Skip to content Skip to content

Site Report: FIA - Block 3 Lot 12 - Saupe Enterprises

Site Name: FIA - Block 3 Lot 12 - Saupe Enterprises
Address: 6223 Old Airport Road, Fairbanks International Airport, Fairbanks, AK 99701
File Number: 100.38.206
Hazard ID: 4314
Status: Active
Staff: Rebekah Reams, 9074512144 rebekah.reams@alaska.gov
Latitude: 64.822811
Longitude: -147.859151
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Petroleum contamination of the soil and groundwater exists at the site. Chevron operated a bulk fuel facility at the site from 1962 to 1973 which utilized eight aboveground storage tanks. Chevron continued to use the site until 1985 presumably to house and maintain tanker trucks. Contamination is assumed to be from surface spills of aviation gas or Jet fuel.

Action Information

Action Date Action Description DEC Staff
10/17/2006 Site Added to Database Site added to the database. Mitzi Read
12/28/2006 Update or Other Action OIT Certificate of RCRA Exemption forms received from OASIS. Purge water contained 12.2 mg/L DRO, 1.54 mg/L GRO, 0.05 ug/L benzene. Kim DeRuyter
1/16/2007 Update or Other Action Called Kris Dubois to discuss Prospective Purchaser Agreements and the lessee history of the site. Bernie Hall is looking into assuming the lease from Saupe. Chevron has documented their intent to assess and remediate contamination from their former bulk fuel operation which was in operation from 1962 to 1985. FIA has some documentation linking contamination at the adjacent property (Block 13 Lot 15B - Hotfoot International) to Chevron's operation. At this time Chevron has not committed to take on remediation of the Hotfoot site. Kim DeRuyter
1/19/2007 Site Characterization Report Approved Site Characterization report received from FIA. FIA-conducted this site investigation in order to facilitate a property transfer. The report indicates that a large portion of the site has been impacted by surface spills which have migrated to groundwater. The highest soil contamination observed was DRO at 9060 mg/kg, GRO at 5720 mg/kg and benzene at 22.2 mg/kg. PAH and VOC analytes did not exceed cleanup levels with the exception of napthalene which was observed at 27.2 mg/kg in soil boring 9-6-8. However, PQL's were above the cleanup level for some analytes. Groundwater contamination was observed as high as 34.3 mg/L DRO, and 7.25 mg/L GRO. Kim DeRuyter
2/13/2007 Update or Other Action Received a response to the PRP letter from Bernie Saupe. He reports that he used the warehouse as a parking garage for two truck tankers, and two tanker-trailers and the only fuel storage was the buried heating oil tank. He mentions a floor sump which he cleaned out when he took possession of the building. He also mentions that there had been a well on the property which Chevron had removed along with the restroom prior to his taking possession. There is no mention of the location of the former septic system. Kim DeRuyter
2/13/2007 Exposure Tracking Model Ranking Baseline ranking completed based on the January 2007 Oasis final site characterization report. Potential ecological impacts to the Airport Pond should be evaluated. Kim DeRuyter
1/17/2008 Update or Other Action ARCADIS BBL submited the 2007 Assessment report for the Former Chevron Facility #309152, Saupe Enterprises Site. The Site Assessment results show that groundwater and soil are impacted near wells MW1 to MW4 located northeast of the building. Samples from MW3 had the highest concentrations. LNAPL was observed in wells MW3 and MW4 in August and Nov. A workplan for delineation of LNAPL and impacted groundwater will be prepared for the 2008 field season. Tamara Cardona-Marek
2/25/2008 Update or Other Action ADEC received the ARCADIS Workplan for Monitoring Well Installation. The plan proposes to add five monitoring wells to further delineate the extent of the groundwater contamination. Tamara Cardona-Marek
7/1/2008 Update or Other Action ADEC received the Petroleum Hydrocarbon Fingerprinting Results for Former Chevron Facility 309152 (Saupe Enterprises Site). Tamara Cardona-Marek
7/10/2008 Update or Other Action ADEC received the First Quarter 2008 Groundwater Monitoring Report for the FIA Saupe Entreprises site. Impacted groundwater was found in the vicinity of wells MW1-MW-4. Measurable LNAPL was observed in wells MW2,MW3,and MW4. Additional groundwater delineation will take place during the summer 2008. Tamara Cardona-Marek
7/11/2008 Meeting or Teleconference Held Met with Dan Carrier (Chevron) and Greg Montgomery (Arcadis) to discuss current activities at the site and plans to do additional assessment. ADEC suggested using temporary wells along the adjacent road to determine if product is originating from an upgradient source, ARCADIS will install a monitoring well at this moment and determine the need for temporary wells based on the results obtained from this well. ADEC also requested sampling the porewater adjacent to the pond. Tamara Cardona-Marek
9/19/2008 Update or Other Action Approved disposal of contaminated soil resulting from well installation and identified post-treatment analysis for ASR facility. Tamara Cardona-Marek
3/13/2009 Meeting or Teleconference Held ADEC discussed with Arcadis and Chevron the status of the site on 3/3/2009. ADEC requested additional characterization north of MW-6 and east of MW-9. Chevron will do additional groundwater gauging to determine the need for more characterization, as requested by DEC. Piezometers will be installed along the pond during the 2009 field season. Semi-annual sampling will take place in 2009. Tamara Cardona-Marek
7/14/2009 Document, Report, or Work plan Review - other DEC received the Work Plan for Additional Assessment for the Formet Chevron Facility 309152. Additional site assessment activities consist of piezometer installation, surface water gauge installation, soil and groundwater sampling, and storm water culvert sampling. Tamara Cardona-Marek
7/29/2009 Site Visit Piezometers installed near pond. Original proposed depth was not reached due to sloughing. Chevron project manager on site. Tamara Cardona-Marek
9/3/2009 Update or Other Action Current site lessee will install a grey water tank at the site. Tank will be installed in the vicinity of MW-10 and disposal of excavated soil will be coordinated with Arcadis. Tamara Cardona-Marek
10/29/2009 Document, Report, or Work plan Review - other DEC received and reviewed the First Semi-Annual 2009 Groundwater Monitoring Report from Arcadis. LNAPL was present in wells MW-1 through MW-4, MW-6, MW-9 and RW-1. MW-8 was inaccesible. DRO was above cleanup levels in MW-7. Benzene was above cleanup levels in MW-5, MW-8 and MW-10. EDB, MTBE and PAH's were not above cleanup levels in any of the samples. Geochemical parameters were collected in groundwater also. Tamara Cardona-Marek
2/2/2010 Document, Report, or Work plan Review - other DEC received and reviewed the Second Semi Annual 2009 Groundwater Monitoring Report. LNAPL was detected in wells MW1, MW2, MW3, MW4, MW6 and MW9. These wells were not sampled. Contaminants above cleanup levels in remaining wells inluded GRO (up to 12,100 ppb), DRO (up to 5670 ppb), benzene (up to 240ppb) and EDB (2.76 ppb). Wells MW-5, MW-10 and MW-11 had no contaminants above cleanup levels. Piezometers installed adjacent to pond were not sampled during this sampling event. MNA parameters were measured in wells without free product. No conclusions were made based on the small amount of MNA data. Tamara Cardona-Marek
2/17/2010 Meeting or Teleconference Held DEC met with Arcadis and Chevron to discuss activities for the site in 2010. Additional plume delineation will be performed by adding 3 monitoring wells. One of these wells will be located on the Hotfoot property. The eco scoping guidance will be used to evaluate potential ecological impacts to the pond adjacent to the site. Sediment and surface water will be collected from the pond in 2010. A work plan will be submitted prior to all work. Tamara Cardona-Marek
6/29/2010 Update or Other Action Site lessee plans to install a greywater tank on site. Installation is being coordinated with Chevron and Arcadis to make sure that any excavated soil is screened and contaminated soil is treated appropriately. Tamara Cardona-Marek
8/13/2010 Document, Report, or Work plan Review - other DEC received and commented on workplan for additional plume delineation and eco evaluation to assess impacts of contamination into the airport pond. Tamara Cardona-Marek
8/26/2010 Site Visit Staff visited the site while addiitonal monitoring wells were installed and to meet with UAF, Chevron, and Arcadis to discuss the use of the site for a research study on phyto-remediation. Tamara Cardona-Marek
9/30/2010 Offsite Soil or Groundwater Disposal Approved Request for transport and disposal at ASR of investigative derived waste approved. Tamara Cardona-Marek
10/11/2010 Document, Report, or Work plan Review - other DEC received the First Semi-Annual 2010 Groundwater Monitoring Report. Concentrations of DRO and GRO are consistent with prior monitoring events. LNAPL present in MW-3, MW-4, MW-9 and RW-1. Sampled for sulfolane with no detections. Tamara Cardona-Marek
7/1/2011 Document, Report, or Work plan Review - other DEC received and reviewed the 2011 Work Plan for Additional Assessment submitted by Arcadis. Plan proposes to install and sample 14 soil borings installed with a hand auger to a depth of 8 feet to assess shallow soils. Tamara Cardona-Marek
7/28/2011 Site Characterization Report Approved 2011 Work Plan for Additional Assessment is approved. Tamara Cardona-Marek
9/14/2011 Document, Report, or Work plan Review - other DEC received and reviewed the 2010 Site Assessment Report and the 2011 First Semi-Annual Groundwater Monitoring Report. Results for the site assessment indicate free product is found across the road on the well located southeast of the site (MW-12) This is due to the nature of the groundwater gradient (flat). Site assessment also revealed highest contamination on surface soil samples collected at a depth of 2 ft, confirming that contamination is due to spills from the historic above ground storage tanks. Tamara Cardona-Marek
12/21/2011 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 75293 Former AST Bulk Fuel Taks & Distribution Sys. . Tamara Cardona-Marek
12/28/2011 Site Characterization Report Approved DEC received and reviewed the 2011 Site Assessment submitted by Arcadis. Report indicates that contaminants are found in the surface soil at depths as shallow as 1.5-2 feet, consistent with spills from above ground storage tanks. DEC has requested that Chevron submits a cleanup plan to remediate and/or mitigate contamination posing current risks to human health and the environment. Tamara Cardona-Marek
1/9/2012 Document, Report, or Work plan Review - other DEC received and reviewed the Second Semi Annual 2011 Groundwater Monitoring Report. GRO, DRO and benzene exceeded the cleanup levels in wells MW-7, MW-8 and MW-12. Ethylbenzene also exceeded cleanup levels in MW-12. LNAPL was found in wells MW-1 through MW-4, MW-6, MW-9 and RW-1. Tamara Cardona-Marek
6/19/2012 Document, Report, or Work plan Review - other DEC received and reviewed the 2012 Groundwater Monitoring Workplan from Arcadis. Tamara Cardona-Marek
7/30/2012 Document, Report, or Work plan Review - other DEC received and reviewed the Work Plan for LNAPL Mobility Assessment. Tamara Cardona-Marek
8/28/2012 Meeting or Teleconference Held DEC met with Chevron and Arcadis to discuss actions for 2012-2013. An updated conceptual site model will be submitted that addresses exposure pathways and how they will be remediated or controlled. This will comprise the cleanup plan that is expected to be submitted in the Fall of 2012. Use of dataloggers was suggested for this site to obtain a year -round trend. Tamara Cardona-Marek
9/7/2012 Document, Report, or Work plan Review - other DEC received and reviewed the First Semi Annual 2012 Groundwater Monitoring Report from Arcadis. Results are consistent with previous monitoring events. No trends documented in the conclusions. Several wells contained free product. Tamara Cardona-Marek
4/29/2013 Meeting or Teleconference Held DEC, Arcadis, and Chevron met to discuss the status of several Fairbanks area Chevron sites. Arcadis will install more wells at FIA Saupe to delineate the extent of the plume to the northeast. Dataloggers will be installed in monitoring wells to monitor the water levels over a longer period of time to get a better idea of the groundwater gradient and how it changes seasonally. Fingerprinting results indicate that the LNAPL on site is a mix of Aviation gas and jet fuel. Active remediation will likely include soil removal in the upper 2 feet around SB-1 and SB-2, followed by air sparging and soil vapor extraction (AS/SVE) to target the GRO and BTEX fraction of the contamination, and MNA for DRO. Upcoming reports will include an updated CSM, trend analyses, and a LNAPL mobility assessment. Robert Burgess
6/6/2013 Update or Other Action Site symbol visually adjusted using ArcGIS and satellite imagery. Robert Burgess
6/10/2013 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 75293 Former AST Bulk Fuel Taks & Distribution Sys. . Robert Burgess
6/13/2013 Site Visit Site visit to observe groundwater sampling. Sampling for VOCs (incl. EDB), BTEX, and DRO was conducted with hydrasleeves. Robert Burgess
7/17/2013 Site Characterization Workplan Approved 2013 Work Plan for Additional Assessment approved with modifications. ARCADIS proposed to install several soil borings to further delineate the vertical and horizontal extent of soil contamination to the northwest of Lot 12 (on lots 15A and B, the former Hotfoot building; file #100.26.102) and to characterize the vertical extent of soil contamination near MW-8. Modifications required by DEC include increasing the depth of initial borings from 8 to 10 feet (14 feet if high PID at 10ft) because previous reports document no impacts above 8 ft. DEC also recommended to follow up this work with the installation of new monitoring wells during this field season. Email chain including plan modifications is documented in the site file. Robert Burgess
7/23/2013 Site Visit DEC conducted a site visit to observe soil sampling via hand augering (0-8 ft) and geoprobe (8-20 ft). Field screening and soil sampling was conducted by qualified personnel following the approved workplan. Previous geotechnical surveys had detected anomalies, one of which was beneath a planned boring location. At this location (and others), refusal was encountered before the boring was completed, but the reason for refusal was unclear. Chevron plans to use a vacuum truck for further investigation and to complete borings. Robert Burgess
8/14/2013 Site Characterization Workplan Approved DEC approved an addendum to the 2013 Work Plan for Additional Assessment. Borings that were unable to be completed will be investigated with a vacuum truck to the water table or to 8 feet below ground surface, and completed, if possible, by hollow stem auger. Soil samples will be collected, field screened and sampled. Two downgradient wells may be installed depending on field screening results. Robert Burgess
8/19/2013 Site Visit DEC project manager conducted a site visit to observe completion of borings via vacuum truck that were previously not able to be hand augered and for utility clearance. Soil samples were also taken at intervals via a hand auger. After leaving the site, received notification that a corrugated metal tank and some type of conduit were discovered at 3.5 feet in one boring that was being completed over an anomaly previously detected during a geophysical survey. Robert Burgess
8/21/2013 Site Visit DEC project manager visited the site to watch the installation of monitoring wells and completion of soil borings. Robert Burgess
2/13/2014 Document, Report, or Work plan Review - other DEC reviewed the Second Semi-annual 2013 Groundwater Monitoring Report. LNAPL was present in several wells; LNAPL and analytical data were generally consistent with historical sampling results, as was the groundwater gradient. Robert Burgess
5/12/2014 Site Visit DEC project manager visited the site to observe installation of soil borings and monitoring wells and associated sampling activities. Robert Burgess
5/14/2014 Meeting or Teleconference Held DEC met with Chevron and ARCADIS to discuss the status of several Fairbanks area Chevron sites. Work from the 2013 field season indicated that the extent of floating product was greater than previously thought. Field work for the 2014 field season is underway and is targeted at complete delineation of product. When product is delineated, Chevron will begin work on a remedial system design to target low molecular weight, volatile fuel components. Robert Burgess
2/27/2015 Document, Report, or Work plan Review - other DEC reviewed the 2015 Cleanup Plan describing excavation of contaminated surface soil and the installation of an air sparge/soil vapor extraction (AS/SVE) system to target volatile organic contaminants and gasoline range organics and the use of institutional controls to prevent exposure at the site. Robert Burgess
4/9/2015 Site Characterization Workplan Approved DEC reviewed and approved the 2015 Work Plan for Additional Site Assessment. The work plan describes additional soil borings intended to delineate the extent of surface soil contamination in preparation for remedial excavation as proposed in the 2014 Cleanup Plan. Robert Burgess
7/10/2015 Document, Report, or Work plan Review - other DEC reviewed the first semi-annual 2015 Groundwater Monitoring Report. LNAPL was present in several wells, consistent with historical data. The dissolved phase plume remains similar in concentrations compared to past events. Robert Burgess
1/11/2016 Document, Report, or Work plan Review - other DEC reviewed the Second Semi-annual 2015 Monitoring Report. Contamination is relatively consistent with past monitoring events, with LNAPL present in several wells as well as dissolved fuels and benzene. Remediation planning is still underway. Robert Burgess
10/6/2016 Meeting or Teleconference Held Meeting with RP and consultant on multiple Chevron sites to discuss current site status and upcoming site action. Shawn Tisdell
1/23/2018 Meeting or Teleconference Held DEC staff met with DOT staff to discuss general coordination of contaminated site issues regarding leased properties at the Fairbanks International Airport and specific site information including cleanup activity status and upcoming work or proposed state action. Shawn Tisdell
6/5/2018 Document, Report, or Work plan Review - other DEC received a report titled "2018 Air Sparge and Soil Vapor Extraction Well Installation Work Plan" This proposed work plan outlines phase one of a three phase work scope. Phase I includes the installation of the air sparge/soil vapor extraction (AS/SVE) wells and is scheduled for the summer of 2018. Shawn Tisdell
6/12/2018 Meeting or Teleconference Held Meeting held with RP and consultants to discuss site progress and outline future site action. Shawn Tisdell
7/2/2018 Document, Report, or Work plan Review - other "2018 Air Sparge and Soil Vapor Extraction Well Installation Work Plan" reviewed and approved. System installation scheduled to begin 7/9/2018 Shawn Tisdell
8/30/2018 Offsite Soil or Groundwater Disposal Approved Transport approval provided for 9 CY of contaminated soil and 460 gal of water removed during the installation of monitoring wells on the site. Shawn Tisdell
11/8/2018 Meeting or Teleconference Held DEC staff met with Chevron and ARCADIS representatives to determine site status and discuss the path forward for multiple sites. Chevron is in the process of transferring site managers from GHD to ARCADIS. Shawn Tisdell
3/12/2019 Meeting or Teleconference Held DEC and DOT staff met to discuss progress and potential future cleanup action at this site. Shawn Tisdell
5/3/2019 Document, Report, or Work plan Review - other The DEC has determined that the work plan submitted for this site does not meet the minimum requirements as defined in DEC guidance and has requested that it be revised. Shawn Tisdell
7/3/2019 Document, Report, or Work plan Review - other DEC received Second Semi-annual 2018 Groundwater Monitoring Report which will be under review. Report conclusion indicates that the analytical results, groundwater elevations, flow direction, and gradient from the second 2018 semiannual groundwater monitoring events are generally consistent with historical trends. Shawn Tisdell
8/9/2019 Meeting or Teleconference Held DEC staff met with Arcadis and Chevron representatives to discuss the current status and upcoming site cleanup goals for this site. Shawn Tisdell
10/17/2019 Site Characterization Workplan Approved Approval to excavate shallow soil (provided 10/9/2019) and install air sparge wells as outlined in the 2019 Shallow Soil Excavation and System Installation Work Plan was provided by the department. ADEC comments have been submitted to the RP requesting additional details or clarifications to the portion of the work plan detailing installation of the air sparge and soil vapor extraction system. Shawn Tisdell
10/17/2019 Site Visit Site visit to observe groundwater sampling event and shallow soil removal activities. Shawn Tisdell
11/4/2019 Offsite Soil or Groundwater Disposal Approved Agency approval to dispose of nine 55-gallon drums (495 gallons) of waste water and twelve supersacks (12 cubic yards) of contaminated soil. the soil will be disposed at Organic incineration Technology, Inc. in Moose Creek, AK and the waste water will be disposed by NRC Alaska LLC at Arlington, Oregon. Shawn Tisdell
11/7/2019 Meeting or Teleconference Held DEC staff met with Arcadis staff to discuss the site and determine cleanup goals for the site. Shawn Tisdell
8/21/2020 Document, Report, or Work plan Review - other DEC staff reviewed 2020 Remedial action plan which outlines the third phase of preparation of mitigation system installation. This work includes system mobilization, installation, startup and monitoring of the soil vapor extraction (SVE) and air sparge (AS) system. To avoid potentially mobilizing free product, the AS portion of the system will only be operated after free product has been reduced and approval is provided by the DEC. Work associated with Phase I and Phase II, included installation of the air sparge and soil vapor extraction wells and a limited excavation of impacted surface soil, has been completed. Shawn Tisdell
9/23/2020 Offsite Soil or Groundwater Disposal Approved An estimated 10 cubic yards of potentially impacted surface soil will be excavated in preparation for installation of a concrete slab for the mitigation system building. Contaminants of concern are GRO, DRO, EDB, BTEX, and PFAS. THe soil will be transported to the Organic Incineration Technology. Inc. facility in Moose Creek, AK. Shawn Tisdell
11/6/2020 Update or Other Action A concrete slab was installed directly on the proposed location where the AS/SVE building will be installed. The location was level, so soil excavation was deemed not necessary. No potentially impacted soil that may have required treatment,was excavated. Shawn Tisdell
1/15/2021 Meeting or Teleconference Held DEC staff met with Chevron Environmental Management Company (CEMC) and Arcadis to discuss Chevron sites located in Alaska during the Annual Portfolio Meeting on January 14th and 15th, 2021. Rebekah Reams
5/11/2021 Document, Report, or Work plan Review - other DEC provided a comment letter requesting additional information regarding site groundwater monitoring reports, including additional information on investigation derived waste management, groundwater gradient, and discussion of headspace present in analytical samples collected during the 2019 Second Semi-Annual Groundwater Monitoring event. Rebekah Reams
8/9/2021 Document, Report, or Work plan Review - other DEC provided comments on the Site Groundwater Monitoring Work Plan. This work plan proposes to establish semi-annual groundwater sampling of site monitoring wells. Rebekah Reams
8/10/2021 Document, Report, or Work plan Review - other DEC provided comments on the Work Plan for Additional Assessment. This work plan proposes to advance three groundwater monitoring wells to further define the extent of contamination downgradient of the site. Rebekah Reams
10/14/2021 Cleanup Plan Approved DEC approved the Remedial Action Plan with addendum following comment resolution. This plan proposes the remedial design, installation, and operation of a soil vapor extraction system at the site. Rebekah Reams
10/14/2021 Document, Report, or Work plan Review - other DEC reviewed the final version of the Field Summary Report – 2018 and 2019 with addendum which documents the installation of Air Sparge (AS) and Soil Vapor Extraction (SVE) wells and the excavation of surface soil completed in 2018 and 2019. Rebekah Reams
12/14/2021 Exposure Tracking Model Ranking A new updated ranking with ETM has been completed for source area 75293 Former AST Bulk Fuel Taks & Distribution Sys. . Rebekah Reams
2/16/2022 Document, Report, or Work plan Review - other DEC approved the Addendum to the Work Plan for Additional Assessment submitted on December 8, 2021. This work plan proposes to advance additional groundwater monitoring wells to further define the extent of contamination downgradient of the site. Rebekah Reams
2/16/2022 Document, Report, or Work plan Review - other DEC approved the Addendum to the Site Groundwater Monitoring Work Plan submitted on December 8, 2021. This work plan establishes semi-annual groundwater sampling of monitoring wells at the site. Rebekah Reams
10/7/2022 Offsite Soil or Groundwater Disposal Approved DEC approved transport of 1,000 lbs of purge and decontamination water and 12,000 lbs of soil cuttings generated in November 2021 and September 2022. Rebekah Reams
2/21/2023 Document, Report, or Work plan Review - other DEC received the 2022 Well Installation Report which documents the installation of monitoring wells MW-22, MW-23, and MW-24 downgradient of the site. Following a preliminary review of the report, ADEC provided concurrence with the recommendations outlined in Section 8, which propose a work plan be submitted to define the downgradient groundwater impacts by installing additional monitoring wells within accessible areas of the adjacent property northwest of the site. Rebekah Reams
6/26/2023 Document, Report, or Work plan Review - other ADEC approved the Additional Offsite Delineation Work Plan following comment resolution. This work plan proposes to advance additional soil borings and groundwater monitoring wells to further define the extent of contamination downgradient of the site. Rebekah Reams
7/17/2023 Long Term Monitoring Workplan or Report Review ADEC approved the Groundwater Assessment and Well Installation Work Plan - Revision 1 following comment resolution. This work plan proposes to decommission damaged monitoring wells MW-8 and MW-19 if they cannot be repaired, replace monitoring well MW-8, and update the analytes included in the groundwater monitoring plan. Rebekah Reams

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details
Hazard ID Site Name File Number
25457 FIA - Sitewide 100.38.079
23131 FIA - Hotfoot - Blk 3 Lots 15a & b 100.26.102

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close