Site Report: Chignik Bay City Tank Farm

Site Name: Chignik Bay City Tank Farm
Address: Southern Part of the City of Chignik, Chignik, AK 99564
File Number: 2531.38.003
Hazard ID: 4225
Status: Active
Staff: * Currently Not Assigned, 9072693057 bill.oconnell@alaska.gov
Latitude: 56.292388
Longitude: -158.407042
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

During a site reconnaissance and assessment of rural bulk fuel tank farms, staining and petroleum odors were observed. Limited sampling confirmed soil contamination exceeding ADEC cleanup levels for DRO. The City Tank Farm is scheduled to be replaced.

Action Information

Action Date Action Description DEC Staff
4/21/2006 GIS Position Updated Using Figure 3 from a Site Reconnaissance and Assessment Rural Bulk Fuel Tank Farm Remediation Projects, Chignik, from HartCrowser, dated January 2002, in conjunction with TopoZone Pro, entered the coordinates for this site. Metadata includes USGS Topo Maps 1:63 (AK) Series, on a Medium Size Map, View Scale 1:25,000, Coordinate Datum NAD83. Moderate degree of confidence in accuracy of location. Alyce Hughey
4/21/2006 Site Ranked Using the AHRM Site ranked using the AHRM. Donald Seagren
4/21/2006 Update or Other Action File number 2531.38.003 assigned and entered into the Fileroom Database, and Contaminated Sites Database. Alyce Hughey
4/21/2006 Site Added to Database Site added to the database. Alyce Hughey
5/9/2007 Exposure Tracking Model Ranking Donald Seagren
6/14/2010 Update or Other Action Conversation with Mayor Richard Sharpe. Mr. Sharpe said the tank farm was upgraded in 2002, one year after the site recon report. According to Mr. Sharpe, Bristol Environmental conducted some soil removal, but the report for these activities has not been located. Bill O'Connell
4/5/2013 Meeting or Teleconference Held Spoke with Mayor Sharpe (Chignik) about characterization and remediation at Chignik. The contaminated soil stockpile remains near the landfill, and we've agreed that the ADEC PM will screen and sample the stockpile and City Tank Farm during a site visit in mid-to-late May. Chignik will pay the lab feed directly to SGS. Richard Bernhardt
5/3/2013 Meeting or Teleconference Held Spoke with Becky (?) at the city office (Mayor Sharpe was out of town) and discussed supplies for Chignik to purchase prior to my arrival. I followed up with an e-mail reminder for those supplies. Richard Bernhardt
5/29/2013 Site Visit DEC coordinated with the Lake and Peninsula School District (LPSD) and the Mayor of Chignik and conducted a site visit May 2013. During the site visit, DEC collected soil samples from: a test pit at the Chignik Bay City Tank Farm, a test pit at the Chignik Bay School Quonset Hut, and from the Chignik Bay School stockpile located at the dump. At the Chignik Bay City Tank Farm, soil samples collected at a depth of 1.5 and 3 feet bgs did not contain petroleum constituents above cleanup levels. At the Chignik Bay School Quonset Hut, two soil samples collected 2 feet bgs did not contain petroleum constituents above cleanup levels. At the stockpile, seven soil samples collected 2, 6, and 10 feet into the pile contained DRO up to 2,420 mg/kg. At 6 feet into the pile, strong hydrocarbon odors, stained soil, shotgun shells, and broken clay pigeons were noted. After sampling, the stockpile was spread from 20 feet to 10 feet above ground surface and amendments including fertilizer, nitrate, and sulfate were spread into the pile to promote remediation. Grant Lidren
12/23/2013 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 75192 misc leaks and drums. Joshua Barsis
10/27/2015 Potentially Responsible Party/State Interest Letter Letter sent on this day with site history and request for a work plan by February 1, 2016. Joshua Barsis
7/21/2021 Update or Other Action J. Fix assigned as new Project Manager. Julie Fix

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.