Action Date |
Action |
Description |
DEC Staff |
8/20/2004 |
Site Characterization Workplan Approved |
Workplan approved this date. |
Anne Marie Palmieri |
1/28/2005 |
Site Characterization Report Approved |
Report approved. Contamination found at the pad for the former ASTs and under the parking lot where the fueling station used to be. Additional characterization/cleanup needed. |
Anne Marie Palmieri |
2/10/2005 |
Site Added to Database |
DRO concentration in soil reached 23,900mg/kg. |
Bruce Wanstall |
2/10/2005 |
Site Ranked Using the AHRM |
Oil spill volume, surface water usage for drinking water and petroleum contamination of surface water are not determined at this time. Multiple sources for petroleum contamination of soil at the site have been identified. |
Anne Marie Palmieri |
3/21/2005 |
Update or Other Action |
Additional action will occur this summer. |
Anne Marie Palmieri |
7/1/2005 |
Update or Other Action |
Workplan submitted for soil excavation. (Action entered 6/13/08). |
Janice Wiegers |
7/11/2006 |
Update or Other Action |
Approved transport of approx. 800 cy of petroleum contaminated soil from job site to OIT in Fairbanks. This is as per previously approved 2004 workplan; however, work was delayed due to operation and funding issues. |
Mike Jaynes |
6/13/2008 |
Interim Removal Action Approved |
Reviewed Report for Building 107 Soil Excavation submitted by Hart Crowser in August 2006. 900 cubic yards of soil was excavated. Confirmation soil samples were below cleanup levels for BTEX and DRO, except for three samples. The highest DRO contamination remaining was 11,400 mg/kg, which was located beneath an asphalt parking area. Regenox was added to the excavation before backfilling. |
Janice Wiegers |
6/18/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Janice Wiegers |
1/25/2011 |
Conceptual Site Model Submitted |
The CSM identifies indoor air as a potential exposure pathway. Soil vapor sampling is proposed to evalute the potential for exposure. |
Melody Debenham |
5/23/2012 |
Site Visit |
Performed a site visit at the C-Camp Auto Shop site and the C Camp Emergency Services/Fire Management Building site in Denali National Park & Preserve. National Park Service (NPS) staff gave us a tour of the C-Camp sites, sites in the Headquarters area and the Hotel Powerhouse site. At the C-Camp site we observed drilling and soil sampling for the installation of a monitoring well. |
Melody Debenham |
8/14/2012 |
Site Characterization Workplan Approved |
Approved the final soil vapor assessment work plan. Previous investigations show petroleum hydrocarbons reaming in the soil from spills and leaks associated with a former fueling station located adjacent to Building 107. To evaluate the indoor air exposure pathway, the NPS proposes to collect shallow, near-slab soil vapor samples and complete a building survey. |
Melody Debenham |
1/18/2013 |
Site Characterization Report Approved |
Approved the final vapor assessment report describing vapor intrusion assessment activities at Building 107. To evaluate the indoor air exposure pathway, the NPS consultant completed a building survey and installed 4 soil vapor probes to collect shallow, near-slab soil vapor samples. There were 7 compounds detected in the soil vapor samples, none above the target levels for residential or commercial use. |
Melody Debenham |
5/15/2014 |
Site Characterization Workplan Approved |
Approved final soil vapor assessment work plan describing the collection of a second round of sampling from the vapor monitoring points installed at this site in 2012. |
Melody Debenham |
8/15/2014 |
Update or Other Action |
Coordinated with NPS regarding upcoming utility work at site. If contaminated soil is encountered during excavation activities, it may be placed back into excavation at the same location. Site will be repaved at the end of utility work. |
Melody Debenham |
9/30/2014 |
Potentially Responsible Party/State Interest Letter |
Potentially responsible party letter sent to the National Park Service. |
Melody Debenham |
10/22/2014 |
Document, Report, or Work plan Review - other |
Approved Final 2014 Soil Vapor Sampling Report. Soil vapor samples were collected from soil the four vapor probe locations that were installed in 2012. No compounds were detected in any of the samples. |
Melody Debenham |
2/13/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 75080 Diesel spill from ASTs. |
Melody Debenham |
8/31/2017 |
Cleanup Complete Determination Issued |
|
Gretchen Caudill |
8/31/2017 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Gretchen Caudill |
5/30/2018 |
Institutional Control Compliance Review |
IC compliance review conducted. Staff changed from Gretchen Caudill to IC Unit. Closure/IC Details added to reflect the 2017 Decision Document. Reminder system set to follow-up every three years. |
Kristin Thompson |
2/2/2021 |
Institutional Control Compliance Review |
IC compliance review conducted. The NPS remains the property owner. A letter to the landowner was not issued at this time. Site review frequency changed to every five years. |
Evonne Reese |