Action Date |
Action |
Description |
DEC Staff |
6/1/1990 |
Update or Other Action |
In 1990 a decision document was issued by the Air Force that reported a well had been installed downgradient of the site that was sampled three times in 1988 and 1989 with a trace detection of tetrachlorethene in 1988. |
Debra Caillouet |
11/8/2005 |
Update or Other Action |
A comment letter was submitted to the AF regarding the site summaries for 23 IRP sites at Clear.
Site 6 (WP006) is the historic sludge pit associated with the station's sewage treatment plant. The sludge pit has been replaced with a lined dry bed in the same location. No records have been found of soil sampling and analysis for this site. One monitoring well was installed downgradient and sampled three times in the late 1980's. The results showed one low level detection of tetrachloroethene (0.64ìg/L) and one of petroleum hydrocarbons at 14,000 ìg/L, which was attributed to the steel well caseing. The Air Force is proposing to perform a Site Inspection (SI) to determine if metals, chlorinated solvents, polychlorinated biphenyls, diesel range organics (DRO), and gasoline range organics (GRO) have migrated to groundwater. DEC requests that in addition to the groundwater evaluation that the soil surrounding the current lined sludge pit be sampled and analyzed for these potential contaminants as well. The results of the soil sampling would be used to determine if any institutional controls would be needed to prevent risk to human health and the environment. |
Debra Caillouet |
12/1/2005 |
Site Added to Database |
Site added to the database. |
Debra Caillouet |
2/2/2006 |
Update or Other Action |
The Alaska Department of Environmental Conservation received the Draft Preliminary Findings Report Sites 6, 7, and 17 on January 27, 2006. The report describes the results of sampling and analysis from the fieldwork in October 2005 and proposes modifications to the work planned for the spring of 2006 based on the preliminary findings. The following comment on the report for Site 6 was sent to the AF.
Surface soil sampling at Site 6, Abandoned Sludge Pit, detected maximum levels of polychlorinated biphenyls (PCBs) – 183 mg/kg, 4-chloroaniline – 5.7 mg/kg, mercury – 9.9 mg/kg, cadmium – 7.4 mg/kg, lead – 630 mg/kg, selenium – 21 mg/kg, barium – 2600 mg/kg, chromium – 71 mg/kg, silver – 28 mg/kg, and arsenic – 15 mg/kg. The work plan identified one sludge pit for sampling but it appears that the field reconnaissance determined that there are two pits separated by a berm. Please confirm this and clarify in the text.
The recommendations for Site 6 are to collect an additional four surface soil samples in the second sludge pit, three surface soil samples around the current sludge-drying area and to install and sample a monitoring well downgradient of the abandoned sludge pit. DEC requests the addition of subsurface sampling in the abandoned sludge pits to estimate the depth of soil contamination.
|
Debra Caillouet |
5/25/2006 |
Update or Other Action |
A response to comments for the Draft Preliminary Findings Report for Sites 6,7 and 17 indicates that Sites 6 and 17 based on the findings will go to a full Remedial Investigation and a work plan will be prepared for field work in 2007. No additional SI work will occur for Site 6 |
Debra Caillouet |
1/22/2007 |
Update or Other Action |
the project manager and risk assessor provided comment on the draft RI and risk assessment work plan for sites 6 & 17 |
Debra Caillouet |
3/22/2007 |
Exposure Tracking Model Ranking |
|
Debra Caillouet |
3/22/2007 |
Site Characterization Workplan Approved |
The work plan for sites 6 & 17 was approved. |
Debra Caillouet |
1/28/2008 |
Update or Other Action |
The project manager and risk assessor provided comment on the RI report and risk assessment |
Debra Caillouet |
8/19/2008 |
Update or Other Action |
The ADEC received an updated Community Involvement Plan for the
Environmental Restoration Program at Clear Air Force Station. |
Debra Caillouet |
10/2/2008 |
Document, Report, or Work plan Review - other |
comments were sent to the Air Force on the draft Feasibility Study |
Debra Caillouet |
11/19/2008 |
Document, Report, or Work plan Review - other |
Staff provided comment on the ACLs shown in the draft final FS. They need tobe recalculated and submitted for review before adjusting the FS. |
Debra Caillouet |
2/6/2009 |
Document, Report, or Work plan Review - other |
The Final Feasibility Study was approved. |
Debra Caillouet |
6/8/2009 |
Update or Other Action |
Comments were sent to the Air Force on a draft proposed plan. |
Debra Caillouet |
8/12/2009 |
Proposed Plan |
The final proposed plan was approved |
Debra Caillouet |
5/21/2010 |
Document, Report, or Work plan Review - other |
The final 2009 well decommissioning report documents the proper closure of 55 wells throughout the base. It recommends an additional 20 wells be decommissioned. |
Debra Caillouet |
8/24/2010 |
CERCLA ROD Approved |
The final ROD was signed by DEC 5/27/2010 and by the AF 7/23/2010. The remedy is to excavate PCB soil to 25 ppm and then cap the area. LUCs will restrict the site to industrial use. |
Debra Caillouet |
3/22/2011 |
Document, Report, or Work plan Review - other |
Draft Remedial Action Work Plan, Sites 6 and 13, Clear Air Force Station, February 2011 |
Debra Caillouet |
6/14/2011 |
CERCLA Remedial Design/Remedial Action Plan Approved |
Final Remedial Action Work Plan, Sites 6 and 13, Clear Air Force Station, May 2011 |
Debra Caillouet |
1/20/2012 |
Document, Report, or Work plan Review - other |
Draft Remedial Action Report, Sites 6 and 13, Clear Air Force Station, December 2011 |
Debra Caillouet |
10/11/2012 |
Cleanup Complete Determination Issued |
The Final Remedial Action Report, Sites 6 and 13 documents the removal of PCB and lead contaminated soil, the installation of a soil cap and a fence. |
Debra Caillouet |
10/11/2012 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Debra Caillouet |
8/16/2013 |
Document, Report, or Work plan Review - other |
The Final Work Plan/Quality Assurance Project Plan Site WP006, Performance Based Remediation, Clear AFS, August 2013 was not approved. |
Debra Caillouet |
9/10/2013 |
CERCLA Remedial Design/Remedial Action Plan Approved |
Final Work Plan/Quality Assurance Project Plan Site WP006, Performance Based Remediation, Clear AFS, |
Debra Caillouet |
5/22/2014 |
Enforcement Action |
A compliance advisory letter was sent to Weston and AECOM for not following their work plan, for transporting soil in uncovered loads and without ADEC approval for disposal. |
Debra Caillouet |
6/12/2014 |
Site Reopened |
The Air Force has determined that it wants unrestricted use for this site. An Explanation of Significant Difference was signed by ADEC today. |
Debra Caillouet |
8/7/2015 |
Update or Other Action |
Several Reports for this file are at Alaska Archives for storage. I am including the barcodes if you need any pulled from there. Please see list of contents in each box to find what you're looking for before requesting any box retrievals. Thank you Barcode 795756 Box 385 Barcode: 587281 Box 348 587285 Box 352 795754 Box 383 795753 Box 382 795757 Box 386 795755 Box 384 |
Susan Carberry |
8/15/2016 |
Document, Report, or Work plan Review - other |
DEC has completed review of the Draft Final Remedial Action Completion Report, Site WP006, Clear AFS, Alaska, dated July, 2016. |
Monte Garroutte |
10/13/2016 |
CERCLA Remedial Action Completion Report |
DEC approved the Remedial Action Completion Report, Site WP006. The objective of this effort was to remove contaminated soils with concentrations above the
DEC-approved project action limits (PALs). This involved: Removing overburden surface materials from 0-6 ft bgs; removing the soil horizon from 6-8 ft bgs and stockpiling into windrows for further assessment; excavating soil below the 8 ft bgs soil horizon; field screening the excavation for lead; collecting confirmation samples from the excavation base and sidewalls; and decommissioning four groundwater monitoring wells. All contaminated soils above project action limits were removed from the site and monitoring wells were decommissioned in accordance with DEC regulations. Following the removal activities, PCBs were detected at concentrations above the DEC Method Two cleanup level in two Multi-Increment samples collected outside of the WP006 site boundary near the windrow stockpile staging area. A new site inspection was recommended for the stockpile area.
|
Monte Garroutte |
5/1/2017 |
Cleanup Complete Determination Issued |
|
Monte Garroutte |
6/21/2017 |
Institutional Control Record Removed |
Institutional Controls have been removed. |
Monte Garroutte |
6/21/2017 |
Exposure Tracking Model Ranking |
A new updated ranking with ETM has been completed for source area 75146 leachfield. |
Monte Garroutte |
10/22/2021 |
Site Reopened |
Site WP006 has been reopened by USAF. A site investigation is planned to investigate PCB contamination at the former WP006 stockpile and at locations parallel to the railroad track. |
Jamie McKellar |
5/24/2022 |
Site Visit |
On 5/23/2022, Contaminated Sites and Solid Waste staff conducted the annual inspection at Clear Space Force Station. CS staff visited Site SS024 and observed pre-characterization test-pitting in prep for a construction project. Sites WP006, TU026, and AFFF Area #5 were also observed. |
Jamie McKellar |
4/30/2024 |
CERCLA RI Plan Approved |
UFP-QAPP Approved: Final Unified Federal Policy-Quality Assurance Project Plan, Per- and Polyfluoroalkyl Substances Phase I Remedial Investigation at Sites AT029P, AT030P, FT010P-SUB, WP006P-SUB, and SS028P, Clear Space Force Station, Alaska. This document describes the proposed management and field sampling approach to be used during a Phase 1 Remedial Investigation for per- and polyfluoroalkyl substances (PFAS) at the five sites listed above. The United States Air Force (USAF) has committed to conduct the required baseline risk assessment under a separate contract. |
Jamie McKellar |
5/12/2025 |
CERCLA RI Report Approved |
DOCUMENT APPROVED: Post Mobilization (MOB) II Fieldwork Update and Proposed Optimization of the MOB III Fieldwork for the Per- and Polyfluoroalkyl Substances (PFAS) Phase I Remedial Investigation (RI) at Sites AT029P, AT030P, FT010P-SUB, WP006P-SUB, and SS028P at Clear Space Force Station, Alaska. This MOB 2 update proposes to update PSLs based on the January 2025 Memo from the Office of the Assistant Secretary of Defense, and summarizes findings from MOB 2. In its approval, DEC requested a meeting to discuss placement of permanent monitoring wells during MOB 3 and a meeting prior to MOB 4 to discuss MOB 3 results. Finally, DEC requested that USAF submit the MOB 3 update document a minimum of 30 days before MOB 4 is scheduled to begin. |
Jamie McKellar |