Action Date |
Action |
Description |
DEC Staff |
4/27/2001 |
Interim Removal Action Approved |
ADOT&PF was approved to excavate contaminated soils encountered during their apron upgrade and stockpile at the Coast Guard base. |
Don Fritz |
5/14/2001 |
Cleanup Plan Approved |
Excavation plan addendum to interim removal action approved. |
Don Fritz |
8/29/2001 |
Site Added to Database |
Petroleum contamination. |
Bruce Wanstall |
8/29/2001 |
Site Ranked Using the AHRM |
Preliminary ranking. Pillar Creek and Monashka Creek Reservoirs provide water, which is stored and distributed by pipe throughout the area. |
Bruce Wanstall |
1/9/2003 |
Update or Other Action |
Comment letter provided for August 2002 soil sampling analytical report. The report was inadequate, and failed to relay needed information to evaluate what took place |
Don Fritz |
2/3/2004 |
Update or Other Action |
Received a current conditions report from the Coast Guard. The intent is to have remaining contamination at the site addressed under the Solid Waste Management Unit 16 for the Kodiak Coast Guard Base. |
Don Fritz |
2/19/2004 |
Update or Other Action |
Received a memo from the Coast Guard to the Army Corps of Engineers requesting the Airport Apron drum site be worked as a Fud based on a Current Conditions Report. Memo states that the contamination occurred while a DOD site prior to Coast Guard occupation |
Don Fritz |
3/22/2004 |
Update or Other Action |
File number assigned and entered into the Fileroom DB and CS DB. |
Alyce Hughey |
9/7/2005 |
GIS Position Updated |
Using Figure 2 from a Site Closure Report, from T & R Environmental Consulting Inc., dated August 2002, in conjunction with TopoZone Pro, entered the coordinates for this site. Metadata includes USGS Topo Maps 1:63K, TopoZone Pro Street Maps, Black and White Aerial Photo, on a Medium Size Map, View Scale 1:24,000, Coordinate Datum NAD83. Moderate to high degree of confidence in accuracy of location. |
Alyce Hughey |
11/18/2005 |
Update or Other Action |
File sent to Anchorage from Soldotna, and changed project manager from Don Fritz to Jeff Brownlee. |
Alyce Hughey |
3/28/2007 |
Update or Other Action |
Site is currently in the FUDS program, but considered a low priority due to limited exposure pathways. |
Jeff Brownlee |
3/28/2007 |
Exposure Tracking Model Ranking |
|
Jeff Brownlee |
9/15/2016 |
Site Visit |
ADEC Contaminated Sites program staff conducted site visits and inspections of the contaminated sites which are located on the USCG Base Kodiak between September 15-16, 2016. |
Curtis Dunkin |
6/24/2021 |
Document, Report, or Work plan Review - other |
ADEC reviewed the scoping letter and preliminary project drawings for the Kodiak Airport Rehabilitation Project and submitted general review comments to the Alaska Department of Transportation and Public Facilities. |
Curtis Dunkin |
7/29/2021 |
Document, Report, or Work plan Review - other |
ADEC reviewed the revised draft 2021 Kodiak Airport Perimeter Fence Project Environmental Management Plan and submitted review comments to the ADOT&PF and USCG. |
Curtis Dunkin |
8/10/2022 |
Document, Report, or Work plan Review - other |
ADEC reviewed the final 2022 Kodiak Airport Perimeter Fencing Upgrades 2021 Pre-construction Sampling Summary Report and submitted a final approval letter to ADOT&PF. |
Curtis Dunkin |
10/24/2022 |
Document, Report, or Work plan Review - other |
DEC evaluated and returned commments to the USCG on the “Environmental Management Plan (EMP), Kodiak Airport Perimeter Fencing Upgrades Project, State Project No. SFAPT00144, Kodiak, Alaska” (Undated) and the “Contaminated Materials Management Plan, ADEC File No’s. 2601.38.112, 2601.26.003, 2601.38.006, 2601.38.073, KDK Airport Perimeter Fencing Upgrades, State Project No. SFAPT00144, October 17, 2022.” The revised draft EMP and contaminated materials management plan (CMMP) describe the excavation, stockpiling and sampling of PFAS-contaminated and potentially PFAS-contaminated media at the Kodiak Airport during fencing construction. |
Melinda Brunner |
2/10/2023 |
Document, Report, or Work plan Review - other |
ADEC reviewed the revised redline final 2022/23 ADOT&PF Kodiak Airport Perimeter Fence Environmental Management Plan and the Contaminated Materials Management Plan and submitted an approval letter to DOT&PF to finalize the document and implement the plan in the field. |
Curtis Dunkin |