Site Report: King Salmon AS GWZ 2 SA043 Drum Storage Area 4

Site Name: King Salmon AS GWZ 2 SA043 Drum Storage Area 4
Address: SA043, Groundwater Zone 2 (OT28), King Salmon, AK 99613
File Number: 2569.38.016.08
Hazard ID: 4516
Status: Active
Staff: Ginna Quesada, 9074515960 ginna.quesada@alaska.gov
Latitude: 58.689453
Longitude: -156.650036
Horizontal Datum:NAD83

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

The site is a drum storage area of unknown contents during active instalation times. The site consists of the drum storage area and a large trench with standing water in it. Two smaller trenches are also present within the site boundaries. A member of the Chugach Support Services indicated that the trenches were used as borrow pits. No drums were located in the drum storage area during the site inspection, however, nine crushed drums were found in the alders 150 feet east of the fence surrounding the missile storage area. No sediment or surface water samples were collected from the trenches. One soil sample was collected from beneath one of the drums found in the alders and returned RRO , 4,4' DDT , and benzo(b)flouranthene detections below cleanup levels. Additional sampling may need to be conducted to confirm that no exceedances are in the water and sediment in the trenches. Also, more comprehensive sampling may be required in the area of the drums found in the alders. AF point of contact: Charley Peyton, Project Manager, 611th CES/CEV 10471 20th Street Suite 338, Elmendorf AFB, AK 99506-2270; Telephone 907-552-9765.

Action Information

Action Date Action Description DEC Staff
12/6/2007 Site Added to Database Site added to the database. Mitzi Read
12/11/2007 Update or Other Action ADEC staff issued a letter to the 611th CES explaining the need for additional site inspection sampling to achieve closure at sites DA033, DA035, SA06 and SA043. Jonathan Schick
2/20/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Jonathan Schick
10/21/2008 Site Visit ADEC staff took part in a site visit to a number of pertinent sites at King Salmon Air Station over a 2 day visit. Sites, especially the pending Multi Site Inspection sites, were inspected for any visible evidence of contamination and potential sampling locations as the work plans are still being formulated. ADEC staff was accompanied to all of the sites by the Project managers from the USAF and thier contractors. A Restoration Advisory Board meeting was held during the site visit. The topics discussed included the most recent basewide monitoring program, a discussion of the Multi-SIte inspection project, an update on the status of the Groundwater Zone 5 Records of Decision, and a brief discussion concerning the TCE treatibility Study in Groundwater Zone 1. The next RAB meeting has been tentatively scheduled for April 21, 2009. Jonathan Schick
1/30/2009 Update or Other Action ADEC Staff recieved a copy of the Work plan, Field Sampling Plan, and Quality Assurrance Project Plan for the Mulit-Site Inspection at King Salmon. The Work Plan is dated January 27, 2009. The Field Sampling Plan and the Quality Assurance Project Plan are dated January 16, 2009. Jonathan Schick
4/21/2009 Update or Other Action ADEC staff conducted a site visit to pertinent sites at King Salmon Air Station over a 2 day visit. Sites were inspected for any visible evidence of contamination and to become more familiar with the layout and topography of the area. ADEC staff was accompanied to all of the sites by the Project manager from the USAF and thier contractors. A Restoration Advisory Board meeting was held during the site visit. The topics discussed included the most recent basewide monitoring program, a discussion of the Multi-Site inspection project which is entering Phase II this summer, an update on the status of the Groundwater Zone 5 Records of Decision, and a brief discussion concerning the TCE treatibility Study in Groundwater Zone 1. The next RAB meeting has been tentatively scheduled for October, 2009. Jonathan Schick
10/26/2009 Site Visit ADEC staff traveled to King Salmon with the new RPM for the King Salmon Air Station to tour the sites and look at the excavations that were completed during the 2009 field season. Several sites were inspected and overall the sites appeared to be secured with orange snow fencing and visqueen covering the stockpiles to prevent ponding and migration of contaminants. While in King Salmon staff attended and participated in a Restoration Advisory Board Meeting to meet with the public of King Salmon and discuss the results from the latest round of base-wide sampling and to discuss the progress of the excavations that were conducted during the summer. Jonathan Schick
3/23/2010 Update or Other Action ADEC staff recieved a copy of the Draft Report for Mulitple Site Inspections which included reports from additional site investigatins at Sites DA031, DA034, SA036, DA037, SA039, SA043, and SA006. Work was performed by Paug-Vik and its subcontractors under the Environmental Restoration Program for the US Air Force. Jonathan Schick
1/28/2011 Update or Other Action Received Final "Multi-Site Inspection Report at KSAS" from US Air Force. Neither soil or ground water contamination was identified. Drum removal for aesthetic reasons was identified as a possible recommendation. Guy Warren
12/6/2012 CERCLA Proposed Plan Submit comments to US Air Force on the Proposed Plan for DA031, DA034, and SA043. Comments were editorial in nature. Guy Warren
3/26/2013 CERCLA Proposed Plan Receive final Proposed Plan for site DA031, DA034 and SA043. A public meeting RAB will be held in April to discuss the proposed plan for these sites and to receive input from the affected public. Remedy for SA043 is to remove drums from the areas of concern. Guy Warren
4/22/2013 Site Visit Attend public meeting to discuss Proposed Plan for site DA031, DA034 and SA043. Guy Warren
8/22/2013 Update or Other Action Received Draft Decision Document for DA031, DA034, and SA043. Submit comments requesting modification to the text of the document. Remedy for SA043 is to remove drums from the areas of concern. Guy Warren
10/31/2016 Update or Other Action ADEC sent a letter requesting additional action on nine sites within the King Salmon Divert. SA043 was included requesting the ROD be finalized and implemented. Holly Weiss-Racine
5/15/2018 Document, Report, or Work plan Review - other ADEC approves the 'Final 2017 Five-Year Review, King Salmon Divert, Naknek Recreation Camp I, Naknek Recreation Camp II, Alaska, November 2017' in a letter dated May 15, 2018. Land Use Controls have not been fully implemented at any groundwater zones at King Salmon Divert. Recommendations include: finalizing the decision document for Zone 7, determine the extent of drinking water wells at Lake Camp (number of wells, depth of wells, and groundwater gradient), and fully implement LUCs by updating public land records for non-USAF owned properties. The next five-year review will be completed in 2022. Sammi Castle
5/18/2023 Site Visit DEC conducted a site visit with the U.S. Air Force. Ginna Quesada

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

No associated sites were found.