Skip to content Skip to content

Site Report: Gold King Creek RRS

Site Name: Gold King Creek RRS
Address: ~37 Miles ESE of Clear, Clear, AK 99704
File Number: 150.38.029
Hazard ID: 561
Status: Active
Staff: Jennifer McGrath, 9072690298 jennifer.mcgrath@alaska.gov
Latitude: 64.199748
Longitude: -147.933985
Horizontal Datum:WGS84

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

Updated January 2022 ADEC informed 5/4/89 of a small landfill that is a potential contaminated site at an radio relay station that was operated from 1959 to 1982. POL and batteries were reportedly disposed at the landfill, which was operated from 1959-1976 by the USAF and from 1976 to 1982by Alascom. Two 14,000 gallon diesel tanks cut open and buried on site. No sampling at tank excavation site. Residences located within 1 mile. Extent of contamination unknown. Cross reference file 150.23.005 and 150.15.006. Landfill (IRP site LF002) located on private property. Located 45 miles south of Fairbanks. Groundwater at 29 - 34' and facility 4500' from Gold King Creek. Former White Alice site (IRP site OT001) declared excess in 1983. State wants to acquire Air Force improvements. Land at the site is owned by state of Alaska. Air Force needs to do an asbestos assessment and additional site cleanup before state will accept property. DSMOA site. Permit # 8731-BA006. (rpltr8). The sites are assigned HIGH overall risks on the Air Force Relative Risk Evaluation Worksheets dated 9/12/95. The worksheets indicate that there are high quality wetlands adjacent to the sites. Site access by humans and animals is unlimited. Moose and large numbers of waterfowl are observed in the area; moose droppings have been observed within 10 feet of soil staining. Local residents (approximately 5) are also known to frequent the area. August 2021- USACE-FUDS stated the site was transferred in time to qualify as a FUDS. The site was operated as a Government Owned Contractor Operated (GOCO) radio relay facility.

Action Information

Action Date Action Description DEC Staff
6/1/1987 Interim Removal Action Approved (Old R:Base Action Code = REM - Removal / Excavation). Air Force removed batteries, transformers, capacitors, waste drums and excavated and drained two 14,000 gallon diesel tanks. Tanks cut open; fuel lines and contaminated soils were placed within and tanks buried. Samples of stained soils and waste oil field-tested for PCBs and proved negative for PCBs, toluene, and xylene. Samples taken from front area of facility and gate area. Sampling of tank excavation apparently not conducted. Former Staff
7/12/1988 Preliminary Assessment Approved Dynamac Corporation concluded that small quantities of hazardous materials were handled at site. Underground storage tanks containing diesel fuel, also batteries, and electrical equipment possibly containing PCBs present at site. No visible evidence of contamination found. Potential contaminated site identified as Site Number 1, a small unlined landfill located outside the fence line east of facility covered with 4 - 6' of soil. HARM rating = 49. Landfill privately owned. Residences within 1 mile. Drinking water source unknown, but assumed to be groundwater aquifer. Recommended site investigation be conducted. Former Staff
9/15/1991 Site Added to Database Landfill at RRS. Former Staff
9/15/1991 Site Ranked Using the AHRM Attempted ranking. Former Staff
7/16/1992 Update or Other Action (Old R:Base Action Code = RECN - Site Reconnaissance (CS)). Conducted a site inspection with Air Force staff. No significant contamination issues noted. Laura Noland
11/15/1993 Site Ranked Using the AHRM Reranked. Former Staff
5/27/1994 Update or Other Action (Old R:Base Action Code = RPL2 - Site Information Request Letter). Sent a PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. Jeff Peterson
3/24/1997 Update or Other Action Site updated by Shannon and Wilson, based on the Air Force Relative Risk Evaluation Worksheet dated 9/12/95. The White Alice Site and Landfill were not assigned separate Reckey numbers due to the limited investigation conducted to date. S&W
11/19/1999 Update or Other Action Site is believed by Air Force to have minor contamination, and may not require any cleanup. Comprehensive site survey for asbestos, leaded paint, and PCBs, and a document review are scheduled for 2000. Tamar Stephens
3/2/2001 Update or Other Action File number updated from 150.23.005 to 150.38.029. Mitzi Read
6/16/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Tamar Stephens
8/10/2015 Update or Other Action Reviewed DSMOA and this site is not on the list for ACOE work in FY15 & 16. Reviewed file and sent up recommendation to ACOE and DOD Program Manager to include this site on attachment A for DSMOA. PA and site assessment is required. Fred Vreeman
11/28/2016 Update or Other Action DEC sent a request for site characterization for this site to the USACE FUDS program. According to DEC review, a management action plan was completed for the site, though site characterization and remediation activity apparently ended following the completion of a joint execution plan in 1999. Monte Garroutte
10/4/2018 Update or Other Action Inquiry/status update made to ADOT&PF in September 2018. ADOT not able to address the issue without an agreement with DEC in place. DEC is in the process of finalizing an MOA with DOT. This MOA will be the framework on how we address DOT sites like these. DOT currently has over 100 sites. Once the MOA is finalized, we will send a formal PRP letter to DOT for all these sites where they are an PRP. We will then prioritize field work at these sites based off risk, public concern, economy of scale, and/or other factors. John O'Brien
8/12/2019 Update or Other Action The U.S. Army Corps of Engineers has confirmed this site is a formerly used defense site (FUDS), and indicated via email on 12 August 2019 they are developing a preliminary assessment, to be completed in 2020. Melinda Brunner
10/11/2021 Potentially Responsible Party/State Interest Letter Letters sent to AT&T and USACE Shonda Oderkirk

Contaminant Information

Name Level Description Media Comments

Control Type

Type Details

Requirements

Description Details

There are no documents for this site report.