Skip to content Skip to content

Site Report: Fort Greely Bldg 617 Fuel Facility

Site Name: Fort Greely Bldg 617 Fuel Facility
Address: North Side of Shaw Avenue, Fort Greely, AK 99731
File Number: 141.38.041
Hazard ID: 4050
Status: Active
Staff: Carly Jensen, 9072697558 carly.jensen@alaska.gov
Latitude: 63.975598
Longitude: -145.717136
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

The Petroleum, Oil and Lubricant (POL) Facility site is located west of Former Landfills 4 and 5 on Shaw Avenue, and is a part of the Fort Greely (FGA) Fuel Facility. The POL Facility was constructed between 1955 and 1961 and was connected to the Canadian Oil (CANOL) distribution system by adjunct supply lines until approximately 1972. The Facility consists of 37,000 square feet, with two fuel dispensing islands for gasoline and diesel, eight USTs, a truck loading rack, a pump station (Building 617), operations office (Building 618), and a valve pit which was connected to two 630,000-gallon aboveground storage tanks (ASTs). In 1984, a 100-gallon motor gas (MOGAS) spill occurred at Building 617, and in 1998, 30-gallons of diesel spilled during refueling operations. Environmental investigations were completed from 1995 to 2010 to delineate and characterize the petroleum contamination. Exceedances for diesel range organics (DRO), gasoline range organics (GRO) and ethylbenzene were identified in the soil, and two areas of contamination were found, one near the 1984 spill site and the other near the 1998 spill site. Groundwater monitoring wells (MW-6 and MW-8) were sampled last in 2017 for GRO, benzene, toluene, ethylbenzene, xylenes (BTEX), ethylene dibromide (EDB), and DRO. No contaminants exceeded the project action levels in 2017. Groundwater monitoring at this site is expected to continue. The corresponding U.S. Army HQAES site number is: 02341.1082.

Action Information

Action Date Action Description DEC Staff
8/28/2003 Site Characterization Workplan Approved Soil sampling workplan. Ground water characterization will be conducted at a later date. Greg Light
9/23/2004 Site Characterization Report Approved Site characterization workplan approved for assessing potential hydrocarbon impacts to the soil at USTs 439 and 442 near Building 617 before they are commissioned as spill containment vessels. A total of seven soil borings will be completed within two feet of the tank sidewalls surrounding the two tanks. Emily Youcha
9/27/2004 Interim Removal Action Approved Approximately 350 cubic yards of POL contaminated soils was excavated during the removal of Fort Greely Underground Storage Tanks (UST) numbers 440 and 441. The POL contaminated soils will be transported to FMW LLC, which is an ADEC approved soil treatment facility. Further cleanup is needed at site. Emily Youcha
10/1/2004 Institutional Control Record Established In the October 2004 Draft Decision Document Fact Sheets, administrative controls (ACs)were estblished in order to minimize risk to human health and the environment. The site is included in the post’s Geographic Information System (GIS), a tool used in the Dig Permit process for notifying contractors, workers, and base personnel of the potential for contamination to exist at this site. The Dig Permit process is used to prevent installation of water production well(s) through the contaminated area, and prevent removal of contaminated material from the site to off-base locations or to environmentally sensitive areas. If future land disturbance activities at the site encounter contamination, the contaminated material encountered will be properly remediated or disposed of in accordance with applicable regulations. The site will be included in 5-year reviews to periodically verify compliance with the ACs. Emily Youcha
3/31/2005 Site Added to Database DRO, GRO and benzene contaminated soil. Deborah Williams
3/31/2005 GIS Position Updated The locational data was collected by the PM and she used Topozone, NAD 83. Deborah Williams
3/31/2005 Update or Other Action ADEC recieved a site characterization summary report dated Feb 2005. The report presents results of further site characterization efforts at the Fort Greely Fuel Facility. Borehole data indicate the presence of contamination at a depth of 111-131 feet below ground surface. Sampling of a well approximately 200 feet downgradient from the valve pit indicates low-level ground-water contamination at the well, but levels are below ADEC cleanup levels. The report is adequate, but ADEC does not consider it a complete site characterization according to 18 AAC 75.335 because the conceptual site model, proposed cleanup levels, and/or proposed cleanup techniques are not included. Emily Youcha
4/13/2005 Update or Other Action Site is in the Fort Greely DPW compliance program. Cost recovery needed for this site. Emily Youcha
5/25/2005 Meeting or Teleconference Held Staff conducted a site visit of Fort Greely. Summer fieldwork is underway and includes soil gas surveys, drilling and sampling several deep boreholes, and installation of at least two new monitoring wells. Staff also attended a RAB meeting where the general public recieved an update on site work for this and upcoming seasons. Emily Youcha
7/6/2005 Site Number Identifier Changed Changed Region from 31 to 33. Former Staff
5/22/2007 Meeting or Teleconference Held Staff attended Interagency Coordination Meeting in Fairbanks. A summary of the past years and future remedial efforts was provided. Zachary Richter
5/23/2007 Meeting or Teleconference Held ADEC Staff attended a RAB meeting held in Delta Junction. The past years work at Fort Greely was summerized and future work projects were presented. Work at the North and South Tank Farms was highlighted. Zachary Richter
5/23/2007 Update or Other Action The Alaska Department of Environmental Conservation (ADEC) received the Groundwater Monitoring and Data Analysis Work Plan Fort Greely, Alaska on April 27, 2007. This work plan abides by the 2005 Final Work Plan with modifications to the wells and analytical parameters to be monitored particularly the addition of polycyclic aromatic hydrocarbon analysis at monitoring wells MW-12, MW-13, and MW-14. Additionally, the pump type used in sampling the monitoring wells will be changed by replacing the Grundfos Ready Flow pump with a QED Sample Pro 1.75 inch bladder pump and QED MP10 controller, or equivalent. All other sampling methodology will remain the same as the 2005 Final Plan. The final modification to the 2007 Work Plan is the addition of Volatile Organic Analysis/1,2-dibromoethane monitoring at drinking water wells ECP2 and ISFAC at the missile field. An updated list of wells to be monitored, and the parameter for analysis from each well, for upcoming sampling events has been provided to replace Table 5 of the 2005 Final Work Plan. ADEC has completed its review of this document and has found that the Groundwater Monitoring and Data Analysis Work Plan Fort Greely, Alaska for 2007 adequately meets the requirements set forth in 18AAC75.355, and with the addition of the previously agreed upon amendment, this work plan is approved. Zachary Richter
7/2/2007 Update or Other Action The Alaska Department of Environmental Conservation (ADEC) has completed its assessment of the environmental laboratory data and quality assurance requirements as set forth in ADEC Technical Memorandum 06-002 for the Groundwater Monitoring 2006 Analytical Data Report Fort Greely, Alaska, February 2007. The report adequately addresses the requirements set forth by ADEC for both laboratory data packages and Quality Assurance (QA) Summaries, therefore the report is approved. Zachary Richter
4/23/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Deborah Williams
8/12/2008 Site Characterization Workplan Approved ADEC approved Fort Greely's Compliance and IRP workplans for the 2008 field season. The following sites will be addressed during the 2008 field season: Compliance: MOGAS/DFA Fuel Line Site (BRAC Sites 92, 94, 96, 97, 98, 99, 100 and 134), Building 612 (BRAC 135) Dry Well, Bldg 628 (BRAC 57) Dry Well, Bldg 157 (BRAC 103) Dry Well, Bldg 675 (BRAC 54) Dry Well, Preconstruction Survey at the Proposed Community Activity Center (CAC) and Active POL Farm Valve Pit Site (Bldg 617). IRP: BRAC Site 85N, 85S, and 133, including Soil Boring 41/MW 10 Area, South Tank Farm, Former Laundry Facility at Bldg 675 (BRAC Site 54). Deborah Williams
11/5/2008 Meeting or Teleconference Held ADEC staff participated in the Restoration Advisory Board meeting for Fort Greely in Delta Junction. During the meeting, Glen Shonkwiler with the United States Army Space and Missile Defense Command presented the fieldwork that was completed during the 2008 field season at Fort Greely. The 2008 fieldwork included remediating the soil in the biocell at the South Tank Farm (STF); conducting further delineation of the subsurface soils at the STF; installing four groundwater monitoring wells in the Old Post area and downgradient of the STF; completing the investigation at the MOGAS fuel line in the Old Post area; conducting additional survey of the Jarvis Creek Munitions Burial site; and conducting additional investigation of the Building 675 vault. He also presented the work that was planned to be completed during 2009. Deborah Williams
10/21/2009 Document, Report, or Work plan Review - other ADEC staff reviewed the document titled Draft 2008 Groundwater Monitoring and Data Analysis Report, Fort Greely, Alaska, dated March 2009. The Fort Greely groundwater monitoring program consists of monitoring wells that were installed during investigation activities on FGA from 1997 to the present. DEC approved a comprehensive groundwater monitoring approach in the 2005 Work Plan. Yearly modifications to the 2005 workplan are incorporated as needed to address environmental program objectives. Monitoring well locations and sampling frequency have been chosen to provide site specific monitoring where necessary, and comprehensive coverage for the old post and main cantonment areas of Fort Greely. Currently, a total of 30 wells are included in the groundwater monitoring program: 11 of these are sampled during the spring and fall on even numbered years, two drinking water wells are sampled quarterly, and 17 monitoring wells are sampled semi–annually. This report summarizes the 2008 groundwater monitoring efforts. A letter detailing staff comments has been provided to the Army. Tana Robert
9/4/2013 Document, Report, or Work plan Review - other Approved the final groundwater sampling work plan for Ft. Greely. As part of the multi-year, post-wide groundwater monitoring program, groundwater samples will be collected from 35 wells. Melody Debenham
4/29/2015 Meeting or Teleconference Held Attended Restoration Advisory Board Meeting. Proposed work in 2015 includes post-wide groundwater monitoring, decommissioning unused monitoring wells, developing a Land Use Control and Long Term Maintenance Plan, and completing propose plans/no further action documents for 51 sites. Melody Debenham
8/28/2015 Document, Report, or Work plan Review - other Approved the Final 2015 Groundwater Monitoring and Data Analysis Work Plan Addendum for long-term post-wide groundwater monitoring at Fort Greely. Groundwater samples will be collected from 25 monitoring wells and 5 supply wells. Melody Debenham
9/2/2015 Document, Report, or Work plan Review - other Approved the Final 2014 Groundwater Monitoring and Data Analysis Report documenting the 2014 post-wide groundwater monitoring activities at Fort Greely. Analytical results from four monitoring wells at the BRAC 94 site were above cleanup levels for diesel range organics, gasoline range organics, and/or benzene. Results from one monitoring well at the South Tank Farm site were above the cleanup level for ethylene dibromide. All other results were either non-detect or below the cleanup level, including all supply well results. Melody Debenham
10/13/2015 Document, Report, or Work plan Review - other Approved final work plan describing decommissioning of USTs 415 and 416 (formerly called USTs 439 and 442). Work planned includes hydrostatic testing of the underground piping associated with the tanks, installing and sampling 10 soil borings around the tanks, collecting soil samples near the piping, vents, dispenser, and loading/unloading rack associated with the tanks, and filling the tanks with pea gravel to permanently close them in place. Melody Debenham
2/8/2017 Update or Other Action USTs 415 and 416 (also identified as USTs 439 and 441) have been permanently closed in place. Soil sampling results were below cleanup levels. Melody Debenham
12/7/2018 Document, Report, or Work plan Review - other DEC approved the Final 2016 Groundwater Monitoring and Data Analysis Report, Fort Greely, Alaska (November 2017). The report provides a summary of the 2016 field activities, site background, analytical results and recommendations for future sampling events at Fort Greely, Alaska (FGA). During the 2016 sampling event, 39 wells were sampled at nine site locations. Of those 39 wells sampled, seven wells contained one or more exceedances of the project action limits for diesel range organics (DRO), ethylene dibromide (EDB), benzene and 1,2,4-trimethylbenzene. The FGA monitoring wells will continue to be sampled. Erica Blake
10/30/2019 Document, Report, or Work plan Review - other DEC approved the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska Final Work Plan (dated October 30, 2019). The purpose of this groundwater monitoring work plan is to guide groundwater sampling activities at selected locations with known or suspected contaminant releases present on Fort Greely, Alaska (FGA). Areas on FGA to be investigated under this work plan are; Robin Road Fuel Spill [Base Realignment and Closure (BRAC) Site 30], Evergreen Road Pipeline Fuel Spill Area (BRAC Site 73), Former Landfills 4 and 5 (BRAC Site 88), BRAC Site 94, BRAC Sites 85N/85S and 133, Tar and Asphalt Disposal Area (TAADA), BRAC Site 92 and 134, Petroleum, oil and lubricant (POL) facility, and South Tank Farm. In addition to collecting groundwater samples and water level measurements, this work plan discusses installation activities for five monitoring wells. The location of these five wells will be provided to DEC in a work plan addendum prior to the spring/summer 2020 work. This work plan describes activities to be conducted fall 2019, and spring/summer 2020. Erica Blake
11/25/2020 Document, Report, or Work plan Review - other DEC approved the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska Final Groundwater Monitoring Report 2019, Fort Greely, Alaska (November 24, 2020). The document describes 2019 groundwater sampling activities conducted on nine Fort Greely sites. Twenty-three monitoring and potable water supply wells were sampled. Long-term monitoring is expected to continue at these nine sites on Fort Greely, Alaska. Erica Blake
12/16/2020 Meeting or Teleconference Held DEC had a teleconference with the Fort Greely Directorate of Public Works (DPW) environmental staff, the U.S. Corp of Engineers, and contractors assisting with the restoration projects to discuss the status of various site cleanup work (specifically discussing sites associated with the Fort Greely Groundwater Monitoring Program). Erica Blake
4/28/2021 Meeting or Teleconference Held DEC staff attended the 2021 Fort Greely Restoration Advisory Board (RAB) meeting in Delta Junction, Alaska at the Delta Junction City Hall. Updates on fieldwork conducted during 2019 and 2020 were presented to community members, RAB members and Fort Greely staff in attendance. Erica Blake
6/8/2021 Document, Report, or Work plan Review - other ADEC provided review comments for the "Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Draft Groundwater Monitoring Report 2020, Fort Greely, Alaska" (dated April 19, 2021) to the U.S. Army. The document discusses results from the 2020 groundwater sampling and includes updated UFP-QAPP pages for the upcoming 2021 field season. Erica Blake
7/19/2021 Document, Report, or Work plan Review - other ADEC provided responses to comments for the Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Draft Groundwater Monitoring Report 2020, Fort Greely, Alaska (dated April 19, 2021) to the U.S. Army. Sites discussed in the document for a recommended No Further Action, ADEC will review site information for closure separately. A redline version of the document was requested for conducting a comment backcheck. Erica Blake
7/30/2021 Document, Report, or Work plan Review - other ADEC provided approval for the "Groundwater Sampling and Environmental Support Services, Fort Greely, Alaska, Final Groundwater Monitoring Report 2020, Fort Greely, Alaska" (dated July 29, 2021) to the U.S. Army. The document includes results from groundwater monitoring activities conducted in 2020, and includes work plan pages describing proposed sampling activities for the upcoming 2021 field season. Erica Blake
9/14/2021 Document, Report, or Work plan Review - other ADEC has provided approval for the "Groundwater Sampling and Environmental Support Services Fort Greely, Alaska Final Work Plan 2021, Fort Greely, Alaska" (dated September 13, 2021) to the U.S. Army. The document includes the final Section 7 Waste Handling (approved April 27, 2021), final updated work plan and UFP-QAPP pages (approved July 30, 2021), and the final Appendix E land use control implementation plan (approved September 14, 2021). All the finalized sections have been compiled in this final work plan describing groundwater monitoring activities and a land use control implementation plan for various sites around Fort Greely. Erica Blake
7/27/2022 Document, Report, or Work plan Review - other ADEC provided review comments for the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Draft Groundwater Monitoring Report 2021, Fort Greely, Alaska (dated June 6, 2022). The document described results from land use control (LUC) inspections, well decommissioning, repair and redevelopment and groundwater sampling activities conducted during the 2021 field season. The document also included updated work plan addendum pages for upcoming 2022 fieldwork. Erica Blake
9/9/2022 Document, Report, or Work plan Review - other ADEC provided responses to comments for the Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Draft Groundwater Monitoring Report 2021, Fort Greely, Alaska (dated June 6, 2022) to the U.S. Army. The document described results from land use control (LUC) inspections, well decommissioning, repair and redevelopment and groundwater sampling activities conducted during the 2021 field season. The document also included updated work plan addendum pages for upcoming 2022 fieldwork. Responses to the review comments were received September 7, 2022. All responses were accepted except for one comment regarding decommissioning a monitoring well at the Tar and Asphalt Disposal Area. A draft-final redline version of the final document was requested for review and comment backcheck prior to ADEC providing any approvals on a final version of the document. Erica Blake
9/20/2022 Document, Report, or Work plan Review - other ADEC provided approval for the "Groundwater Sampling and Environmental Support Services Fort Greely, Alaska, Final Groundwater Monitoring Report 2021, Fort Greely, Alaska" (dated September 16, 2022) to the U.S. Army. Appended to the document were updated work plan pages for the upcoming 2022 field season, and the 2021 land use controls report. ADEC will work with the Army to obtain copies of background studies referenced in the 2021 Groundwater Sampling Report and verify the site boundaries for Landfill #7. With this document approval, the 2022 field work is expected to start September 26, 2022. Erica Blake
12/29/2023 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 78368 POL Yard and Facility. Erica Blake
1/23/2024 Document, Report, or Work plan Review - other DEC provided comments for the "Environmental Summary Report: CCFGLY-002 Building 617 and POL Yard Facility, Fort Greely, Alaska (dated August 14, 2023)" to the U.S. Army. The report summarizes site cleanup and recommends the site be closed with institutional controls (IC's). During review of the document several data gaps were identified. In providing review comments, additional information was requested to assist with DEC's review (boring logs and additional analytical data). Erica Blake
5/10/2024 Document, Report, or Work plan Review - other DEC provided responses to comments for the "Environmental Summary Report: CCFGLY-002 Building 617 and POL Yard Facility, Fort Greely, Alaska, Draft-Final, (dated March 27, 2024) to the U.S. Army. The site is a fuel yard and will remain that way into the foreseeable future. DEC will be able to close the site with institutional controls. The migration to groundwater pathway should be monitored, and controls to mitigate vapor intrusion risks into the buildings onsite need to be put in place. Erica Blake
7/3/2024 Document, Report, or Work plan Review - other The Alaska Department of Environmental Conservation (DEC) has completed the review of the Environmental Summary Report: CCFGLY-002_Building 617 and POL Yard Facility [02341.1082] which details the historical records, environmental investigations, and remedial actions for the building 617 and POL Yard Facility, and to evaluate the extent and magnitude of remaining contamination against the current cleanup standards. All responses to comments have been incorporated or closed out in the final document and are accepted. This document is now approved. Carly Jensen

Contaminant Information

Name Level Description Media Comments
DRO Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil
Benzene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil
Toluene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil
Ethylbenzene Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil
Xylenes (total) Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil

Control Type

Type Details
Land Use Plan / Maps / Base Master Plan In the October 2004 Draft Decision Document Fact Sheets, administrative controls (ACs)were estblished in order to minimize risk to human health and the environment. The site is included in the post’s Geographic Information System (GIS), a tool used in the Dig Permit process for notifying contractors, workers, and base personnel of the potential for contamination to exist at this site.

Requirements

Description Details
Groundwater Use Restrictions The Dig Permit process is used to prevent installation of water production well(s) through the contaminated area 5 year reviews
Excavation / Soil Movement Restrictions Prevent removal of contaminated material from the site to off-base locations or to environmentally sensitive areas 5 year reviews
When Contaminated Soil is Accessible, Remediation Should Occur If future land disturbance activities at the site encounter contamination, the contaminated material encountered will be properly remediated or disposed of in accordance with applicable regulations. 5 year reviews

There are no documents for this site report.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close