Action Date |
Action |
Description |
DEC Staff |
3/17/2004 |
Site Added to Database |
DRO contaminated soil from fuel distribution lines. |
Deborah Williams |
3/17/2004 |
Site Ranked Using the AHRM |
Preliminary ranking. |
Deborah Williams |
5/7/2004 |
Update or Other Action |
Waiver approved for sampling by NPS personnel. |
Larry Johnson |
8/24/2004 |
Site Characterization Workplan Approved |
Approved workplan. Letter located at G:\SPAR\Spar-Contaminated Sites\38 Case Files (Contaminated Sites)\220 Denali National Park\220.38.013 Denali Nat'l Park C-Camp HOT Investigation. Basic approval for early stages of site investiagtion.Waiver approved for sampling by NPS personnel. |
Mike Jaynes |
1/26/2005 |
Update or Other Action |
NPS submitted over-excavation and remediation report. A total of 175 cubic yards was excavated from 38 individual locations. Soil samples for 14 sites exceeded DRO cleanup levels. BTEX exceeded cleanup levels at two of these sites. Contaminated soil was stored at the 7-mile pit until it was hauled to OIT for thermal remediation. Remaining excavation work planned for the east side of the site was deferred until 2005. NPS also plans to complete additional work at Buildings 185, 152, 153, 154, and 155 in 2005. (Action entered in 2008) |
Janice Wiegers |
1/26/2005 |
Update or Other Action |
Hart Crowser submitted an investigation report describing installation of 8 soil borings, 4 of which were completed as monitoring wells (MW-5, MW-6, MW-7, MW-8). DRO exceeded soil cleanup levels in MW-5 and BH-4 at shallower depths, but not at deeper depths. DRO exceeded groundwater cleanup levels in MW-5, and was present, but below cleanup levels in the downgradient wells MW-7 and MW-8. Groundwater was found 33 to 57 ft bgs. (Action entered in 2008) |
Janice Wiegers |
6/22/2005 |
Update or Other Action |
Spoke with Bill Heubner of NPS who stated Hart Crowser has discovered 2 feet of product in monitoring well just north of the site (MW-3 on Auto Shop site). NPS to move a product recovery system in place and will discuss issue further. This may be associated with the separate fuel distribution site. |
Mike Jaynes |
9/16/2005 |
Update or Other Action |
Hart Crowser submited a groundwater monitoring report for samples collected in June. All June samples are non-detect, except for MW-5, which contains DRO below cleanup levels. (Action entered in 2008) |
Janice Wiegers |
12/1/2005 |
Update or Other Action |
Hart Crower submitted monitoring report for Fall 2005. (Action entered in 2008) |
Janice Wiegers |
3/13/2006 |
Update or Other Action |
NPS submitted over-excavtion and remediation report for the east side and center of the site. Excavations were completed at 12 locations with 400 cubic yards of contaminated soil removed. The soil will be stored at Mile 7 until it can be remediated at OIT. Several areas were re-excavated based on the results from the 2004 excavation work. Due to concern about structural integrity, residual contamination was left beneath a cabin with a DRO level of 1000 mg/kg. Significant volatile contamination was also found at Building 154 - which was the location of a paint shop in the 1930's. Benzene, methylene chloride and chromium were present in one sample from this location. Excavation was stopped at Building 154 due to high voltage lines. NPS plans to move the electrical lines and continue excavation in the future.
(Action entered in 2008) |
Janice Wiegers |
3/31/2006 |
Update or Other Action |
Workplan was submitted to assess groundwater quality and flow characteristics. Additional investigation of the groundwater near MW-8 was also planned based on discovery of contamination near this location in 2005. According to the workplan, in 2005 NPS removed 375 cy of contaminated soil from excavation activities in this area. (Action entered in 2008) |
Janice Wiegers |
9/8/2006 |
Update or Other Action |
Groundwater monitoring report submitted. Petroleum was not detected in the wells sampled. (Action entered in 2008) |
Janice Wiegers |
9/18/2006 |
Spill Transferred from Prevention Preparedness and Response Program |
Site transferred from PERP staff Toivo Luick. Spill no. 02309919301; spill date 7/12/02; substance = diesel (heating oil); amount 480-500 gallons; PERP file no. 220.02.001. The National Park Service was in the process of replacing the fuel oil heaters with propane in the resident cabins at C-Camp when a construction crew ruptured an aboveground fuel line connected to a full or nearly-full 500-gallon tank during piping abandonment. 170 cubic yards of contaminated gravel were removed but the excavation had to stop at 15 feet below ground surface due to potential threats to the integrity of the road and nearby structures. |
Mitzi Read |
12/5/2006 |
Update or Other Action |
Updated site name per Project Manager. |
April Woolery |
6/11/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Janice Wiegers |
5/23/2012 |
Site Visit |
Performed a site visit at the C-Camp Auto Shop site and the C Camp Emergency Services/Fire Management Building site in Denali National Park & Preserve. National Park Service (NPS) staff gave us a tour of the C-Camp sites, sites in the Headquarters area and the Hotel Powerhouse site. At the C-Camp site we observed drilling and soil sampling for the installation of a monitoring well. |
Melody Debenham |
5/23/2013 |
Document, Report, or Work plan Review - other |
Approved the final work plan for groundwater sampling at the C-Camp sites. Groundwater samples will be collected from 14 of the 17 wells on site and analyzed for diesel range organics, gasoline range organics, and benzene, ethylbenzene, toluene, and xylenes. In addition, 3 wells near the Emergency Services/Fire Management Building will be analyzed for volatile organic compounds. |
Melody Debenham |
5/15/2014 |
Document, Report, or Work plan Review - other |
Approved final 2014 Comprehensive Report documenting results from the 2013 groundwater monitoring. Diesel range organics were detected above the cleanup level in 4 monitoring wells. Gasoline range organics were detected above the cleanup level in 2 monitoring wells. The report also provide a comprehensive review of all of the contaminated sites at the C-Camp area (file numbers 220.26.005, 220.38.010, 220.38.041, 220.26.002, and 220.38.004) |
Melody Debenham |
6/27/2014 |
Document, Report, or Work plan Review - other |
Approved work plan describing site characterization activities to identify extent of remaining contamination at former Cabin 154 site. |
Melody Debenham |
9/30/2014 |
Potentially Responsible Party/State Interest Letter |
Potentially responsible party letter sent to the National Park Service. |
Melody Debenham |
10/22/2014 |
Document, Report, or Work plan Review - other |
Approved final 2014 C-Camp Site Investigation Report describing site investigation activities at the Former Cabin 154 site. Past investigations identified petroleum contaminated soil near Cabin 154 associated with the C-Camp housing area fuel distribution pipeline. 16 test pits were excavated in the area of the Former Cabin 154 site to delineate the extent of remaining contamination. Samples were analyzed for GRO, DRO, and VOCs. The two locations with the highest field screening results were also analyzed for PAHs. No GRO, DRO, VOCs, or PAHs were detected above the cleanup levels |
Melody Debenham |
3/13/2015 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78397 paint shop. |
Melody Debenham |
1/9/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78397 paint shop. |
Melody Debenham |
1/9/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 78398 fuel distribution tanks and lines. |
Melody Debenham |
1/30/2017 |
Cleanup Complete Determination Issued |
|
Melody Debenham |
1/30/2017 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Melody Debenham |
10/6/2017 |
Institutional Control Compliance Review |
IC compliance review conducted and staff changed from Melody Debenham to IC Unit. Reminder system set to follow-up in 2020. |
Kristin Thompson |
1/27/2020 |
Institutional Control Compliance Review |
IC compliance review conducted, and all ICs functioning as intended. Reminder system set to follow-up in 2023. |
Tim Sharp |
8/17/2022 |
Meeting or Teleconference Held |
ADEC met with NPS and representatives from Ahtna to discuss multiple site histories and potential paths forward for remediation and eventual closure with or without ICs. |
Tim Sharp |