Action Date |
Action |
Description |
DEC Staff |
12/4/2003 |
Site Added to Database |
Historical Oil Spill. Transfer from PERP. |
Bruce Wanstall |
12/15/2003 |
GIS Position Updated |
GPS using North American Datum 27 at airport frontage road. |
Bruce Wanstall |
6/2/2004 |
Site Ranked Using the AHRM |
Site Assessment data, site inspection and knowledge of the area. |
Bruce Wanstall |
6/7/2004 |
Update or Other Action |
File review. Request via email for Site Assessment final report from responsible party. |
Bruce Wanstall |
6/29/2004 |
Update or Other Action |
Site Assessment Report review and discussion with RP consultant to obtain sample COC for lab data; groundwater monitoring will follow Phase II Site Characterization and Corrective Action. |
Bruce Wanstall |
10/4/2004 |
Interim Removal Action Approved |
Fifty cubic yards of contaminated soil was excavated from 3 source areas on the property. Samples from the limits of excavation for DRO at the hanger foundation reached 2,480 mg/kg; at the former jet fuel AST DRO reached 417 mg/kg; and at the dispenser DRO concentrations were all below 230 mg/kg. Contaminated material was shipped and remediated off-site. |
Bruce Wanstall |
10/15/2004 |
Site Characterization Report Approved |
Site Characterization Approval with request for groundwater assessement letter sent to RP; pdf version sent by email. |
Bruce Wanstall |
11/3/2005 |
Update or Other Action |
Requested groundwater assessment and sampling of the on-site drinking water well; coordinating with consultant on driller schedule. |
Bruce Wanstall |
7/19/2006 |
Update or Other Action |
Letter of interest requesting groundwater investigation sent to the responsible party via regular and email. |
Bruce Wanstall |
8/24/2006 |
Site Characterization Workplan Approved |
Ground water assessment workplan approval sent by letter. Contaminated soil removal was completed from the surface to the capillary fringe of the vadose zone in three areas: the jet fuel above ground storage tank, the dispenser hydrant, and the emergency generator fuel storage tank. Contaminated soil removal at the generator tank site was limited also by the hanger foundation; diesel range hydrocarbon concentration data at that excavation sidewall reached 13, 000 mg/kg. |
Bruce Wanstall |
4/12/2007 |
Exposure Tracking Model Ranking |
Initial ETM site ranking |
Bruce Wanstall |
4/16/2007 |
Update or Other Action |
Data indicate that concentrations of DRO above the most conservative Method 2 cleanup level remain in soils at the site. The remaining DRO concentrations in soil were 2,400 mg/kg at the emergency generator drum storage excavation and 417 mg/kg at the jet fuel AST excavation. Further cleanup was determined to be impracticable near the former jet fuel AST, the emergency generator diesel drum, and the former dispenser hydrant because additional excavation of contaminated soil was submerged below the ground water table.
|
Bruce Wanstall |
4/18/2007 |
Site Characterization Report Approved |
The findings in the Release Investigation by Oasis in 2006 adequately demonstrate that residual petroleum contamination in the former source areas are of insufficient mass and concentration to cause an exceedance of regulatory benchmarks for groundwater. The ADEC finds that data in the release investigation are sufficient to support site closure with institutional controls placed on the property that restrict excavation and transport of material having residual petroleum contamination. |
Bruce Wanstall |
4/19/2007 |
Update or Other Action |
Notice of Environmental Contamination: The remaining DRO concentrations in soil were 2,400 mg/kg at the emergency generator drum storage excavation and 417 mg/kg at the jet fuel AST excavation. Further excavation of impacted soil was limited by shallow groundwater. |
Bruce Wanstall |
4/23/2007 |
Conditional Closure Approved |
The contaminant concentrations remaining on the ERA Yakutat Airport property were evaluated with regard to the potential exposure pathways and ADEC determined they do not pose an unacceptable risk to human health or the environment. The residual DRO remaining on site will attenuate over time and site management controls are established to ensure contamination will not impact ground water. |
Bruce Wanstall |
4/23/2007 |
Institutional Control Record Established |
Any proposal to transport soil or groundwater off site requires ADEC approval in accordance with 18 AAC 75.325(i). |
Bruce Wanstall |
4/24/2007 |
Long Term Monitoring Established |
ERA will submit for approval a monitoring plan to sample ground water again by June 1st 2010 to ensure that residual petroleum impacts to soil are not migrating in concentrations that exceed Table C cleanup levels |
Bruce Wanstall |
10/29/2008 |
Long Term Monitoring Complete |
Updated ETM ranking: In 2006, four temporary monitoring wells downgradient from source areas were sampled and tested for BTEX, GRO, DRO and PAHs. Results for all analytes were below Table C screening levels; DRO was detected in test well-6 at 1.46 mg/L but may have been influenced by a utility conduit preferential pathway from a spill source. The findings in the Release Investigation by Oasis in 2006 adequately demonstrate that residual petroleum contamination in the former source areas are of insufficient mass and concentration to cause an exceedance of regulatory benchmarks for groundwater. Surface soil and migration to groundwater pathways are complete but the risk of exposure not unacceptable. |
Bruce Wanstall |
4/1/2010 |
Update or Other Action |
Check Received $100.40 from Law 03/25/10 |
Traci Nebeker |
3/7/2013 |
Institutional Control Record Removed |
The long term groundwater monitoring has been completed. This site meets the 2009 closure policy therefore ICs can be removed. The defaul requirement of any proposal to transport soil or groundwater off site requires ADEC approval in accordance with 18 AAC 75.325(i) will still apply. |
Evonne Reese |