Action Date |
Action |
Description |
DEC Staff |
4/15/1988 |
Update or Other Action |
(Old R:Base Action Code = SI - Site Investigation). Air quality study by NORTECH concluded that furnace was leaking across heat exchanger resulting in combustion gases indoors. Presence of formaldehyde above recommended levels also indicated. |
Former Staff |
2/13/1989 |
Update or Other Action |
(Old R:Base Action Code = SI - Site Investigation). Soil quality investigation by Shannon and Wilson included two soil borings. Analyses of soil samples detected up to 1000 ppm TPH near tank location. No purgeable aromatics detected. |
Former Staff |
5/12/1989 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Cleanup plan for contaminated soil submitted. Proposed removal of soil from site to borough landfill, where it would be allowed to aerate. |
Former Staff |
5/24/1989 |
Update or Other Action |
(Old R:Base Action Code = RAPR - Remedial Action Plan Review (CS)). Second remediation plan proposed for contaminated soil. Two alternatives included spreading soil over new church parking lot or over H&H road project. |
Former Staff |
6/1/1989 |
Interim Removal Action Approved |
(Old R:Base Action Code = REM - Removal / Excavation). Heating oil tank and approximately 10 cubic yards of contaminated soil removed. Performed during June 1989. |
Former Staff |
6/1/1989 |
Update or Other Action |
(Old R:Base Action Code = F - Site Treatment, Soil/H2O). Passive vapor extraction system installed with pea gravel on bottom of the hole. An active system can be instituted by applying a vacuum to the system. Performed during June 1989. |
Former Staff |
6/2/1989 |
Update or Other Action |
(Old R:Base Action Code = FI - Field Inspection (General)). Site visit by R. Little, J. Janssen, and B. Thomas. HNu readings from several hand-dug holes ranged from 1 to 11 ppm. No vapor levels above 1 ppm except where holes were dug. |
Ben Thomas |
7/24/1989 |
Update or Other Action |
(Old R:Base Action Code = FI - Field Inspection (General)). Site visit by B. Thomas to inspect remediation work. |
Ben Thomas |
5/30/1990 |
Site Number Identifier Changed |
Old Reckey 198931011111. |
Former Staff |
12/10/1990 |
Site Ranked Using the AHRM |
Initial ranking. |
Former Staff |
1/9/1994 |
Update or Other Action |
(Old R:Base Action Code = RPL2 - Site Information Request Letter). Sent PRP-CS Database Notification Letter to RP requesting update and more environmental information concerning contaminated site. RP received letter, but as of this "complete date" no response from them. |
Jeff Peterson |
1/25/1994 |
Site Added to Database |
Fuel oil. |
Former Staff |
2/7/1995 |
Update or Other Action |
SITE SUMMARY: Leaking HOT removed in 1988. Soils were supposedly removed and treated as hot asphalt in 1989. Review file and check fate of soils. Site may qualify for NFA. |
Cindy Thomas |
2/4/1997 |
Interim Removal Action Approved |
(Old R:Base Action Code = REM - Removal / Excavation). Removal of contaminated soil and steam cleaning of basement wall. Inaccurate date entered because there was no actiondt. Action date reflects date actiondt was entered. |
Former Staff |
3/2/2001 |
Update or Other Action |
File number updated from 102.02.050 to 102.38.079. |
Mitzi Read |
7/10/2002 |
GIS Position Updated |
Changed the Latitude, Longitude, Method Accuracy, Accuracy and Unit fields. |
Heather Goldman |
5/12/2008 |
Exposure Tracking Model Ranking |
Initial ranking with ETM completed. |
Neal Everson |
3/12/2013 |
Update or Other Action |
Site symbol visually relocated using ArcGIS.com, Bing satellite imagery and documents from the file. |
Laurel Gale |
3/12/2013 |
Update or Other Action |
File reviewed by DEC staff to determine workload priority. |
Laurel Gale |
6/8/2016 |
Potentially Responsible Party/State Interest Letter |
PRP letter sent to the Friendship Baptist Mission. |
Janice Wiegers |
6/8/2016 |
Update or Other Action |
Letter sent to Friendship Baptist Mission indicating the site is still active and requesting a response by July 15. |
Janice Wiegers |
7/14/2016 |
Update or Other Action |
Contacted by a local church representative regarding letter sent on 6/8/16. The church representative indicated that the Southern Baptist Convention Home Mission Board owned the church and that the church leadership believed that the spill had been taken care. He said contaminated dirt had been removed by H&H Contractors and taken to ESI for thermal treatment. The representative supplied several names of people that were around during the spill. According to the representative, no odors are present now. The building was formerly a parsonage but has been sold. |
Janice Wiegers |
8/5/2016 |
Potentially Responsible Party/State Interest Letter |
PRP letter sent to current property owners. Additional letter requesting that owners contact DEC as DEC would like to inspect the site and discuss options for site closure. No phone number available for current owners. |
Janice Wiegers |
8/10/2016 |
Update or Other Action |
Received call from current property owner; arranged site visit for next week. Owner said he was not aware of the contaminated site issues at the property when he purchased it. |
Janice Wiegers |
8/17/2016 |
Site Visit |
Met current property owner at site to evaluate the condition of the basement with a Photoionization Detector and to see if passive ventilation piping was still in place. The piping was present, although only one end was visible (attached to building). It is assumed that the rest of the piping is still in place in the ground. PID readings were low in the house and basement. |
Janice Wiegers |
2/13/2017 |
Update or Other Action |
DEC received call from trustee at Friendship Baptist Mission requesting information on status of site. Discussed site visit last summer and evaluation for possible site closure. |
Janice Wiegers |
7/27/2017 |
Update or Other Action |
Contacted trustee regarding status of closure. The closure letter is being drafted and has been preliminary approved by DEC management. |
Janice Wiegers |
7/27/2017 |
Update or Other Action |
|
Janice Wiegers |
9/13/2017 |
Institutional Control Record Established |
Institutional Controls established and entered into the database. |
Former Staff |
9/14/2017 |
Cleanup Complete Determination Issued |
Site closed based on evaluation of file, groundwater data from adjacent site, and site inspection to determine if any concern remained about petroleum vapor intrusion. |
Janice Wiegers |