Site Report: USCG Kodiak Site 10 Air Station

Site Name: USCG Kodiak Site 10 Air Station
Address: Cape Spencer Street, Womens Bay, Kodiak, AK 99619
File Number: 2601.38.020
Hazard ID: 490
Status: Active
Staff: Curtis Dunkin, 9072693053 curtis.dunkin@alaska.gov
Latitude: 57.735958
Longitude: -152.504560
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Contaminated soil and GW resulting from releases of JP-5 in 1987 and 1992. Petroleum compounds also detected in adjacent marine waters and sediments. Elevated metals concentrations were detected in marine waters. The metals concentrations were not correlated with the petroleum constituents and non-petroleum source has not been identified. Another spill, 92250109901, had an LC of 14929960. Last staff assigned was Patrick-Riley, Seagren, Brownlee.

Action Information

Action Date Action Description DEC Staff
9/12/1994 Update or Other Action EPA submits technical comments on draft RFI/CMS reports. Donald Seagren
2/15/1995 Update or Other Action Final RFI/CMS Report, Volume 5, Site 10 submitted to EPA and ADEC. Donald Seagren
11/6/1995 Update or Other Action RFI Contaminant Characterization Study submitted. This study is specific to Hangar 2 which is designated Site 19. Donald Seagren
11/13/1995 Site Added to Database Releases of JP-5. Kent Patrick-Riley
11/13/1995 Site Ranked Using the AHRM Initial ranking. Medium Priority. Kent Patrick-Riley
12/6/1995 Site Characterization Workplan Approved ADEC comments on Contaminant Characterization Study. Concurs with proposed approach of establishing a comprehensive investigative/ corrective action approach under Site 10. Kent Patrick-Riley
8/20/1996 Update or Other Action Draft RFI/CMS Work Plan for Site 10 and Site 11 submitted to EPA and ADEC. Donald Seagren
9/17/1996 Update or Other Action EPA provides technical review comments of Draft RFI/CMS Study Work Plan. Donald Seagren
10/16/1996 Update or Other Action USCG provides responses to EPA's technical review comments on drat RFI/CMS study work plan. Donald Seagren
5/9/1997 Update or Other Action Summary Data Report Sites 10/11 submitted. Donald Seagren
5/19/1997 Update or Other Action USCG submit proposal to close 2 USTs near hangar 1 under State UST regulations with NFA status. Final site cleanup will be conducted under RCRA consent order. Donald Seagren
6/15/1997 Update or Other Action EPA provides technical comments on review of Summary Data Report, Sites 10/11. Donald Seagren
6/17/1997 Update or Other Action Closure of 2 USTs under State UST regulations with final corrective action to be conducted under RCRA Consent Order. Paul Horwath
6/23/1997 Update or Other Action Summary Data Report Site 10 and 11 submitted to EPA and ADEC. Donald Seagren
7/25/1997 Update or Other Action Draft Supplemental Work Plan for CMS of Site 10 submitted to EPA and ADEC. Donald Seagren
8/5/1997 Update or Other Action USCG provides response to EPA technical review of Summary Data Report, Sites 10/11. Donald Seagren
9/25/1997 Update or Other Action EPA provides conditional approval of Draft Supplemental Work Plan for the Corrective Measures Study for Site 10. Donald Seagren
6/5/1998 Update or Other Action EPA provides technical comments on Draft Supplemental Work Plan for the SMS, Site 10. Donald Seagren
7/7/1998 Update or Other Action USCG submits response to EPA technical review comments work plan for CMS Site 10. Donald Seagren
7/23/1998 Update or Other Action Final Supplemental Work Plan for CMS of Site 10 submitted to EPA and ADEC. Donald Seagren
10/17/2001 Update or Other Action Completed review of Sites 10/11 Final CMS/Risk Assessment/Bioremediation Feasibility Study. Agree with conclusions and recommendations. Awaiting review an comments from EPA. Donald Seagren
7/19/2002 Record of Decision 10X rule ROD signed by Frechione. Donald Seagren
8/20/2002 Update or Other Action Reviewed EPA comments on Site 10/11 CMS. Donald Seagren
11/18/2002 Update or Other Action Provide review comments on draft Work Plan for Flow Monitoring and Environmental Sampling to Support Storm water Management. Donald Seagren
11/19/2002 Update or Other Action Provide review comments on Draft Interim Action Work Plan. Donald Seagren
2/6/2003 Update or Other Action USCG Kodiak N-21 Transfer Site, Reckey 1994250117206 is now being worked as USCG Kodiak Site 10-Air Station, Reckey 1988250131564. DB Administrator deleted USCG Kodiak N-21 Transfer Site. Donald Seagren
9/24/2003 Update or Other Action Reviewed draft Quarterly Report for Flow Monitoring, Environmental Sampling, and Product Recovey Results USCG ISC Kodiak, Site 10/11 dated 12 September 03 Donald Seagren
6/16/2004 Update or Other Action File number assigned and entered into the Fileroom DB and CS DB. Alyce Hughey
4/21/2005 Update or Other Action Contaminated Sites staff reviewed a Summary Report for work done during 2004 at Sites 10/11 on the Coast Guard base in Kodiak. Two large JP-5 spills in 1987 and 1992 caused free product on groundwater. The site is a large asphalt covered tarmac for helicopter and plane activity at the base and is adjacent to Woman’s Bay. A free product recovery system was installed in the months after the initial spill became known. 118,000-gallons of free product have been recovered, most in the first couple years after each spill. Currently the recovery systems are passive and the detection of free product in wells is intermittent. Continued groundwater monitoring is planned. It appears that the risk assessment may need to be re-evaluated for recreational fisher people and ecological pathways. Impacts to the bay currently appear to be below surface water criteria although exceedences have been measured during storm events Jeff Brownlee
1/22/2009 Meeting or Teleconference Held Contaminated Sites staff participated with the Corps of Engineers in a Kodiak Island Borough Assembly meeting and a public open house to discuss Formerly Used Defense Sites on Kodiak Island. An update was provided on sites currently being worked on including Drury Gulch, Buskin Beach, Airport Staging Area, and Building A-711 Jeff Brownlee
3/22/2017 Document, Report, or Work plan Review - other ADEC reviewed the draft 2017 C130JLOX Construction Project Environmental Management Plan and submitted review comments to the U.S. Coast Guard. Curtis Dunkin
12/1/2017 Cleanup Plan Approved ADEC received and reviewed several submittals of responses to comments from the U.S. Coast Guard and participated in several technical planning and resolution meetings with representatives from the USCG, EPA, and their respective contracted technical support for the revised draft final 2017 C130JLOX Construction Environmental Work Plan. ADEC received a copy of the final EMP and submitted approval to the USCG for the plan to be implemented in the field. Curtis Dunkin
9/14/2018 Document, Report, or Work plan Review - other ADEC reviewed the draft 2018 Hangar 1 Fire Protection System Construction Work Plan and submitted comments to the U.S. Coast Guard. Curtis Dunkin
9/27/2018 Site Visit ADEC's project manager for the Kodiak USCG contaminated sites traveled to Kodiak, AK and participated in a day-long annual planning meeting and conducted site inspections with project delivery team representatives from the USCG and Environmental Protection Agency. Curtis Dunkin
11/28/2018 Document, Report, or Work plan Review - other ADEC received and reviewed the USCG's responses to comments on the draft 2018 Hangar 1 FPS Construction Work Plan. ADEC participated in multiple rounds of response resolution and technical planning meetings with representatives from the USCG, EPA, and their respective technical planning teams and submitted approvals of the final responses and for the USCG to finalize the document and implement the work plan in the field. Curtis Dunkin
5/14/2019 Document, Report, or Work plan Review - other ADEC reviewed the draft 2019 Sites 10 and 11 Corrective Measures Investigation Work Plan and submitted comments to the US Coast Guard. Curtis Dunkin
6/3/2019 CERCLA RI Plan Approved ADEC received and reviewed responses to comments and revised redline documents from the US Coast Guard for the draft 2019 Sites 10 and 11 Corrective Measures Investigation Work Plan. ADEC completed its review of the responses and redline documents and submitted determinations and approval to the USCG to finalize the documents and to implement the plan in the field. Curtis Dunkin
7/10/2019 Meeting or Teleconference Held ADEC traveled to Seattle, WA and participated in two days of technical planning and project status update and prioritization meetings with representatives from the US Coast Guard, US Environmental Protection Agency, and their respective contracted technical support. Curtis Dunkin
7/23/2019 Document, Report, or Work plan Review - other ADEC reviewed the draft 2019 USCG Kodiak Hangar 1 Fire Protection System Construction Project Environmental Management Plan and submitted comments to the USCG. Curtis Dunkin
8/8/2019 Document, Report, or Work plan Review - other ADEC received responses to comments (RTCs) and revised redline documents for the draft 2019 Air Station Hangar 1 Fire System Construction Environmental Management Plan (EMP). ADEC completed its review of the RTCs and revised redline EMP documents, participated in a comment resolution with the project team, and submitted review determinations and approvals to the USCG to finalize the document and implement the EMP in the field. Curtis Dunkin
8/22/2019 Site Visit ADEC traveled to the USCG Base Station, Kodiak and participated in two full days (August 21-22, 2019) of site inspections and technical project team meetings with representatives from the EPA, USCG, and their respective contracted technical support. Curtis Dunkin
9/5/2019 Document, Report, or Work plan Review - other ADEC reviewed the draft 2019 Fuel Systems Deficiencies Replacement Environmental Management Plan (EMP) and submitted comments to the USCG. Curtis Dunkin
9/27/2019 Document, Report, or Work plan Review - other ADEC participated in a technical planning meeting to resolve responses to comments for the draft 2019 Fuel Systems Deficiencies Replacement Environmental Management Plan with representatives from EPA, the USCG, and its contracted technical support. Curtis Dunkin
12/20/2019 Document, Report, or Work plan Review - other ADEC reviewed the revised, post-technical resolution responses to comments (RTCs), revised design drawings, and the revised final 2019 Fuel Systems Deficiencies Replacement Environmental Management Plan (EMP), and submitted approvals of RTCs and a conditional approval for the final EMP to the USCG. Curtis Dunkin
4/23/2020 Offsite Soil or Groundwater Disposal Approved ADEC reviewed and submitted transport approvals to the USCG and its contracted technical implementation teams for the transport and disposal of IDW that was generated as a result of the 2019 Sites 10/11 Remedial Investigation and the 2019 Hangar 1 Fire Suppression Line Construction Project. Curtis Dunkin
7/21/2020 Document, Report, or Work plan Review - other DEC provided review comments for the draft Corrective Measures Implementation Report, Solid Waste Management Unit/Site 10/11 – Air Station/Paint Storage Area, RCRA Permit AK9690330742, Base Kodiak, USCG, December 2019. The purpose of the activities summarized in this CMI Report was to determine the current concentrations of contaminants in soil, groundwater, and surface water; evaluate the effectiveness and status of the current selected remedy (Section 6.1); and determine the appropriate path forward for the site, including considering potential revisions to the remedy and defining the data quality objectives associated with those remedy components and long-term management of the site. Dennis Shepard
7/22/2020 Meeting or Teleconference Held ADEC participated in annual project prioritization meetings on July 21 and 22 with representatives from the US Coast Guard, the Environmental Protection Agency, and respective contracted project technical support and implementation teams. The purpose of the annual meetings are for stakeholders to provide respective site status updates, conduct technical planning and site prioritization, and scheduling for implementation of projects through the current and upcoming fiscal years. Curtis Dunkin
12/15/2020 Document, Report, or Work plan Review - other ADEC reviewed the draft 2020 Storis Drive Pre-Construction Site Investigation Report and the draft 2020 Storis Drive Construction Environmental Management Plan and submitted comments to the U.S. Coast Guard. The project will involve multiple phases implemented over several years across multiple sites that are adjacent to Inner Womens Bay. Curtis Dunkin
4/1/2021 Document, Report, or Work plan Review - other ADEC reviewed the responses to comments as well as the redline and revised draft documents for the draft 2020-21 Storis Drive Waterline Replacement Environmental Management Plan. ADEC submitted review determinations and additional comments to the USCG, including conditional approval for the USCG to finalize the document; conditional that the USCG develop and submit additional detailed work plans for regulatory review and approval which are more specific to the contaminated site management concerns within the specified areas of concern that will be specific to each of the three separate phases of the project. Curtis Dunkin
7/28/2021 Document, Report, or Work plan Review - other ADEC reviewed the draft 2021 Base Kodiak Monitoring Well Decommissioning Work Plan and submitted comments to the USCG. Curtis Dunkin
8/3/2021 Site Visit ADEC participated in annual project delivery team meetings at the USCG Base Kodiak with representatives from the USCG, EPA, and their respective contracted technical support representatives, and conducted site visits and inspections of the active USCG Kodiak sites. Curtis Dunkin
1/28/2022 Document, Report, or Work plan Review - other ADEC reviewed the responses to comments and the redline revised draft final 2022 Monitoring Well Decommissioning Work Plan and submitted review determinations and approvals to the USCG to finalize the document and and implement the work plan in the field. Curtis Dunkin
3/26/2022 Document, Report, or Work plan Review - other ADEC reviewed the revised draft 2022 USCG Storis Waterline Construction Environmental Management Plan and submitted comments to the USCG. Curtis Dunkin
4/8/2022 Document, Report, or Work plan Review - other ADEC issued final approval to the USCG for the final 2022 Kodiak Storis Waterline Construction Environmental Management Plan. Curtis Dunkin
7/15/2022 Document, Report, or Work plan Review - other ADEC reviewed the draft 2022 Building N1 Air Station Site Investigation Work Plan and submitted comments to the U.S. Coast Guard. Curtis Dunkin
7/21/2022 Document, Report, or Work plan Review - other ADEC reviewed responses to comments for the draft 2022 Building N1 Site Investigation Work Plan and submitted review determinations and approval to finalize the plan to the U.S. Coast Guard. Curtis Dunkin
8/16/2022 Document, Report, or Work plan Review - other ADEC received and reviewed the final 2022 Building N1 Site Investigation Work Plan and submitted a final approval letter to the U.S. Coast Guard. Curtis Dunkin
9/13/2022 Meeting or Teleconference Held ADEC participated in two full days of annual project delivery team meetings with representatives from the USCG, EPA, and their respective contracted technical support staff. Curtis Dunkin
4/4/2023 Document, Report, or Work plan Review - other ADEC reviewed the responses to comments for the draft 2022 Sites 10 and 11 RCRA Corrective Measures Implementation Monitoring Report and submitted review determinations and additional comments to the U.S. Coast Guard. Curtis Dunkin
2/1/2024 Document, Report, or Work plan Review - other ADEC reviewed the revised final 2024 Building N1 Environmental Management Plan and Dewatering Plan and submitted final approval of the document and for the plans to be implemented in the field to the U.S. Coast Guard. Curtis Dunkin
4/22/2024 Site Visit ADEC staff conducted 4 full days of site visits and inspections of all active contaminated sites located on USCG Base Kodiak during the week of April 22, 2024 including comprehensive site walks, land use and site condition evaluations, and in-situ inspections and observations of field work implementation; including multiple ADEC-approved site characterization and cleanup removal action efforts at multiple sites across the Base. Curtis Dunkin
6/26/2024 CERCLA PA ADEC reviewed the draft 2024 Base USCG Kodiak PFAS Preliminary Assessment (PA) Report and submitted comments to the U.S. Coast Guard. The draft PA effort evaluated both confirmed as well as potential historical AFFF use and/or release locations across the contiguous USCG Base Kodiak as well as other adjacent USCG properties. The report also ranked the inventory of sites and proposed future actions and investigation efforts. Curtis Dunkin
8/26/2024 Meeting or Teleconference Held ADEC staff participated in 3 days of annual project delivery team planning and prioritization meetings in Seattle, WA at the EPA Region 10 Headquarters with stakeholders from the U.S. Coast Guard, EPA-RCRA, and ADEC. Curtis Dunkin
11/1/2024 Site Characterization Workplan Approved ADEC reviewed the draft 2024 Hangar 3 Site Investigation Work Plan and submitted approval to the USCG to finalize the document and implement the plan in the field. Curtis Dunkin
12/18/2024 Document, Report, or Work plan Review - other ADEC reviewed the draft 2024 USCG Kodiak OPC/FRC Homeport Environmental Management Plan and submitted comments to the U.S. Coast Guard. Curtis Dunkin
3/27/2025 Document, Report, or Work plan Review - other ADEC reviewed the draft final 2024-25 Nationwide U.S. Coast Guard PFAS Site Inspection Quality Assurance Work Plan and the draft 2025 Base Kodiak PFAS Site Inspection Quality Assurance Work Plan and submitted comments to the U.S. Coast Guard. Curtis Dunkin
4/23/2025 CERCLA RI Plan Approved ADEC reviewed the responses to comments along with the revised draft final 2024-25 Nationwide U.S. Coast Guard PFAS Site Inspection Quality Assurance Work Plan and the revised draft final 2025 Base Kodiak PFAS Site Inspection Quality Assurance Work Plan and submitted accepted review determinations and approvals to the U.S. Coast Guard to finalize the documents and to implement the plans in the field. Curtis Dunkin
5/6/2025 Site Visit ADEC staff traveled to Kodiak and conducted two full days of site visits with U.S. Coast Guard staff and their contracted technical support team for evaluations and technical planning in support of the 2025 Base Kodiak PFAS Site Inspection Work Plan that is planned for implementation later in 2025. Curtis Dunkin
5/9/2025 Document, Report, or Work plan Review - other ADEC reviewed the draft 2024-25 Barracks-Windrider Phase II Utilities Construction Contaminated Materials Management Plan (CMMP) and submitted comments to the U.S. Coast Guard. The CMMP is intended to support the development of a prospective Environmental Management Plan for the replacement of the utilities network that runs through and adjacent to the Site 3 Former Laundry site. Curtis Dunkin
6/20/2025 Document, Report, or Work plan Review - other ADEC received and reviewed the final Waste Management Plan for Kodiak Building N1 Utilities project, within the USCG Kodiak Site 10 Air Station. Silvija Kreilis
8/20/2025 Document, Report, or Work plan Review - other ADEC submitted comments for the final Waste Management Plan for Kodiak Building N1 Utilities project, within the area of USCG Kodiak Site 10 Air Station. Silvija Kreilis
9/9/2025 Site Visit ADEC staff conducted site inspections at 17 active contaminated sites across Base Kodiak in support of ADEC's oversight of the U.S. Guard's ongoing and future planned construction and restoration projects. Curtis Dunkin
9/17/2025 Meeting or Teleconference Held ADEC staff traveled to Seattle, WA to participate in two full days of annual Project Delivery Team meetings with representatives from the U.S. Coast Guard and EPA-RCRA to discuss the status and planned work updates and project prioritization and implementation schedules for the 2025-26 fiscal years. Curtis Dunkin
11/25/2025 Offsite Soil or Groundwater Disposal Approved ADEC reviewed the Contaminated Media Transport and Treatment or Disposal Form and the supporting laboratory analytical waste characterization reports for seventy 55-gallon drums of PFAS-contaminated soil and water investigative derived wastes that were generated from implementation of the 2025 USCG Kodiak Base-wide PFAS Site Inspection Work Plan at multiple locations and areas of concern within and outside of the continuous Base Kodiak. ADEC submitted approval to the U.S. Coast Guard to conduct offsite transport to and disposal of the wastes at the Clean Harbors Grassy Mountain Landfill Facility located in Aragonite, UT. Curtis Dunkin
1/8/2026 Meeting or Teleconference Held ADEC staff participated in the monthly January 2026 Base Kodiak Construction Project Delivery Team planning meeting with the U.S. Coast Guard. Curtis Dunkin
1/28/2026 Document, Report, or Work plan Review - other ADEC submitted approval the final Waste Management Plan for Kodiak Building N1 Utilities project, within the USCG Kodiak Site 10 Air Station. Silvija Kreilis

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close