallel 2: 53.833333; Latitude of Origin: 51.000000; GCS North American 1983. |
Jason Weigle |
| 11/19/2004 |
Update or Other Action |
Draft Final Cleanup Report, 19 Sites submitted to Department for Review. |
Jason Weigle |
| 12/10/2004 |
Update or Other Action |
Review of Draft Final Cleanup Report, 19 sites completed; comments were submitted to the Navy. The document was incomplete as submitted; Navy will revise and resubmit. |
Jason Weigle |
| 2/9/2005 |
Update or Other Action |
Interim conveyance document contains an equitable servitude that restricts residential land use in addition to the domestic use of groundwater. Site is located in the downtown excavation notification zone. |
Jason Weigle |
| 3/7/2005 |
Update or Other Action |
Added MRTS data, derived from ADNR and USGS range, township, and section data overlaid on lat/lon coordinates derived previously. Accuracy is equivalent to the lat/lon coordinates. MRTS information depicts the center point of range fans and target areas; actual target areas or fans may overlap several sections. |
Jason Weigle |
| 3/8/2005 |
Update or Other Action |
Added legal description for site. |
Jason Weigle |
| 3/20/2006 |
Update or Other Action |
Final 2005 Institutional Control Primary Site Inspection Report received on this date. No IC problems noted at this site. |
Jason Weigle |
| 4/5/2006 |
Update or Other Action |
File number 2501.38.003.01 assigned on this date. |
Jason Weigle |
| 12/18/2006 |
Update or Other Action |
Received Draft 2006 Institutional Control Primary Site Inspection Report that details the results of annual Institutional Control (IC) inspections to determine the effectiveness of IC's selected in the OUA Record of Decision. |
Guy Warren |
| 12/27/2006 |
Update or Other Action |
Submitted comment letter to the Navy on the Draft Institutional Control Primary Site Inspection Report. Comments focused on the adequacy of the excavation notification program, the effectiveness of the ordnance awareness program, and visitor notification of ICs. |
Guy Warren |
| 3/13/2007 |
Update or Other Action |
Received the Final 2006 Institutional Control Primary Site Inspection Report. Several Department comments will be addressed through revisions of the Institutional Control Management Plan planned for 2007. The remaining comments were addressed and additional recomendations to increase efforts to notify island visitors of ICs (including the ordnance awareness education program) were included in the final document. |
Guy Warren |
| 2/16/2011 |
Document, Report, or Work plan Review - other |
The draft 2010 IC Site Inspection Report was received on January 11, 2011 and DEC sent comments on February 16, 2011. There were no observed problems with ICs at this site. |
Meghan Dooley |
| 5/12/2011 |
Document, Report, or Work plan Review - other |
The Final 2010 IC Site Inspection Report was received by ADEC. ICs appear to be functioning as intended at this site. |
Meghan Dooley |
| 6/4/2013 |
Institutional Control Periodic Reporting |
The Final 2012 Institutional Control Site Inspection Report was received. There were no observed changes to land use and no indications of groundwater use or excavation activities. Signs were present. ICs appear to be functioning as intended. |
Meghan Dooley |
| 9/10/2014 |
Institutional Control Periodic Reporting |
The Final 2013 Institutional Control Site Inspection Report was received. There were no observed changes to land use and no indications of groundwater use or excavation activities. Signs were present. ICs appear to be functioning as intended. IC inspection frequency has been reduced to every 4 or 6 years (to coincide with the 5-year review). |
Guy Warren |
| 3/16/2015 |
Update or Other Action |
Received Final 2014 Institutional Controls Site Inspection Report, OUA and OUB of the former Adak Naval Complex. No recommendations for site in report, as all IC’s appear to be functioning as intended. Next IC inspection is scheduled to occur in 2019 in coordination with the 5-year review. |
Guy Warren |
| 3/11/2024 |
ANCSA Program Eligible |
This site meets the criteria for the EPA Contaminated ANCSA Lands program: the site is on ANCSA conveyed land, the contamination occurred pre-ANCSA conveyance, and there is documented proof of contamination that exceeds DEC’s cleanup values in 18 AAC 75. This site will be listed as “verified” on EPA’s contaminated lands inventory. |
Brittani Mack |
| 9/29/2025 |
Document, Report, or Work plan Review - other |
COMPREHENSIVE MONITORING PLAN, Revision 9, Institutional Control Management Plan. DEC provided comments on CMP Revision 9 which describes the mechanisms that have been implemented to ensure compliance with institutional controls (ICs) for sites at the former Adak NAS (includes active sites and sites closed with ICs). The CMP also includes the details for Munitions Educational Awareness Program, which is required by the OU B-1 ROD and will address sites in the in-draft OU B-2 ROD. Note that munitions sites addressed in the OU B-1 ROD with slopes exceeding 30 degrees were issued No Further Action determinations as part of that ROD. This includes C3-01A through C3-01F, FB-01, FB-03,
260 HH-01, ML-01A, ML-01B, and ML-01C. |
Jamie McKellar |
| 10/21/2025 |
Institutional Control Periodic Reporting |
REPORT APPROVAL: DEC approved the 2024 Institutional Controls Inspection Report, which documents site inspections conducted between August 15–30, 2024. While the report is approved, DEC has noted several observations for documentation, including references to RCRA status, environmental release reporting, SWMU 1 and SWMU 20. These observations do not affect the approval of the ICIR but may warrant further evaluation during the upcoming Five-Year Review. DEC continues to coordinate with the Navy to ensure long-term protectiveness of institutional controls at the Adak site. |
Jamie McKellar |