Action Date |
Action |
Description |
DEC Staff |
4/29/1993 |
Update or Other Action |
(Old R:Base Action Code = RARR - Remedial Action Report Review (CS)). |
Former Staff |
8/26/1993 |
Site Added to Database |
|
Former Staff |
11/10/1994 |
Site Ranked Using the AHRM |
Inigtial ranking. |
Former Staff |
7/5/1996 |
Site Characterization Report Approved |
GeoEngineers impound basin soil sampling report. |
Bill Janes |
7/16/1996 |
Site Characterization Workplan Approved |
GeoEngineers assessment of soil in the base of the tank farm prior to installation of new liner. |
Bill Janes |
9/25/1996 |
Site Characterization Report Approved |
Tank farm soil assessment report - GeoEngineers. |
Bill Janes |
10/21/1996 |
Site Ranked Using the AHRM |
Re-ranking based on new information. |
Bill Janes |
10/25/1996 |
Site Characterization Workplan Approved |
Removal and treatment of petroleum contaminated sediments in impound basin. |
Bill Janes |
9/15/1997 |
Update or Other Action |
Date approximate - TOSCO purchased facility from Unocal. |
Bill Janes |
5/14/1998 |
Meeting or Teleconference Held |
Site visit. |
Bill Janes |
6/16/1998 |
Cleanup Level(s) Approved |
ACLs approved using draft regulations. |
Bill Janes |
7/2/1998 |
Site Characterization Workplan Approved |
GeoEngineers - monitoring and sampling support during placement of the secondary containment liner. |
Bill Janes |
1/22/1999 |
Update or Other Action |
Status report letter from TOSCO. |
Bill Janes |
3/2/1999 |
Meeting or Teleconference Held |
Teleconference - Sub drain liner sampling being conducted monthly. Down to < 1 ppb PAHs. Basically drinking water clean. Will continue monthly but may request quarterly monitoring soon. Tesoro planning to start back on liner installation in April. Stockpiled soil - high fine content. Tesoro does not want it back in tank farm. Looking into mixing with gravel material to add consistency. Sitting on top of impermeable liner may not allow it to ever dry out. TOSCO may eventually haul the rest of the stockpiled soil to Rabanco. 300 cubic yards approximately taken there last October. Dames and Moore supposed to be giving Marty Cramer a report on confirmation monitoring and sampling. |
Bill Janes |
9/24/1999 |
Meeting or Teleconference Held |
Progress teleconference - About 500 cubic yards of soil meeting cleanup criteria was placed on top of new liner. Other 500 yards may be sent south because there is no more room for onsite disposal. Sampling beneath stockpiles shows levels slightly above cleanup level. Report expected from Noll Environmental soon. Marty Cramer still has to make some corrections to the Dames and Moore report before sending it to us. Facility upgrade is complete. Subdrain sampling ND. Marty will be sending an NFA request letter and referenced reports soon. |
Bill Janes |
11/22/1999 |
Meeting or Teleconference Held |
Progress teleconference - Report and NFA request expected mid January. |
Bill Janes |
9/8/2000 |
Update or Other Action |
Project closure site visit with Marty Cramer of Tosco |
Bill Janes |
11/1/2000 |
Conditional Closure Approved |
No Further Remedial Action Planned as of this date. Letter is at: G:\SPAR\Spar-Contaminated Sites\SITES\Ket Tank Farm Decision Documentation.doc.
Also in Juneau reading file this date. |
Bill Janes |
11/1/2000 |
Institutional Control Record Established |
Controls are those adopted by reference in the ROD as part of the facility's contingency plan. |
Bill Janes |
1/3/2001 |
Update or Other Action |
$1,288.26 cost recovery check received by Law. |
Bill Janes |
5/23/2001 |
Update or Other Action |
$182.98 CR check received. |
Bill Janes |
10/2/2012 |
Institutional Control Update |
Database reminder system initialized in order to perform an IC review to see if ICs are still protective. |
Evonne Reese |
12/2/2014 |
Institutional Control Update |
Verified that there is a current contingency plan for the operations on this property. The current C-plan is under the name Petro Marine. |
Evonne Reese |
12/14/2018 |
Institutional Control Compliance Review |
A compliance review was conducted and I verified with DEC - Prevention, Preparedness, and Response that there is a current Contingency Plan in place for the Petro Marine Ketchikan facility. The Plan ID is 1014 and it is approved thru 3/26/2023. |
Evonne Reese |