Action Date |
Action |
Description |
DEC Staff |
7/15/2001 |
Update or Other Action |
West Sak River State B-10 final Report submitted by URS |
Grant Lidren |
5/13/2002 |
Update or Other Action |
Final Cleanup Report for West Sak River State B-10 dated 4/25/2002 submitted by ConocoPhillips and recieved by ADEC on this date. |
Grant Lidren |
3/18/2003 |
Update or Other Action |
West Sak River State B-10 Gravel Pad Investigation dated 12/9/2002 submitted be USR and recieved by ADEC on this date. |
Grant Lidren |
3/18/2003 |
Update or Other Action |
Rehabilitation plan for west sak B10, Kuparuk Oilfield, Alaska dated 3/7/2003 submitted by ABR and recieved by the ADEC on this date |
Grant Lidren |
11/30/2003 |
Update or Other Action |
On May 22, 2009, ADEC received Rehabilitation of West Sak B10 Exploratory Well Site 2003 Progress Report, submitted by ADR. Inc., dated November 30, 2003 |
Grant Lidren |
3/15/2005 |
Update or Other Action |
On May 22, 2009, ADEC received Rehabilitation of West Sak B10 Exploratory Well Site 2004 Progress Report, submitted by ADR. Inc., dated March 2005 |
Grant Lidren |
1/29/2008 |
Site Added to Database |
Site added to the database. |
Mitzi Read |
1/29/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Grant Lidren |
6/10/2009 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Grant Lidren |
6/10/2009 |
Cleanup Complete Determination Issued |
There may be contamination remaining above established cleanup levels at West Sak River State B-10, but ADEC has determined there is no unacceptable risk to human health or the environment, and this site will be granted a Cleanup Complete- Institutional Controls Determination subject to the following: 1.Any future change in land use may impact the exposure assumptions cited in this document. If land use and/or ownership changes, current ICs may not be protective and ADEC may require additional remediation and/or ICs. Therefore ConocoPhillips shall report to ADEC concurrent with the reporting schedule for rehabilitation outlined in the Rehabilitation Plan dated July 2001 (with subsequent updates) or as soon as ConocoPhillips becomes aware of any change in land ownership and/or use, if earlier. The report should include any changes in land use and visual observations of sheen, thermokarsting, or other disturbances. The report can be sent to the ADEC project manager or electronically to DEC.ICUnit@alaska.gov. 2.A Notice of Residual Contamination will be recorded on the ADEC database to document that there is contamination remaining on site above the most stringent ADEC cleanup levels. 3.Any proposal to transport soil or groundwater off site requires ADEC approval in accordance with 18 AAC 75.325(i). 4.Movement or use of potentially contaminated soil in a manner that results in a violation of 18 AAC 70 water quality standards is unlawful. This determination is in accordance with 18 AAC 75.380(d) and does not preclude ADEC from requiring additional assessment and/or cleanup action if future information indicates that this site may pose an unacceptable risk to human health or the environment.
|
Grant Lidren |
7/22/2009 |
Update or Other Action |
ADEC received signed CC-IC agreement |
Grant Lidren |
6/13/2012 |
Update or Other Action |
Staff changed from Grant Lidren to IC Unit. |
Kristin Thompson |
7/9/2012 |
Institutional Control Compliance Review |
IC review conducted and additional details added to the reminder system record. |
Evonne Reese |
7/29/2014 |
Institutional Control Update |
An IC reminder letter was issued to the responsible party on this date. |
Kristin Thompson |
12/4/2014 |
Update or Other Action |
Staff name changed from IC Unit to McLoone. |
Evonne Reese |
9/28/2016 |
Update or Other Action |
At this time, the project manager chooses to retain management of this site which has institutional controls. |
IC Unit |
4/3/2017 |
Document, Report, or Work plan Review - other |
Reviewed the Rehabilitation of West Sak B-10 Exploratory Well Site, dated March 2017. A rehabilitation summary was provided, along with information from the most recent 2016 monitoring event. In summary, all performance standards have been met for the capped reserve pit, the former gravel pad, and the former reserve pit and flare pit berms. At this time, rehabilitation of West Sak B-10 is considered complete, and no further treatment or monitoring is planned. |
Joshua Barsis |
2/3/2021 |
Institutional Control Compliance Review |
IC compliance review started. A combined letter for all ConocoPhillips sites with ICs will be issued in early 2021 and land use will be verified. |
Evonne Reese |
5/30/2024 |
Institutional Control Compliance Review |
IC compliance review completed on this date. An IC reminder letter was e-mailed to the landowner. The next review will be in five years’ time. |
Gaige Robinson |
12/2/2024 |
Institutional Control Compliance Review |
The landowner responded to the IC reminder letter and provided a written confirmation that land use has not changed |
Gaige Robinson |