Skip to content Skip to content

Site Report: Egegik Icicle Seafoods Spills

Site Name: Egegik Icicle Seafoods Spills
Address: 1 Cannery Road, Egegik, AK 99579
File Number: 2543.38.002
Hazard ID: 4378
Status: Active
Staff: Stacee Henderson, 9072628202 stacee.henderson@alaska.gov
Latitude: 58.215546
Longitude: -157.375732
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

A release of approximately 50 to 100 gallons of diesel #2 fuel occurred from a day tank near the Freezer plant on June 30, 2005. Contaminated soil was immediately excavated and stockpiled for landfarming. In 2007 a report from BGES indicated that the freezer plant diesel tank had numerous overfills throughout the years resulting in contaminated surface soil. A leak was observed at the bulk fuel storage tank farm located upgradient during the summer of 2006. On July 19, 2006 a release of 200 gallons diesel occurred at the generator building. Contamination at the generator building includes historic bunker C. On June 11, 2008 a release of about 100 gallons at the Mechanic's building was reported to ADEC. Soil from all three spill areas is being landfarmed off site.

Action Information

Action Date Action Description DEC Staff
4/10/2007 Site Added to Database Site added to the database. Mitzi Read
5/23/2007 Update or Other Action On July 19, 2006, DEC was notified of a spill at the Generator Day Tank. Icicle Seafoods estimated that 200 gallons of diesel fuel spilled onto the ground underneath the generator building. In addition, stressed vegetation and staining were noted near the diesel tank farm. Todd Blessing
6/13/2007 Exposure Tracking Model Ranking Initial ranking. Todd Blessing
6/15/2007 Potentially Responsible Party/State Interest Letter CSP noted in a letter dated, June 15, 2007, that Icicle Seafoods is liable for CSP oversight of three pollution incidents. At this time, CSP requests that BGES issue a cleanup plan to CSP that defines the means and methods to treat soil and/or groundwater that has adversely been impacted from recent spills. Todd Blessing
6/11/2008 Update or Other Action DEC was notified that a spill occured at the Mechanics Shop. Over 100 gallons of fuel was spilled. Icicle Seafoods is excavating soil from the spill area and stockpilling it in the landfarm area for treatment. Todd Blessing
6/16/2008 Update or Other Action DEC staff reviewed a 2007 Hydrocarbon Remediation Report. BGES documented the removal of the day tank In the area of the Freezer Plant, which is located at the top of the bluff. The day tank has been repeatedly overfilled with diesel fuel. The last known spill was in 2005 and estimated to have been approximately 50 to 100 gallons. BGES estimated that approximately 106 gallons of fuel have been recovered since that time. In 2006, Icicle reported a release of approximately 200 gallons of diesel fuel at the Generator Building. Approximately 150 gallons were recovered with sorbent materials and hand digging immediately after the release. During 2007, approximately 4 to 7 inches of accessible impacted soils were removed from underneath and adjacent to the Generator Building, for a total of 6.8 cubic yards of soil transported to the land-farm. After removing these soils (excluding the areas of the apparent Bunker C), the soils appeared dark black. Excavation attempts were made in the area of a trench that was created in 2006 to capture fuel floating on the surface on the ground. After removing approximately 4 inches of soil, it was apparent that the Bunker C contamination extended further northeast than originally anticipated. Bunker C contamination was observed underneath the stairs of the Generator Building, at 5 inches below grade. It appears that the Bunker C contamination extends approximately 41 feet northwest from the Bunker C secondary containment tank. All of the impacted soils that were above the Bunker C were removed by hand shoveling in the area of the stairs of the Generator Building. Although the lateral and vertical extent of the contamination had not been delineated. Near the Generator Building, two confirmation samples were collected to characterize a portion of the remaining soils. The sample collected underneath the valve of the original fuel release, indicated that the soils were greatly impacted 7 inches below grade with DRO (43,700 mg/Kg). Another sample, which was collected approximately 8 feet south of the first sample, in soils that bordered the fresh diesel release and the Bunker C contamination, indicated that these soils were also impacted with DRO at 104,000 mg/Kg. If the Generator Building is demolished in the future, BGES recommended removing the impacted soils in this area and transporting the soils to the land-farm. A new bladder is anticipated to be installed by Icicle in the concrete secondary containment area beneath the diesel tanks in 2007. BGES recommended that after the new tank farm bladder is installed, or during the process of installation, excavation of the previously identified impacted soils at the northeast side of the diesel tank farm be performed. Todd Blessing
7/10/2008 Update or Other Action DEC staff has completed a review of a 2008 Petroleum Hydrocarbon Remediation Work Plan. This work plan was prepared by BGES Inc. and received at DEC’s Anchorage Office on April 30, 2008. BGES proposes to do the following in August 2008: • Excavate contaminated soils from the tank farm area and collect confirmation soil samples; • Treat and sample contaminated soils at the landfarm area; and • Prepare a report of the remedial actions DEC staff issued a letter on July 10, 2008 approving of the work plan under the following conditions: 1. BGES will screen, sample and treat potentially contaminated soil in accordance with 18 AAC 78 and 18 AAC 75 regulations. 2. BGES will sample the excavation pit at the mechanics shop in accordance with 18 AAC 78 regulations to determine if all contaminated soil has been removed. 3. BGES will modify their sampling frequency of landfarmed soil (in accordance with 18 AAC 78 regulations) to accommodate the increase in soil volume from the disposal of contaminated soil that was excavated from the mechanics shop. Todd Blessing
7/28/2008 Update or Other Action DEC reviewed and approved an amendment to 2008 remediation work plan. BGES proposed to sample and analyze the excavation pit at the Mechanics' Housing spill area by selecting descrete sampling points based on field screening values. Soil will be field screened with photoionizing detector and confirmatory samples will be collected at a rate of 3 for the first 250 square feet, and one additional sample for each additional 250 square feet. The samples will be analyzed for DRO/RRO and BTEX. If confirmatory results suggest the excavation pit is still contaminated, additional excavation will be initiated until laboratory samples confirm clean soil is left in place. Todd Blessing
5/14/2009 Document, Report, or Work plan Review - other DEC staff reviewed BGES' "2008 Petroleum Hydrocarbon Remediation Report", which was recieved at DEC's Anchorage office on May 8, 2009. Contaminated soil was removed from adjacent to the Mechanics Bunkhouse and from underneath the former tank farm and transported to the landfarm area. Eight cubic yards was removed from the northeast side of the former tank farm. A total of 43 cubic yards was removed from adjacent to the Mechanics Bunkhouse resulting from the 2008 day tank spill. Three confirmation samples were collected from the contaminated area at the former tank farm and no contaminants of concern were detected above DEC cleanup criteria. Todd Blessing
5/19/2009 Update or Other Action DEC staff completed a review of BGES, Inc’s “Icicle Seafoods Inc. Egegik Alaska 2008 Petroleum Hydrocarbon Remediation Report". Within the report, BGES Inc. (BGES) documented soil cleanup activities at the Icicle Seafoods Processing Facility that were not WAFCO’s responsibility due to fuel releases since June 30, 2005. BGES recommended that no further cleanup work would be required for the following spills: Tank Farm area, Mechanics Housing area, Generator Building, and Freezer Building day tank. DEC issued a letter on May 19, 2009 commenting on this report and concurred with BGES recommendations for no further work at the Mechanics Housing area, Generator Building, and Freezer Building day tank since the amount of fuel recovered from cleanup activities equaled or exceeded the estimated amount of fuel spilled. The amount of fuel spilled at the tank farm however, was not known and groundwater contamination in this area suggested their is still soil contamination that has not been addressed. Todd Blessing
7/27/2009 Site Characterization Workplan Approved DEC staff has completed a review of the BGES, Inc.’s “2009 Site Assessment and Remediation Work Plan”, which was received at DEC’s Anchorage Office On July 21, 2009. BGES proposed to do the following during the summer and fall of 2009: 1. Collection of groundwater samples from monitoring well MW-12 to be analyzed for GRO, DRO, BTEX, and RRO; 2. Tilling of landfarmed soil at least twice; 3. Collection of soil samples from the landfarmed area (twice for the first 50 cubic yards of soil and one sample per each additional 50 cubic yards) to be analyzed for GRO, DRO, BTEX, and RRO; and 4. Preparation of a brief sampling and analysis report DEC approved of the work plan in a letter dated July 27, 2009. Todd Blessing
5/5/2011 Update or Other Action DEC staff reviewed BGES Inc.’s “2009 Site Assessment and Remediation Activities Report, Icicle Seafoods, Inc. Facility, Egegik, Alaska”, Dated April 29, 2010. The report discusses the evaluation of groundwater contamination near the tank farm area and the results of soil testing of contaminated soil in the landfarm area. In August 2009, groundwater samples were collected from monitoring well MW-12 to be analyzed for contaminants of concern which included GRO, DRO, RRO, and BTEX. In these samples, DRO and RRO were the only contaminants of concern detected and these analytes were not detected above DEC groundwater cleanup criteria. During the summer of 2010 this well was again sampled and no contaminants of concern were detected above DEC groundwater cleanup criteria. BGES reported that during 2009 the landfarm area was only tilled once and that nutrients were not applied to landfarmed soil. In August 2009, BGES collected three soil samples from the landfarmed area. which were tested for GRO, DRO, RRO, and BTEX. Each of the soil samples were collected from near the center of the landfarm area and from an approximate depth of 0.5 feet below ground surface. In these samples, DRO and GRO were measured at levels exceeding DEC migration to groundwater cleanup criteria. DRO levels ranged from 339 to 3,970 mg/kg, and GRO ranged from 0.48 to 520 mg/kg. BGES reported that the landfarm area was only tilled once during the summer of 2009. Todd Blessing
2/2/2012 Update or Other Action DEC staff received a letter from Margaret deGravelle in which she discussed the activities conducted at the facility. On May 14, the circulation pump began operation. On May 26, the soil in the landfarm was tilled, On May 27, urea fertilizer was applied. On August 12, the soil was tilled again and on August 18, the silt was removed from the discharge end of the recirculation system. On September 18, the circulation pump was shut down following the end of the field season. Todd Blessing
2/9/2012 Update or Other Action DEC staff recieved a letter from Margaret deGravelle in which she discussed the activities conducted at the facility. On May 14, the circulation pump began operation. On May 26, the soil in the landfarm was tilled, On May 27, urea fertilizer was applied. On August 12, the soil was tilled again and on August 18, the silt was removed from the discharge end of the recirculation system. On September 18, the circulation pump was shut down following the end of the field season. Todd Blessing
6/11/2013 Site Characterization Workplan Approved Reviewed and approved March 2013 work plan by BGES for turning and mixing the landfarmed soil and collecting confirmation multi incremental samples from the two landfarmed areas. Jacob Gano
1/21/2015 Update or Other Action DEC staff reviewed the Annual Soil Remediation Project Updates for 2012, 2013, and 2014. In 2012, The trench circulation pump was active from the end of May until the end of September. The landfarm was tilled once. In 2013, the trench circulation was active from June until the end of September. The landfarm was tilled twice and urea fertilizer was applied once. According to the summary, multi-increment sampling was also conducted. In 2014, the trench circulation pump was active from the end of April until the beginning of October. Soil was tilled and fertilized with urea fertilizer once. Lisa Krebs-Barsis
4/10/2015 Document, Report, or Work plan Review - other Reviewed the 2013 Land-Farm Monitoring Activities Report. The land farm was sampled as two separate decision units, ICLF-DU1 (38 cubic yards excavated from 2005 to 2007) and ICLF-DU2 (51 cubic yards excavated in 2008). The consultant conducted multi-increment sampling (MI). One sample was collected for ICLF-DU1. One sample, a duplicate, and triplicate were collected for ICLF-DU2. Diesel range organics (DRO) analytical results for ICLF-DU1 and ICLF-DU2 exceeded cleanup levels at 254 mg/Kg and 869 mg/Kg, respectively. ADEC will request another round of MI sampling in 2016 per the consultant's recommendations. Lisa Krebs-Barsis
6/16/2016 Meeting or Teleconference Held Teleconference with Icicle Seafoods representative was held to discuss the current status and future path forward on two sites in Egegik. Immediate actions for source removal have been completed. Both sites are in remediation phase through in situ bioremediation. The last sampling of landfarm soils occurred in 2013. Icicle Seafoods representative requested to resume monitoring in 2017 to give the landfarm soils more time to remediate. There are no other immediate concerns and the extension for monitoring was granted. Darren Mulkey
11/2/2018 Update or Other Action Received 2018 project update from Icicle Seafoods. Landfarm was tilled during 2018 and treated with urea. No sampling was conducted. Landfarm has been closed for winter and will resume operation in spring 2019. Erin Gleason
11/6/2018 Update or Other Action Per the 11/6/2018 ADEC email, Icicle will submit a project update by Nov 15th of every year detailing what actions occurred at the landfarm, photographs of the landfarm, and any preliminary sampling. Once Icicle anticipates the landfarm is near cleanup levels, the QEP will sample the landfarm and prepare recommendations for decommissioning. Erin Gleason
11/6/2018 Meeting or Teleconference Held ADEC and Icicle had phone meeting to discuss next steps for site. The landfarm will continue to be tilled in summer 2019 and treated with urea. Icicle will submit a project update in the fall. ADEC and Icicle discussed possibility of closure with ICs once landfarming was complete. Erin Gleason
7/25/2019 Site Characterization Workplan Approved Received landfarm work plan from Shannon and Wilson on behalf of Icicle Seafood on 7/23/2019. ADEC has reviewed the work plan and it is now approved. Erin Gleason
10/30/2019 Meeting or Teleconference Held Phone meeting with Shannon and Wilson to discuss next actions for landfarm. Erin Gleason
11/4/2019 Site Characterization Report Approved Received landfarm report from Shannon and Wilson on 10/21/2019. ADEC has reviewed the report and requests that some changes and additions be made by 11/15/2019. Revised report received by ADEC on 11/4/2019. The report is now approved. The report shows that the landfarm was covered by tall grass, had no berms, one sign, and no defined edge. In addition sampling indicated contaminants of concerns exceed ADEC cleanup levels in the landfarming area and below the landfarm. ADEC request that a work plan be submitted to bring the landfarm into compliance with 18 AAC75.360 by 1/15/2020 Erin Gleason
1/28/2020 Update or Other Action Work plan deadline extend 45 days per request of Icicle Seafoods. Work plan is due March 13th, 2020. Erin Gleason
4/8/2020 Document, Report, or Work plan Review - other Received work plan from Shannon and Wilson on behalf of Icicle Seafoods on3/26/2020. ADEC has reviewed the work plan and request some revisions. Electronic letter sent to Icicle on this date. Erin Gleason
4/28/2020 Meeting or Teleconference Held Teleconference held today with ADEC, Shannon and Wilson, and Icicle Seafoods to discuss work plan revisions, overall site closure pathway, and how to proceed forward on the site during the covid-19 pandemic. Erin Gleason
2/24/2022 Meeting or Teleconference Held Meeting with Shannon and Wilson to discuss work plan revisions and how to move forward with waste characterization discovered in 2019 at the land farm and a limited removal action (LRA) to dispose of some land farm soil. Shannon and Wilson are planning to conduct work during April and August 2022. Naomi Mason
4/1/2022 Site Characterization Workplan Approved Received revised landfarm work plan from Shannon and Wilson (S&W) on behalf of Icicle Seafood on 3/11/2022. ADEC has reviewed the work plan and it is now approved. Field work anticipated for April and August 2022. Naomi Mason
11/9/2022 Document, Report, or Work plan Review - other ADEC received the Icicle Seafoods Egegik Cannery 2022 Soil Landfarm Activities report on 10/26/2022 from Shannon & Wilson on behalf of Icicle. ADEC has reviewed the report and requests revisions. Naomi Mason
11/14/2022 Site Characterization Report Approved ADEC received the revised 2022 Soil Landfarm Activities Icicle Seafoods Egegik Cannery Landfarm report on this date. Report was approved on 11/15/2022. Sampling activities consisted of reestablishing landfarm boundaries by measuring the area, collecting GPS coordinates, taking swing tie locations, and installing orange snow fencing along the perimeter of the landfarm. Additionally, one soil sample was taken from the area of stained soil observed in 2019, revealing DRO, arsenic, and naphthalene above DEC cleanup levels. A total of 36 soil samples were taken from the landfarm area, revealing DRO exceedances in 26 of the 36 samples. Overall, DRO concentrations in the landfarm ranged from 24.9 mg/kg to 1,650 mg/kg. Icicle intends on sampling the landfarm again in 2025. Naomi Mason

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close