Skip to content Skip to content

Site Report: Prescott Equipment - Rampart Drive

Site Name: Prescott Equipment - Rampart Drive
Address: 2774 Rampart Drive, Anchorage, AK 99501
File Number: 2100.38.088
Hazard ID: 3752
Status: Cleanup Complete - Institutional Controls
Staff: IC Unit, 9074655229 dec.icunit@alaska.gov
Latitude: 61.220278
Longitude: -149.825833
Horizontal Datum:NAD27

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Trichloroethene (TCE) identified in groundwater collected from two of three temporary monitoring wells at the site. TCE concentrations in groundwater were 0.072 mg/L and 0.218 mg/L using EPA Method 8260B. The elevation is ~33 meters (~109 feet). In 2003 and 2004, DEC performed a State lead investigating the area wide contaminant plume. On the findings of the State lead investigation and other information known, DEC issued a NFRAP with an IC in the form of a deed notice for the Prescott Pipeyard-Rampart Drive Lot on July 15, 2004. State assumed lead in 2003

Action Information

Action Date Action Description DEC Staff
10/11/2001 Update or Other Action ADEC received discharge notification from Law Offices of James H. McCollum, LLC. Enclosed with letter were two reports from GeoEngineers, Inc.: a Phase I and a Phase II Site Assessment, both dated September 27, 2001. Scott Pexton
10/25/2001 Site Added to Database Trichloroethane in detected in groundwater. Bruce Wanstall
10/25/2001 Site Ranked Using the AHRM Preliminary ranking. Permitted wells within one mile of site in NE1/4 Section 15. Bruce Wanstall
10/29/2001 Update or Other Action Letter sent to Mary Jane Henrickson with request for site characterization work plan by December 14, 2001. Scott Pexton
12/6/2001 Update or Other Action ADEC received a hand-delivered letter from Heller, Ehrman, attorneys representing Prescott Equipment, Inc. The letter suggested that Prescott Equipment is not the responsible person and that the Municipality of Anchorage and/or the Alaska Army National Guard may be responsible for the TCE contaminated groundwater. The letter requested a suspension of the December 14, 2001 submittal date for a site characterization work plan. Scott Pexton
12/12/2001 Update or Other Action ADEC received a copy of a letter from Susan Bailar, Staff Judge Advocate for the Alaska Army National Guard to Mr. Andrew Behrend, an attorney at Heller-Ehrman et al regarding the site. Also, The CS project manager verbally informed Andrew Behrend, attorney for Prescott Equipment, that the site characterization work plan due date was suspended indefinitely. A follow-up email was sent and copied to representatives of the Alaska Army National Guard and the Municipality of Anchorage. Scott Pexton
3/29/2002 Update or Other Action ADEC received copies of letters (dated March 28, 2002) from attorney Andrew Behrend (representing Prescott Equipment Co.) to Municipal Attorney William Greene and to Staff Judge Advocate Susan Bailar of the Alaska Air National Guard indicating their belief that the TCE groundwater contamination discovered at the 2774 Rampart Drive property originated on an adjacent parcel located at 2839 Mountain View Drive. Scott Pexton
4/15/2002 Update or Other Action ADEC received copy of letter (dated 12 April 2002) from Susan Bailar, Staff Judge Advocate (Joint) representing the Alaska Army National Guard to Andrew Behrend of Heller, Ehrman, White and McAuliffee LLP. The letter indicated that the Army National Guard was not interested in purchasing the real estate located at 2774 Rampart Drive and that the letter from Andrew Behrend did not establish liability on the part of the Alaska Army National Guard for any of the contamination alleged to have been found on the property in question. Scott Pexton
5/3/2002 Update or Other Action ADEC received a letter (dated May 2, 2002) from Andrew Behrend indicating the point of the previous letter was not to definitively establish liability, but that "although site assessment information remained to be fully developed, the facts as currently known strongly suggest that the contamination is coming from upgradient, i.e. from 2839 Mountain View." The letter also suggested that it would be more cost-effective for the AKANG to purchase the property and deal with investigation and remediation costs directly, rather than having Prescott incur remediation costs, and then recover those costs plus economic damages related to reduced property value and inability to sell the property. Scott Pexton
5/9/2002 Update or Other Action Request for Proposal sent by ADEC Contract Manager Dennis Harwood to Max Schwenne of OASIS/Bristol Environmental Services. Scott Pexton
5/15/2002 Update or Other Action ADEC received proposal from OASIS/Bristol Environmental Services to perform the groundwater investigation work. Scott Pexton
5/24/2002 Update or Other Action Funding approval request approved by Director of Division of Spill Prevention and Response. Scott Pexton
5/31/2002 Update or Other Action ADEC received email from Max Schewenne with an attached file with the Groundwater Investigation workplan for review. Scott Pexton
6/6/2002 Update or Other Action Letter sent from ADEC to Mary Jane Henrickson of Prescott Equipment Co., William Vagt of the Alaska Army National Guard, and Gearge Cannelos, of the Municipality of Anchorage, Heritage Land Bank. The letter indicated that ADEC had contracted with an environmental consulting firm to conduct a groundwater investigation in the vicinity of properties located at 2774 Rampart Drive and 2839 Mountain View Drive in Anchorage. The letter stated the "purpose of the groundwater investigation is to determine groundwater flow direction and gradient and to characterize the nature and extent of hazardous substance contamination in groundwater." Scott Pexton
6/12/2002 Update or Other Action ADEC sent an email to Max Schwenne with comments on the May 31, 2002-work plan and requested revision of the plan to address the comments. Scott Pexton
6/28/2002 Update or Other Action ADEC received the" Work Plan for Groundwater Investigation, Vicinity of 2774 Rampart Drive, Anchorage Alaska". The work plan was prepared by ADEC term contractor, OASIS/Bristol Environmental Services with Max Schwenne identified as the Contract Manager. Scott Pexton
7/3/2002 Update or Other Action ADEC sent letter to sent from ADEC to Mary Jane Henrickson of Prescott Equipment Co., William Vagt of the Alaska Army National Guard, and Gearge Cannelos, of the Municipality of Anchorage, Heritage Land Bank. The letter indicated that a copy of the groundwater investigation work plan was enclosed. The letter stated "The purpose of the groundwater investigation is to determine groundwater flow direction and gradient and to characterize the nature and extent of hazardous substance contamination in groundwater. During the groundwater investigation, soil cuttings from the drill holes and purge water from the monitoring wells will be generated and stored in drums until the analytical results are available. In order to facilitate this investigation, ADEC may contact you regarding the possible storage of drums on your property until analytical results are available to determine their disposition." Scott Pexton
7/17/2002 Update or Other Action ADEC received "Returned to Sender" stamped letter sent by ADEC on July 3, 2002 and addressed to Andrew Behrend. Andrew Behrend indicated to Scott Pexton during a telephone conversation that his address had changed. A copy of the letter was faxed to Andrew Behrehd at fax number 277-1920. Scott Pexton
7/19/2002 Update or Other Action Scott Pexton hand delivered a copy of the Groundwater Investigation work plan to the Heritage Land Bank office. Also, DEC faxed a copy of Figure 1 from the Groundwater Investigation workplan to Andrew Behrend. Scott Pexton
7/31/2002 Update or Other Action ADEC received letter from Andrew Behrend indicating the work plan for Groundwater Investigation to be "patently unacceptable". Scott Pexton
8/1/2002 Meeting or Teleconference Held Meeting held in sixth floor conference room at ADEC offices at 555 Cordova Street to discuss the groundwater investigation work plan. Participants included Scott Pexton and Jim Frechione for ADEC; Mary Jane Henrickson, Andrew Behrend, & Ralph Hulbert (representing Prescott Equipment Co.); Michael Krueger and Rhonda Fehlen representing the Municipality of Anchorage; and William Vagt representing the Department of Military and Veteran's Affairs (Alaska Army National Guard). Scott Pexton
8/6/2002 Update or Other Action ADEC received letter (dated August 5, 2002) from Andrew Behrend with an enclosed report from AlaskChem Engineering on magnetometer and standpipe investigations at 2774 Rampart Drive. Scott Pexton
8/12/2002 Update or Other Action ADEC received email from Ralph Hulbert of AlaskChem Engineering with attached PDF file. The email message offered an alternative groundwater investigation proposal. Scott Pexton
8/13/2002 Update or Other Action ADEC received and email from Ralph Hulbert of AlaskChem Engineering with a PDF file attachments. The email indicated a draft work plan and budget were attached for determining the source of the TCE plume at the Prescott and MOA properties. Scott Pexton
11/29/2002 Update or Other Action CSP issued a letter on 11/29/02 that it did not object to the implementation of AlaskChem Engineering’s (AlaskChem) workplan dated 10/7/02. On 10/22, CSP discussed with Hulbert of AlaskChem that because the workplan was premised on the findings of the groundwater investigation on the lot next to Prescott Equipment Rampart Drive, i.e., the MOA 2839 Mount View Drive property, that the CSP would hold off providing comments until the findings of that investigation was available. Hulbert agreed to this approach. Hulbert then provided CSP with a portion of the draft report from the MOA’s groundwater investigation that he had obtained from the MOA. Based on this preliminary data, Hulbert submitted on 11/13 via e-mail a supplemental plan titled “2774 Rampart Drive; Groundwater Investigation Workplan; Further Comments and Request for Allowance to Proceed” dated 11/9/02. The AlaskChem groundwater workplan proposes to install three microwells using a rather unorthodox direct push technique, and sample groundwater for petroleum and volatile organic compounds in the northeast corner and southeast corner of Lot 3. During this investigation, the northeast corner was targeted because of recent findings on the MOA property that indicates groundwater flow direction may be from their property, where TCE was detected, towards your property in a southwest direction. The southeast corner of Lot 3 was targeted because it appears down-gradient from a reported leach pit location on the MOA property. The CSP non objection letter was caveated that the groundwater data obtained will be reliable and representative of the groundwater in those areas. The CSP also requested that AlaskChem coordinate with the MOA prior to implementing its workplan so AlaskChem can hopefully take groundwater measurements in monitoring wells on the adjacent MOA property to assist them in the development of the groundwater map. Rich Sundet
3/25/2003 Meeting or Teleconference Held Sundet met with Michael Krueger of the MOA with their legal counsel Rhonda Fehlen-Westover; Alaska National Guard representative Norman Straub; and Mrs. Henrickson, Ralph Hulbert, Tim Spernak her real estate agent, and Andrew Behrend, her legal counsel, to discuss the next steps to investigate the TCE groundwater contamination found at the AK Guard Mt. View Armory site now owned by the MOA and the adjacent Prescott Rampart Pipeyard site. Hulbert proposed that he submit a plan for a soil vapor gas investigation around the former dump area on both properties and perhaps, off the properties up gradient, e.g., Block 2, Lot 13 or the right-of-way for Mt. View Road. Hulbert noted that the work could begin on 5/1/03 as soon as the frost goes out of the ground and a brief report provided to all parties by 5/15/03. Sundet noted that CS would prepare to begin a drinking water well survey immediately and that after Hulbert's data is received, another such meeting occur for the next step(s). Action can then be proposed if a RP is identified as a result of that work, or the CSP pursue performing a groundwater investigation. Rich Sundet
4/4/2003 Update or Other Action In a letter dated 4/4/03, the CSP provided comments regarding AlaskChem's 4/1/03 dated workplan that proposed a soil vapor gas investigation on the MOA property at 2839 Mt. View Drive and the adjacent Prescott Equipment Pipeyard site at 2774 Rampart Drive. The plan was received by CSP via e-mail on 4/1 and is in follow-up to a meeting between MOA, Prescott Equipment, Alaska Army National Guard, and CSP on 3/25/03. The soil vapor gas investigation would be performed in early May and a final report be provided to the MOA, CSP and Alaska National Guard by 5/15/03. The purpose of the investigation is to hopefully determine the source(s) of the TCE groundwater contamination found on both lots. Rich Sundet
5/27/2003 Update or Other Action On 5/27/03, the CSP issued a non-objection letter to the MOA, Mrs. Henrickson and the Alaska Army National Guard regarding AlaskChem's proposal to begin a Phase II soil vapor gas investigation on the Prescott Pipeyard and the adjacent MOA property. The AlaskChem report for the Phase I soil gas investigation including the subject workplan was submitted to CSP via email on May 15, 2003 and titled "Soil Vapor Investigation on 2774 Rampart Drive and 2839 Mountain View Drive, Results of Round 1" dated May 15, 2003. CSP's letter also noted that the workplan proposed up to 4 new monitoring wells would be installed but did not specify who or when they would be installed. Based upon the findings of the Phase I soil vapor gas investigation which was inconclusive, and that this work would not include further groundwater investigation work, the CSP informed the MOA, Mrs. Henrickson and the Alaska Army National Guard that it would perform a groundwater investigation unless one or more of the parties informed the CSP by 5:00 PM on 6/6/03 that it would perform this work by 6/30/03. Rich Sundet
7/8/2003 Update or Other Action On 7/8/03, DEC emailed to Oasis a RFP to perform a groundwater investigation in the vicinity of the Prescott Equipment Pipeyard. The investigation would include the installation of up to 8 monitoring wells and perform a drinking water well search within 1/4 mile of the site. Rich Sundet
7/17/2003 Update or Other Action Oasis submitted to DEC a revised proposal to perform a groundwater investigation in response to DEC's RFP for a total of $66,378.88 with a contingency for an additional $16,725.58 to install an additional 2 monitoring wells (therefore then a total of 8 wells). Rich Sundet
8/4/2003 Update or Other Action On 8/4/03, SPAR Director Dietrick approved the funding request for $66,378.88 for the groundwater investigation. Rich Sundet
8/5/2003 Update or Other Action On 8/5/03, NTP 18700025-18 was issued to Oasis for $66378.88 to perform the groundwater investigation in the vicinity of the Prescott Pipeyard property. Rich Sundet
8/20/2003 Update or Other Action CSP notified Andrew Behrend legal counsel for Prescott Equipment that the State was beginning a state lead investigation regarding the TCE groundwater contamination in the vicinity of the Prescott Pipeyard and adjacent MOA property (formerly the AKARNG Mt. View Armory site). The letter requested permission for access to install one or more monitoring wells on the Prescott Pipeyard property. Rich Sundet
8/21/2003 Update or Other Action CSP notified Mike Krueger of the MOA that the State was beginning a state lead investigation regarding the TCE groundwater contamination in the vicinity of the Prescott Pipeyard and adjacent MOA property (formerly the AKARNG Mt. View Armory site). The letter requested permission for access to install one or more monitoring wells on the MOA property as well as within the right-of-ways of nearby roads in the vicinity of the known contamination. CSP hand delivered a letter to Katie Frey, General Manager, of AP Logistics, LLC that the State was beginning a state lead investigation regarding the TCE groundwater contamination in the vicinity of the Prescott Pipeyard and adjacent MOA property (formerly the AKARNG Mt. View Armory site). The letter requested permission for access to install one or more monitoring wells on the AP Logistics, LCC property because the property was adjacent to the known contaminated area. Rich Sundet
9/4/2003 Update or Other Action On 9/4/03, CSP provided the Oasis draft workplan dated 8/25/03 to Andrew Behrend representing Mrs. Henrickson and Mike Krueger of the MOA. Rich Sundet
9/11/2003 Update or Other Action On 9/11/03, CSP issued a letter to the MOA ROW department requesting access to install monitoring wells in the MOA's ROWs. The letter noted that DEC's subcontractor Discovery Drilling would be submitting a completed permit application for this work. Rich Sundet
9/16/2003 Update or Other Action In a letter dated 9/16/03 (received on 9/18), Andrew Behrend provided a signed access form from Mrs. Henrickson granting access to locate utilities. POC for Mrs. Henrickson is Tim Spernak or Behrend. Rich Sundet
9/19/2003 Site Characterization Workplan Approved On 9/19/03, DEC received the final workplan "Vicinity of 2774 Rampart Drive Work Plan" dated 9/19/03 from Oasis. DEC verbally approved of the plan on that date. Rich Sundet
9/22/2003 Update or Other Action On 9/22/03, DEC provided via email a copy of the final workplan to Behrend and Hulbert representing Prescott Pipeyard, Krueger of the MOA, and Norm Straub of the AKARNG. Rich Sundet
9/23/2003 Update or Other Action In a letter dated 9/22/03 (received on 9/23), Andrew Behrend provided a signed access form from Mrs. Henrickson granting access to install monitoring wells as set forth in Oasis final workplan dated 9/19/03. Rich Sundet
2/5/2004 Update or Other Action In a letter dated 2/5/04, CSP provided the draft Oasis report "Draft Report Groundwater Investigation Vicinity of 2774 Rampart Drive Anchorage, Alaska" dated 1/29/04 to the three PRPs, i.e., MOA, Alaska National Guard, and Prescott Equipment Co. The letter requested that if the parties had any comments, to please provide the comments prior to 2/23/04. The report showed that the TCE contamination in the groundwater was localized to primarily the MOA (former AKARNG Mt. View Armory site), and the Prescott Pipeyard, and the downgradient International Wood Industries tract adjacent to the Prescott property. Rich Sundet
4/30/2004 Update or Other Action In response to McDougall of Oasis 4/29/04 request to transport 20 drums of slightly contaminated soil to ASR for thermal treatment, CSP issued a letter on 4/30/04 granting permission to transport the soil to ASR. Rich Sundet
6/17/2004 Update or Other Action CSP transmitted to the MOA, Ms. Henrickson and AKARNG one copy each of the Oasis "Final Report Groundwater Investigation Vicinity of 2774 Rampart Drive Anchorage, Alaska" dated June 4/ 2004. CSP received the report on 6/8/04. CSP requested a meeting between all three PRPs around June 29, 2004 to discuss the findings and options for next actions. Rich Sundet
6/24/2004 Meeting or Teleconference Held Sundet and Chris Kennedy met with Mrs. Henrickson, Hulbert, Tim Spernak and Hulbert to discuss the draft NFRAP for the Prescott Pipeyard property and associated ROD, which were provided to them prior to the meeting. Rich Sundet
7/15/2004 Record of Decision ROD signed this date that determined no further remedial action was required but there remain soil (at groundwater interface) and groundwater above established cleanup levels. Jim Frechione
7/15/2004 Institutional Control Record Established IC established that identifies soil and groundwater contamination remaining on site. Also, shallow groundwater aquifer is restricted from use unless DEC (Contaminated Sites and Drinking Water Programs) approve of well installation. Jim Frechione
7/15/2004 Conditional Closure Approved NFRAP was issued based on ROD. Jim Frechione
7/19/2004 Update or Other Action On 7/19/04, Prescott Equipment filed the "Notice of Environmental Contamination", signed by Mary Jane Henrickson as President of Prescott Equipment, Inc. The "Notice..." was required as a deed notice per the condition in the NFRAP and ROD issued for the site. Rich Sundet
8/4/2004 Update or Other Action On 8/4/04, DEC provided Prescott Equipment and the CCs on the earlier 7/15/04 letter a copy of Figure 5 showing the estimated zone of groundwater contamination. It was inadvertently not attached to the 7/15/04 letter. Rich Sundet
9/14/2004 Update or Other Action On 9/14/04, a warranty deed was recorded that showed that Prescott Equipment sold the property to Alaska Mining & Diving Supply, Inc. Rich Sundet
9/20/2004 Update or Other Action In response to a submittal received by CSP from the Municipality of Anchorage that noted that information was incorrect in the NFRAP/IC and ROD issued for this site regarding land ownership, on 9/20/04 CSP informed Prescott Equipment that it had amended the NFRAP/IC and ROD. The amendment noted that the MOA never leased the property to the AKANG. Information in the NFRAP and ROD was based upon several environmental reports that were on file. The 9/20 letter included a time line for land ownership for both Lots 9 and 10, Block 3, First Addition, Alaska Industrial Subdivision in Anchorage. The letter also noted that CSP understood that Prescott Equipment recently sold the subject property and requested information on the new owner so it could keep the new property owner informed regarding the contaminated site. Rich Sundet
10/15/2004 Update or Other Action On 10/15/04, CSP issued letters to Prescott Equipment, MOA, and AKARNG that DEC expects to have groundwater monitoring performed in fall 2004 and in the future for the TCE plume in the Prescott Pipeyard vicinity, and provided them the opportunity as PRPs to perform the work. If no one performs the work, CSP informed them that DEC was prepared to do so. CSP requested if they intend to do the work that they notify CSP by 10/22/04. Rich Sundet
10/19/2004 Update or Other Action CSP discussed the history of the Prescott Pipeyard contaminated site with the new property owner Stephen Hershbach representing Alaska Mining & Diving Supply, Inc. In follow-up, CSP issued a PRP letter and requested that he inform DEC by 10/22/04 whether his company would perform the fall groundwater sampling and if not, sign the enclosed form granting access to DEC and its contractors to perform the work. Rich Sundet
10/21/2004 GIS Position Updated Update the site coordinates from Montana State Graphic locator values using TopoZone Pro, Street Address and Aerial Photo Overlay Features with in conjunction with the Anchorage Area Atlas, 1:10,000 Scale, NAD27. Former Staff
10/22/2004 Update or Other Action On 10/22/04, DEC received a fax from Steve Hershbach of Alaska Mining & Diving that granted access to DEC to perform groundwater monitoring and surveying. Steve also noted that the two monitoring wells were somewhat impaired because the contractor that they had level the surface of the land ran over the wells and the cap was found on one some distance away and the other was not found. Steve noted that his company would repair the monitoring wells. In a followup conversation that day, Steve requested coordinates of the wells and Sundet faxed him the coordinates and mailed a copy of the final Oasis report to him. Steve noted that he would contact Oasis to repair the monitoring wells and inform DEC when this work was finalized. Rich Sundet
10/27/2004 Update or Other Action On 10/27/04, DEC received an email from Rhonda Fehlen-Westover of the MOA granting access to the MOA sign and paint shop. Rich Sundet
11/10/2004 Update or Other Action On 11/10/04, NTP #1870002534 was issued to Oasis Environmental to conduct a Site Characterization / GW Investigation (i.e., one groundwater monitoring event and surveying of the existing monitoring wells) at the subject site. NTP not-to-exceed amount is $14,711.60 and the end date is 6/30/05. Rich Sundet
11/23/2004 Update or Other Action In follow-up to a conversation on 11/12/04, DEC issued a letter to Stephen Hershbach of Alaska Mining & Diving that based upon a 11/12/04 report by Oasis, that it requested that MW-7 be decommissioned because grading activity had filled the monitoring well with soil above the water table. DEC requested a brief report within 30 days of when the well would be decommissioned and that the well be decommissioned by 12/15/04. DEC also noted that it was not requesting replacement of MW-7 at this time but if future data indicates that plume is migrating, that it may request a replacement well. Rich Sundet
12/13/2004 Update or Other Action On 12/13/04, CSP faxed to Oasis marked up pages with comments from Oasis "Draft Work Plan, Groundwater Investigation, Vicinity of 2774 Rampart Drive, Anchorage, Alaska," which DEC received on 12/10/04. Rich Sundet
1/3/2005 Update or Other Action On 1/3/05, DEC received copies of Oasis final workplan "Work Plan Groundwater Investigation Vicinity of 2774 Rampart Drive Anchorage Alaska" dated 12/28/04. Rich Sundet
1/24/2005 Update or Other Action In a letter dated 1/24/05, Oasis informed Alaska Mining and Diving the property owner and DEC that it had abandoned MW-7 on 12/21/04 per DEC's 1992 guidance document "Recommended Practices for Monitoring Well Design, Installation,a nd Decommissioning." Oasis noted that the monitorin well was broken at the ground surface and was filled with gravel above the groundater level. Rich Sundet
5/19/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Rich Sundet
3/2/2012 Update or Other Action Found deed notice in DNR Recorder's Office records and attached document in CS database. Kristin Thompson
10/30/2012 Update or Other Action Staff reviewed and approved of Oasis' "2012 Work Plan for Site Characterization 2774 Rampart Drive Vicinity". This work plan was dated October 24, 2012, and recieved at DEC's Anchorage Office on October 24, 2012. Oasis was hired by DEC to charzcterize the current levels of contaminants of concern in groundwater. Oasis will install three additional groundwater monitoring wells and up to two contingency wells based on field screening results. Eight of the monitoring wells plus any contingency wells will be sampled to characterize the current extent and magnitude of the TCE groudnwater plume. Todd Blessing
10/30/2012 Update or Other Action Staff reviewed and approved of Oasis' "2012 Work Plan for Site Characterization 2774 Rampart Drive Vicinity". This work plan was dated October 24, 2012, and recieved at DEC's Anchorage Office on October 24, 2012. Oasis was hired by DEC to characterize the current levels of contaminants of concern in groundwater. Oasis will install three additional groundwater monitoring wells and up to two contingency wells based on field screening results. Eight of the monitoring wells plus any contingency wells will be sampled to characterize the current extent and magnitude of the TCE groudnwater plume. Todd Blessing
5/30/2013 Document, Report, or Work plan Review - other ADEC recieved the 2013 Groundwater Investigation Report. Two wells were installed and groundwater was sampled at seven wells. TCE was the only COC detected above cleanup levels and concentrations ranged from non-detect to 0.142 mg/L, exceeding the cleanup level of 0.005 mg/L. Meghan Dooley
1/20/2015 Site Visit Site visit to observe investigation at 2945 Mnt. View Drive. Bill O'Connell
3/18/2015 Site Characterization Report Approved Reviewed 2015 Vapor Intrusion and Sub-Surface Investigation Report for Prescott Equipment-Rampart Drive. The investigation consisted of two rounds of sub-slab vapor sampling at the International Wood Industries building at 429 Industrial Way and a subsurface investigation into the nature and extent of soil and groundwater contamination at the Anchorage Vehicle Processing Facility at 2945 Mountain View Drive. Sub-slab vapor samples were collected from three sampling ports on two occasions in 2014. During one event, 1,1,2,2-tetrachloroethane was detected above the commercial target level however the duplicate sample was below the detection limit for this compound. All other results from both sampling events were below commercial target levels. To evaluate the extent of contamination to the North, four soil borings were advanced and sampled and temporary monitoring wells were installed for groundwater sampling. TCE was detected in soil in two of the borings at concentrations up to 2.06 mg/kg and in groundwater in one of the wells at 0.158 mg/l. Analytical data suggest the extent of the plume was successfully delineated as a result of these investigations. Bill O'Connell

Contaminant Information

Name Level Description Media Comments
Trichloroethene > Table C Groundwater
Trichloroethene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil

Control Type

Type Details
Notice of Environmental Contamination DEC required a NEC for the ROD issued for Lot 9, Block 3, First Addition Alaska Industrial Subdivision in Anchorage be recorded at the DNR Recorder's Office. On 7/19/04, Mrs. Henrickson filed the NEC with the Recorder's Office District 301 and its identification number is 2004-053359-0.

Requirements

Description Details
Excavation / Soil Movement Restrictions NEC requires if soil above cleanup levels becomes accessible in the future additional investigation is required and if soil is excavated below 25 ft bgs, a workplan approved by DEC is required prior to such work. If soil is excavated below 25 ft bgs, a workplan approved by DEC is required prior to such work.
Groundwater Use Restrictions Use of groundwater restricted. Any proposal to install a drinking water well must be submitted to DEC's drinking water program. If well installed in the upper aquifer, VOCs must be sampled on a yearly basis and reported to DEC's CSP and DWP.
Groundwater Monitoring A groundwater monitoring plan is required to sample MWs 2,3,4,5,6,7,8, 9 and 10 in September 2004 and once every other year after. Sampling for VOCs per EPA Method 8260 is required. A report is to be submitted to DEC within 60 days of each sampling event.
Advance approval required to transport soil or groundwater off-site. Off site transportation is required of contaminated soil and groundwater. DEC approval is necessary prior to transport.
Other Access to the site shall be granted to owners of Lot 9 Block 3, First Addition Alaska Industrial S/D to DEC or its consultant or to a PRP that is allowed by DEC to inspect and to sample monitoring wells on the lot (MWs 6 & 7). If monitoring wells are negatively impacted, the owners of the lot shall replace/repair them under a plan approved by DEC. Owner is required to provide DEC with current phone numbers and address so they can be reached. DEC approval is required prior to replacing/repairing damaged monitoring wells on the lot, and to provide owner contact address/phone numbers.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close