Action Date |
Action |
Description |
DEC Staff |
3/12/2003 |
Site Added to Database |
DRO and lead. |
Cliff Walden |
4/14/2003 |
Interim Removal Action Approved |
Initial screening level investigation at this site and other APC facilities approved as interim removal action. Site will be listed as either non-qualifying or active depending on results. |
Bill Janes |
8/15/2003 |
Cleanup Plan Approved |
|
Bill Janes |
8/15/2003 |
Cleanup Level(s) Approved |
Method 3 - DRO 691 ppm |
Bill Janes |
8/27/2003 |
Update or Other Action |
Contractor on site conducting cleanup activities. |
Bill Janes |
8/29/2003 |
Update or Other Action |
Notification from Forest Service that batteries were discovered and reported under CERCLA. A Time Critical Removal Action was initiated. |
Bill Janes |
9/2/2003 |
Update or Other Action |
Carson Dorn reported that 109 batteries have been found thus far. |
Bill Janes |
9/3/2003 |
Update or Other Action |
Site visit with Carson Dorn and Forest Service. |
Bill Janes |
9/11/2003 |
Site Ranked Using the AHRM |
Ranks medium due to the presence of lead |
Bill Janes |
9/11/2003 |
Meeting or Teleconference Held |
Teleconference with FS and consultants to discuss options for dealing with the expanded volume of contaminated soil, GW considerations and possible revisions of cleanup levels. |
Bill Janes |
9/23/2003 |
Meeting or Teleconference Held |
Site visit and meeting in Hoonah to discuss site options and possible revision to the ACLs. |
Bill Janes |
10/7/2003 |
Update or Other Action |
Cleanup plan addendum for second round of work and installation of monitoring wells downgradient of generator shed excavation. |
Bill Janes |
10/9/2003 |
Update or Other Action |
Contractor on site conducting second phase of cleanup. |
Bill Janes |
12/1/2003 |
Site Number Identifier Changed |
Changed Workplan from 01 to 09 based on lead contamination found from batteries. |
Bill Janes |
3/5/2004 |
Update or Other Action |
Data from the three stockpiles show #1 meets cleanup levels, # 2 does not and # 3 is questionable. Eight of 16 are below cleanup level. |
Bill Janes |
4/28/2004 |
Update or Other Action |
Bioremediation cell design and GW monitoring plan approved. |
Bill Janes |
5/12/2004 |
Update or Other Action |
Accompanied Tom Hanna on site visit. Todd Miller Construction just about finished spreading soil out for bioremediation. More batteries recently uncovered in the course of excavating clean material for berm construction. |
Bill Janes |
5/28/2004 |
Update or Other Action |
Contractor returning to site to conduct tilling and reconstruct part of the cell. About 200 cubic yards needs to be moved out of the road per FS request. Additional test excavations to be done as well due the presence of a single battery at one of the areas not investigated. |
Bill Janes |
7/15/2004 |
Update or Other Action |
June biocell sampling showed only two samples above cleanup levels. Final tilling to occur in mid-July. Three of four GW monitoring wells had insufficient water for sampling. Surface water sample ND |
Bill Janes |
7/15/2004 |
Update or Other Action |
Email approval under 18 AAC 75.370 to transport batteries, shards and lead and petroleum contaminated soil out of state. |
Bill Janes |
7/31/2004 |
Update or Other Action |
Additional 400 cubic yards of previously undetected contaminated soil near the debris pile and generator excavated and stockpiled at the upper end of the curent biocell. |
Bill Janes |
8/23/2004 |
Update or Other Action |
Approval given to bioremediate the additional 400 cubic yards in the northeast corner of the current biocell. |
Bill Janes |
9/14/2004 |
Update or Other Action |
Approval given for a final round of water sampling. See email this date. |
Bill Janes |
10/21/2004 |
Update or Other Action |
Groundwater wells and bio cell # 2 sampled. DRO levels in the cell ranged from 50 to 420 mg/kg, meeting the alternative cleanup level of 691 mg/kg. RRO ranged from 297 to 1,590 mg/kg, also meeting the cleanup level. The 3 GW monitoring wells sampled all met cleanup levels. |
Bill Janes |
1/21/2005 |
Update or Other Action |
Review and concurrence of 11/15/04 memo documenting the groundwater and biocell sampling results. |
Bill Janes |
11/4/2005 |
Update or Other Action |
Draft NFA letter sent to FS and APC for review and comment. |
Bill Janes |
11/30/2005 |
Institutional Control Record Established |
The Forest Supervisor issued an Administrative Site Controls Memorandum to the District Ranger on October 31, 2005. The Forest Service has noted the locations where petroleum-contaminated soil remains above method 2 cleanup levels. Administrative site control boundaries are notated by polygons in the Forest Service Geographic Information System. |
Bill Janes |
11/30/2005 |
Conditional Closure Approved |
|
Bill Janes |
12/5/2005 |
Update or Other Action |
Conditional written determination covering 17 camp cleanups issued to APC by the Forest Service. No further hazardous substance removal required by the FS. |
Bill Janes |
1/23/2007 |
Exposure Tracking Model Ranking |
Intitial Ranking Complete for Source Area: 74840 (Autogenerated Action) |
|
3/17/2008 |
Update or Other Action |
Data are stored for all APC logging camp cleanup sites on a CD in the Cape Pole file. |
Bill Janes |
9/8/2008 |
Exposure Tracking Model Ranking |
Updated Ranking Complete for Source Area: 74840 (Autogenerated Action) |
|
3/2/2010 |
Institutional Control Record Removed |
ICs are removed as an administrative action. The remaining contamination has been noted on the U.S. Forest Service GIS records. The current site conditions meet the 2009 site closure criteria.
|
Evonne Reese |