8 Star Alaska LLC Gas Treatment Plant PSD Permit Construction Extension

8 Star Alaska LLC is proposing to construct the Gas Treatment Plant (GTP) located on Alaska’s North Slope in the Prudhoe Bay Unit (PBU), approximately 8.5 miles north-northwest of Deadhorse. The GTP is part of one integrated liquefied natural gas (LNG) project to bring natural gas from Alaska’s North Slope to international markets in the form of LNG, as well as for in-state deliveries in the form of natural gas. The GTP will take gas from the PBU and the Point Thomson Unit (PTU) and treat/process the gas, before it is sent 807 miles through a 42-inch diameter pipeline to the Liquefaction Facility in Nikiski on Alaska’s Kenai Peninsula for export in foreign commerce.

Construction Permit No. AQ1524CPT01 issued on August 13, 2020 authorized the installation of twelve (12) cogeneration gas-fired turbines for compression with supplemental firing duct burners and waste heat recovery units, six (6) simple cycle gas-fired turbines for power generation, eight (8) gas-fired heaters, one (1) black start diesel-fired engine generator, three (3) diesel-fired firewater pump engines, two (2) diesel-fired emergency generators, and eight (8) natural/process gas flares. Construction never commenced under Construction Permit No. AQ1524CPT01 and the deadline to begin construction under both the permit and extensions were not met. Subsequently, an application for Construction Permit No. AQ1524CPT02 was submitted on February 11, 2025, to update certain elements of the original application with more timely information.

For additional information please contact Dave Jones at 907-465-5122 or at dave.jones2@alaska.gov

Date Title and Document Download Category Program
6/18/2021 Alaska LNG Gas Treatment Construction Air Permit AQ1524CPT Extension Update (PDF 267K) Extension AGDC
3/26/2021 Gas Treatment Plant Air Permit Extension Letter (PDF 77K) Extension AGDC
2/11/2022 AQ1524CPT01 Extension Approval Letter (PDF 263K) Extension ADEC
5/12/2023 AQ1524CPT01 Alaska LNG Gas Treatment Plant Permit extension Request (PDF 138K) Extension AGDC
6/16/2023 AQ1524CPT01 2nd PSD Extension RBLC Search Email (PDF 359K) Extension AGDC
6/16/2023 AQ1524CPT01 2nd PSD Extension Supporting Materials Email 061623 (PDF 509K) Extension AGDC
5/31/2023 AGDC GTP Permit Extension Information Request (PDF 1.3M) Extension AGDC
7/14/2023 AQ1524CPT01 2nd PSD Extension Approval Letter (PDF 285K) Extension ADEC
7/14/2023 15210 Large Combined Cycle Turbines (XLS 144K) Extension ADEC
7/14/2023 15.110 Large Simple Cycle Turbines (XLS 51K) Extension ADEC
5/8/2025 AQ1524CPT01 Third PSD Extension Approval Letter Corrected (PDF 302K) Extension ADEC
2/11/2025 AQ1524CPT02 Application GPT Construction Cover Letter Application Form (PDF 900K) Application AGDC
2/11/2025 AQ1524CPT02 Application Attachment 1 Reference Information (PDF 183K) Application AGDC
2/11/2025 AQ1524CPT02 Application Attachment 2 GTP BACT Analysis (PDF 2M) Application AGDC
2/11/2025 AQ1524CPT02 Attachment 4 Existing ADEC Permit (PDF 1.8M) Application AGDC
5/8/2025 AQ1524CPT01 Cover Ltr Third PSD Extension Approval 05082025 (PDF 341K) Extension ADEC
5/14/2025 AKLNG Transmittal AQ1524CPT02 Modified Files Public Use (PDF 2M) Application AGDC
9/22/2025 Source Impact Modeling Analysis GTP PSD Construction Permit AQ1524CPT02 (PDF 425K) Application AGDC
3/27/2026 Information Request Response 03272026 Addendum to 03242026 Response (ZIP 3M) Information Request 8 Star Alaska LLC
3/24/2026 Information Request Response 03.24.26 (ZIP 8.3M) Information Request 8 Star Alaska LLC
12/3/2025 AQ1524CPT02 Information Request 12.03.2025 (DOC 300K) Information Request ADEC
11/17/2025 AQ1524CPT02 Information Request 11.17.2025 (PDF 159K) Information Request ADEC