Skip to content Skip to content

Site Report: Municipal Light & Power, Plant No. 2, Spill 1

Site Name: Municipal Light & Power, Plant No. 2, Spill 1
Address: 8670 Glenn Highway, Frontage Road, Anchorage, AK 99504
File Number: 2100.38.356
Hazard ID: 9
Status: Cleanup Complete - Institutional Controls
Staff: IC Unit, 9074655229 dec.icunit@alaska.gov
Latitude: 61.230833
Longitude: -149.713889
Horizontal Datum:

We make every effort to ensure the data presented here is accurate based on the best available information currently on file with DEC. It is therefore subject to change as new information becomes available. We recommend contacting the assigned project staff prior to making decisions based on this information.

Problems/Comments

A transformer oil spill of "several hundred gallons" occurred in the 1970's when vandals shot a transformer. The location was evaluated during a transformer upgrade in 2002 and soils impacted by oil were removed; PCBs were not present in the soils.

Action Information

Action Date Action Description DEC Staff
6/13/2002 Update or Other Action Approved request of 6/12/2002 to transport and thermally remediate approximately 170 cubic yards of contaminated soil. Eileen Olson
6/26/2002 Update or Other Action Received a site characterization report dated June 17, 2002 for transformer upgrade. No PCBs detected but excavation sidewall samples showed that DRO concentrations are elevated, with the maximum result 5,550 mg/kg DRO. Conclusions propose borings to characterize contamination. Eileen Olson
12/30/2002 Update or Other Action ADEC received a letter report on December 30, 2002 indicating that the soil had been successfully remediated and would be used in the construction industry. Prior to disposal the soil was in two separate stockpiles. Both stockpiles (approximately 180 cubic yards) were sent to ASR. Beatrice Egbejimba
12/31/2002 Site Characterization Report Approved Letter sent to Lena Saville of Municipal light and Power with information regarding ADEC's approval of report and a request for additional site characterization of the north sidewall of the excavation. The report describes a previous field investigation involving the upgrade of an 8,000-gallon transformer that is located in an area of known transformer oil spills that may have contained polychlorinated biphenyls (PCB). Transformer No. 5 was temporarily relocated while a secondary containment basin was constructed and impacted soil removed from its former location. The confirmation sample results identified a maximum concentration of 5,550 mg/Kg diesel-range organic (DRO) hydrocarbons and 724 mg/Kg residual-range organic (RRO) hydrocarbons remaining in the northern sidewall of the transformer upgrade excavation. PCBs were not detected in any of the confirmation samples. Approximately 180 cubic yards of soil and 35 cubic yards of concrete was excavated and sent to Alaska Soil Recycling in June for thermal remediation. Beatrice Egbejimba
12/31/2002 Update or Other Action ADEC sent state letter of interest. Beatrice Egbejimba
1/6/2003 Update or Other Action Site address is 8670 Glenn Highway, Anchorage, 99504, based on information provided by Lena Saville. Database updated to reflect new information. Beatrice Egbejimba
2/5/2003 Update or Other Action ADEC met with Lena Saville of ML&P to discuss proposal for a work plan. Beatrice Egbejimba
2/6/2003 Update or Other Action ADEC visited site with Lena Saville of ML&P to discuss the possible use of data from on-site wells (MWB10 and B6). After the site visit it was agreed that site conditions were not similar and a work plan with inferred data from MWB10 and B6 would not be acceptable. Beatrice Egbejimba
2/26/2003 Site Added to Database Spill date uncertain but the year of the spill is correct. Former Staff
3/6/2003 Update or Other Action ADEC received site characterization work plan. The work plan proposes to install a monitoring well adjacent to the location with the highest concentration of DRO identified during the 2002 investigation. Beatrice Egbejimba
3/25/2003 Update or Other Action ADEC sent letter to Lena Savile of ML&P with approval of site characterization work plan. Beatrice Egbejimba
5/20/2003 Update or Other Action ADEC sent approval letter regarding Additional Environmental Assessment report to Lena Savile of ML&P. Additional wellls were requested to delineate the nature and extent of groundwater contamination at the site. A work plan is requested by June 24, 2003. Beatrice Egbejimba
6/11/2003 Update or Other Action Staff received a report entitled "August 2001 Environmental Assessment Report, plant Two, Unit *, Pipeline Closure” and a work plan entitled “Corrective action Plan” from former PM. The August 2001 Environmental Assessment, documents a field activity in which two soil samples were collected and analyzed at 5 to 7 feet and 7.5 to 9.5 feet from Boring B1. A maximum concentration of 1330 mg/kg DRO was reported at 7.5 to 9.5 feet. A corrective action plan (CAP) was submitted to DEC for approval in October 2001. No documentation of CAP approval letter was found in file. Beatrice Egbejimba
6/17/2003 Update or Other Action ADEC received work plan to install 2 additional monitoring well in the visinity of tranformer #5. Beatrice Egbejimba
6/19/2003 Meeting or Teleconference Held ADEC met with Lena Savile of ML&P to discuss proposed work plan received June 17, 2003. The work plan proposes to install two additional wells adjacent to the transformer. Based on two reports received from former project manager on 6/11/03, staff advised ML&P to relocate one monitoring well. Reports indicate that contaminated soil is present adjacent to Unit 8. Unit 8 is in close proximity to transformer #5 and contaminated soil from this area may be contributing to the high level of DRO in the groundwater. It was agreed that a well will be installed in the approximate location of Boring B1. Boring B1 was advance by Shannon & Wilson during an investigation in 2001. A maximum concentration of 1330 mg/kg DRO was reported at 7.5 to 9.5 feet. A revised work plan to investigate the groundwater beneath this area will be submitted for ADEC’s approval. Beatrice Egbejimba
6/24/2003 Update or Other Action ADEC revised workplan for the investigation of groundwater beneath transformer #5 and unit 8 areas. Beatrice Egbejimba
6/26/2003 Update or Other Action ADEC sent letter to Lena Savile of ML&P with approval of work plan for the installation of monitoring wells MW2 and MW3. ADEC suggested that MW 2 be relocated further up gradient of its current location, so that the groundwater direction can be more accurately determined. If relocation is not feasible because of underground utilities or other constrains the current location is acceptable. A report should be submitted by September 1, 2003. Beatrice Egbejimba
9/5/2003 Update or Other Action ADEC sent letter to Lena Savile of Municipal Light & Power Plant with information regarding report received 9/4/03. The report provided information regarding the installation and sampling of monitoring wells MW-2 and MW-3 and sampling of previously existing MW-1. The report shows that monitoring well MW1 has shown an increase since the April 2003 groundwater monitoring event from 3.80mg/ L diesel-range organics (DRO) and 2.62 mg/L residual-range organics (RRO) to 9.40mg/L DRO and 6.18 mg/L RRO. Results obtained from the newly installed groundwater monitoring wells MW-2 and MW-3 did not indicate the presence of any contaminant of concerns above the applicable groundwater cleanup level of 1.5 mg/L DRO and 1.1 mg/L RRO. However, impacted soil above the applicable cleanup level of 250 mg/kg DRO was encountered during the installation of monitoring well MW-3. 956mg/kg DRO was the maximum concentration reported. This soil sample was collected at a depth of 15 -17 feet below ground surface (bgs). Groundwater was encountered at 23.5 feet bgs with no detectable concentration of DRO at the groundwater interface. Based on the information provided in the report ADEC has determined that quarterly groundwater monitoring is necessary to establish the concentration trend. A workplan indicating a schedule was requested by ADEC by September 30, 2003. Beatrice Egbejimba
9/5/2003 Long Term Monitoring Established Decision was based on the information provided in the Additional Site Characterization of the Transformer No. 5 and Unit No. 8 Area, Plant 2 report received by ADEC on 9/4/03. Beatrice Egbejimba
9/17/2003 Update or Other Action ADEC approved work plan for quarterly monitoring of the three wells associated with the impacted groundwater in the transformer area. Beginning September 2003, these wells will be monitored for DRO and RRO. A report was requested within 60 days of completing site characterization activities. Beatrice Egbejimba
10/20/2003 Update or Other Action ADEC received September 2003 Groundwater Monitoring report. Beatrice Egbejimba
10/27/2003 Institutional Control Record Established Institutional Controls established and entered into the database. Bill O'Connell
10/27/2003 Cleanup Complete Determination Issued The Alaska Department of Environmental Conservation, Contaminated Sites Program (ADEC) has completed review of the environmental records associated with the ML&P Plant 2, Spill 1, located at 8670 Glenn Highway in Anchorage. Based on this information, the ADEC has determined a Cleanup Complete Determination with Institutional Controls shall be granted. The hazardous substance contamination has been adequately addressed and does not pose an unacceptable risk to human health or the environment. (This action entered 9/17/09) Bill O'Connell
2/5/2004 Update or Other Action File number changed from CS69.28-1 to 2100.38.356. Sarah Cunningham
8/24/2004 Meeting or Teleconference Held CSP staff met with Lena Savile of ML&P to discuss the recent excavation around a key box near the formerly identified contamination. The excavation around the key box removed DRO contaminated soil that was estimated to be part of the previously identified contamination and the result of the 1964 earthquake. Soil was stockpiled nearby and the highest DRO level was measured at 1,600 mg/kg. Options were discussed how to address the contamination. ML&P will provide a workplan to CSP for review. It is possible that ML&P may propose a Method 3 determination or higher levels of contamination be excavated and landfarmed on the property coupled with monitoring. Rich Sundet
9/2/2004 Update or Other Action On 9/2/04, DEC approved ML&P's 9/2/04 request to transport about 10 cubic yards of DRO contaminated soil excavated from around a waterline keybox to ASR for thermal treatment. The soil was generated during parking lot improvements at Plant 2 north of Unit 8. Rich Sundet
6/13/2008 Exposure Tracking Model Ranking Initial ranking with ETM completed. Eileen Olson
7/21/2008 Document, Report, or Work plan Review - other Reviewed July 2008 Groundwater Monitoring Report. Samples were collected from wells MW-1, MW-2, and MW-3 on two occasions in 2008 and analyzed for DRO and RRO. Only RRO was detected above the clenaup level on one occasion in MW-1 at 1.34 mg/l. Bill O'Connell
9/18/2009 Document, Report, or Work plan Review - other Reviewed January 2009 Groundwater Monitoring Report. Samples were collected from wells MW-1, MW-2, and MW-3 in January 2009 and analyzed for DRO and RRO. Contaminants were not detected above cleanup levels. Bill O'Connell
9/21/2009 Document, Report, or Work plan Review - other Reviewed July 2009 groundwater monitoring report. Samples were collected from MW1, MW2, and MW3. Contaminants were not detected above cleanup levels. Bill O'Connell
9/22/2009 Update or Other Action Based on recent data, groundwater monitoring is no longer required at this site. All other conditions of the closure decision remain in effect. Bill O'Connell
10/12/2009 Document, Report, or Work plan Review - other Monitoring well decommissioning report received. MW-2 and MW-3 were decommissioned in accordance with ADEC guidance, MW-1 was in an area of overhead utilities so the well casing was cut off 2.5 feet below ground surface and filled with bentonite. Bill O'Connell

Contaminant Information

Name Level Description Media Comments
DRO Between Method 2 Migration to Groundwater and Human Health/Ingestion/Inhalation Soil

Control Type

Type Details
Other CS database notation and letter to landowner/RP (added during a QC check 4/9/2014).

Requirements

Description Details
Advance approval required to transport soil or groundwater off-site.
Groundwater Monitoring Semi-annual groundwater monitoring required

No associated sites were found.

Missing Location Data

Because the GIS location data for this site has not been entered, we cannot direct you to its position on the map. Click "Continue" to proceed to the Contaminated Sites Web Map or "Close" to return to the site report.
Continue     Close